Viability Gap Funding (VGF) Scheme
This section contains list of PPP projects granted final approval by the Empowered Institution (EI)/Empowered Committee (EC)under the Scheme for Financial Support to PPPs in Infrastructure (VGF Scheme).
Export to Excel
Sr No. | Project Name | Location | Sector | Total Project Cost (In Rs. Crore) | VGF Approved (in Rs. Crore) | In Principle Approval | Final Approval | Implementing Authority |
---|---|---|---|---|---|---|---|---|
1 | Development of a 400 kV Bikaner Sikar D/C Power Transmission Line for evacuation of power from wind and solar power in Rajasthan | Rajasthan | Power | 260.00 | 28.80 | 19 Dec 2014 (61th EI) | 17 May 2016 (71st EI) | Rajasthan Rajya Vidyut Prasaran Nigam Limited |
2 | 4-laning of Muzaffarnagar - Saharanpur Road (SH-59) from Km.0.000 to Km.52.950 on Design, Build, Finance, Operate and Transfer (DBFOT) toll basis | Uttar Pradesh | Roads | 752.88 | 150.58 | 23 Dec 2014 (22nd EC) | 03 Jan 2017 (28th EC) | Uttar Pradesh State Highways Authority |
3 | Development of road from NH-63 near Ginigere-Gangavathi to Sindhanur | Karnataka | Roads | 190.16 | 4.59 | 06 Jan 2012 (37th EI) | 08 Apr 2016 (70th EI) | Karnataka Road Development Corporation Limited (KRDCL) |
4 | Development of Sinnar-Nashik section of NH-50 (from km 177.0001 to 201.350) in the State of Maharashtra with 4-lane through DBFOT IBOT (Toll)] basis. | Maharashtra | Roads | 312.96 | 62.59 | 01 Dec 2011 (36th EI) | 06 Oct 2016 (74th EI) | Public Works Department, Government of Maharashtra |
Total | 1,516.00 | 246.56 |