This Report provides information on infrastructure projects implemented by the Government on PPP basis across pre-defined set of parameters and following coverage criteria:
Export to Excel

Projects that were either under 'Pre-construction Stage', 'Under Construction' or 'Operation and Maintenance Stage' as on April 1, 2011 or 'Awarded' thereafter and with Project Cost >INR 5 crore.

Please click on project name for more details of the project.

  • No. of Projects in this Report: 1883
  • Total Project Cost(in Rs Crore): 2,495,568.44
Sr No. Project Name Project Capacity Total Project Cost (In Rs.Crore) Sector Sub-Sector Status Project Authority Location Update Date
1 Community Shopping Facilities at Jharpada, Bhubaneswar on DBFOT mode 3 to 4 acres have been identified in each of the BMC zones i.e in the North, South-East and South-West zone of BMC 350 Social and Commercial Infrastructure Tourism Pre-construction stage Bhubaneswar Development Authority Odisha
2 Development of Bio-CNG Plants in Bhubaneswar in DBFOT mode 4 numbers of 50TPD 120 Water Sanitation Solid Waste Management Pre-construction stage Housing and Urban Development - Bhubaneswar Muncipal Corporation Odisha
3 Captive Jetty at Jatadhar Muhana in Jagatsinghpur District on BOOST basis Not Available 2104 Transport Ports Pre-construction stage Directorate of Ports & I.W.T, Odisha Odisha
4 Setting up of Intra State Connectivity (8 airstrips) of Airports within the state of Odisha under Regional Connectivity Scheme (RCS) in PPP mode category 1A < 9 passenger seating capacity Category 1: 9 - 20 - Transport Airports Pre-construction stage Commerce and Transport Department Odisha
5 Setting up of Electric Vehicle Charging Stations (EVCS) on PPP Mode at Various Locations in Bhubaneswar & Puri 83 locations across Odisha 25 Transport Urban public transport Pre-construction stage Commerce and Transport Department Odisha
6 Automated Driving Testing System (ADTS) @ 30 locations 30 locations across Odisha 167 Transport Urban public transport Pre-construction stage Commerce and Transport Department Odisha
7 Automated Testing Stations (ATS) 38 locations across Odisha 42 Transport Urban public transport Pre-construction stage Commerce and Transport Department Odisha
8 Development of Truck Terminals in various Districts of Odisha 25 locations across Odisha 396 Transport Urban public transport Pre-construction stage Commerce and Transport Department Odisha
9 Development, Operation and Maintenance of Shri Jagannath International Airport on PPP mode at Puri Not Available 2230 Transport Airports Pre-construction stage Commerce and Transport Department Odisha
10 Development of Silk (Ahimsa) Spinning mill in PPP mode 3000 Spindles 400 Social and Commercial Infrastructure Handlooms & Textiles Pre-construction stage Handlooms, Textiles and Handicrafts Department Odisha
11 Upgradation of Toy Train Service at Nandankanan Zoological Park into an engaging, educative, and attractive package through PPP mode 1.6 kilometers 15 Social and Commercial Infrastructure Tourism Pre-construction stage Forests, Environment and Climate Change Department Odisha
12 Selection of Operator for Operating, Maintaining & Managing - six State Government Testing Laboratories (at Cuttack, Angul, Berhampur, Rourkela, Bolangir and Balasore) on Public Private Partnership (PPP) Mode Cuttack- 42120 sq ft plot Angul - 19776 sq ft plot Berhampur - 15899 sq ft plot Rourkela - 68400sq ft plot Bolangir - 11979 sq ft plot Balasore - 15000 sq ft plot - Social and Commercial Infrastructure Common infrastructure for industrial parks, SEZ Pre-construction stage MSME Department Odisha
13 Construction of Godowns ( 10000MT each) through Private Entrepreneurs Guarantee (PEG) Scheme 4,00,000 MT (40 locations of 10,000MT each) 400 Social and Commercial Infrastructure Post-harvest storage infrastructure for agriculture and horticulture produce including cold storage Pre-construction stage Odisha State Civil Supply Corporation Ltd. Odisha
14 Government Industrial Training Institutes (ITIs) at Patnagarh in Bolangir and Athamalik in Angul for running in Private Training Partner (PTP) mode Bolangir - 208 seats Angul - 248 seats Social and Commercial Infrastructure Education Pre-construction stage Skill Development and Technical Education Department Odisha
15 Farmer Skill and Agri-Incubation Centre Not Available 150 Social and Commercial Infrastructure Education Pre-construction stage Department of Agriculture and Farmer's Empowerment Odisha
16 Agri-Tech Smart Farm (ATSF) at Puri, Sukinda, Similiguda under PPP mode Not Available 200 Social and Commercial Infrastructure Agriculture and horticulture Pre-construction stage Department of Agriculture and Farmer's Empowerment Odisha
17 Production of non-paddy seeds by the Seed Producing Agencies in selected Government Agricultural Farms of Directorate of Agriculture through PPP mode 42 farms in 4 clusters Cluster 1 : 120.44 ha Cluster 2: 194.8 ha Cluster 3: 284.95 ha Cluster 4: 101.5 ha - Social and Commercial Infrastructure Agriculture and horticulture Pre-construction stage Department of Agriculture and Farmer's Empowerment Odisha
18 Joda - Bamberi Road Corridor Not Available 221.87 Transport Roads and bridges Under Construction Works Department Odisha
19 Angul- Duburi- Sukinda- Rail Link 95 kilometer 3602 Transport Railway track, tunnel, viaducts, bridges Under Construction Works Department Odisha
20 Subarnarekha Port Not Available 5000 Transport Ports (excluding captive) Under Construction Directorate of Ports & I.W.T, Odisha Odisha
21 Astaranga Port Not Available 7417 Transport Ports (excluding captive) Under Construction Directorate of Ports & I.W.T, Odisha Odisha
22 Development of Integrated Residential Complex at Paikarapur, Bhubaneswar by BDA 9.775 Acres =153.9 Social and Commercial Infrastructure Housing Under Construction Housing and Urban Development Department and Bhubaneswar Development Authority Odisha
23 Affordable housing project under model 3 of "Policy on Housing for All in Urban Areas" 2015 (at Chhend, Rourkela) 500 EWS units over 3.30 acres 45 Social and Commercial Infrastructure Housing Under Construction Housing and Urban Development Department Odisha
24 Affordable Housing Project (AHP) as per provisions of Model-Ill under Policy on Housing for all in Urban Areas, Odisha-2015 (at Naranpur Cuttack) 550 EWS unit 320 LIG units over 8 acres 88.31 Social and Commercial Infrastructure Housing Under Construction Housing and Urban Development Department Odisha
25 Slum rehabilitation and redevelopment housing project under model 4 of the “Policy on Housing for All in Urban Areas” 2015 (Mahavir Awas Yojana) 3.82 acres 20 Social and Commercial Infrastructure Housing Under Construction Housing and Urban Development Department Odisha
26 Slum rehabilitation and redevelopment housing project under model 4 of the “Policy on Housing for All in Urban Areas” 2015 (at Nilamadhav slum in Chandrasekharpur) 5.32 acres for 1170 SRRH units 2.86 acres for developer 194 Social and Commercial Infrastructure Housing Under Construction Housing and Urban Development Department Odisha
27 Berhampur Solid Waste Management 150 TPD (Tonne per day) 80 Water Sanitation Solid waste management Under Construction Berhampur Municipal Corporation Odisha
28 Commissioning, Operation, Maintenance and Management of Cancer Hospital at Jharsuguda on PPP mode 120 beds 168.72 Social and Commercial Infrastructure Healthcare Under Construction Health and Family Welfare Department Odisha
29 Commissioning, Operation, Maintenance and Management of Cardiac Care Hospital at Jharsuguda on PPP mode 100 beds 110 Social and Commercial Infrastructure Healthcare Under Construction Health and Family Welfare Department Odisha
30 Establishment of affordable healthcare projects State-wide - Bidding of Angul. Barbil, Bhadrak & Jharsuguda under the revamped VGF Scheme of Government of India Angul and Barbil- 200 beds each Bhadrak and Jharsuguda - 100 beds each =(116.72+113.78)*(100/80) Social and Commercial Infrastructure Healthcare Under Construction Health and Family Welfare Department Odisha
31 Automated Driving Testing System (ADTS) 6 locations across Odisha 30 Transport Urban public transport Completed Commerce and Transport Department Odisha
32 Institute of Driving Training and Research (IDTR) Bonai - 2880 students Keonjhar - 24000 students Berhampur - 1680 students 120 ( Rs. 30 Cr per location) Transport Urban public transport Completed Commerce and Transport Department Odisha
33 Selection of Bus Operator for Cluster 1 - V under LAccMl scheme (integrated public transport connecting Gram panchayats, Block, & districts) in PPP mode 1000 buses in 5 clusters 669.7 (Total Cost of Procured Buses) Transport Urban public transport Completed Commerce and Transport Department Odisha
34 City bus service in Bhubaneswar (Bhubaneswar – Puri – Khurda - Cuttack urban cluster & Choudwar) • Package I - 100 new midi-buses • Package II - 100 new standard buses (of which 50 are A.C. & 50 non-A.C.) • Package III - 110 existing buses (refurbish, operate & maintain) 605 Transport Urban public transport Completed Commerce and Transport Department Odisha
35 City bus service in Rourkela (Jhirpani,Bonaigarh,Rajgangpur,Lathikata ,Bisra & Rourkela city) Not Available 100 Transport Urban public transport Completed Commerce and Transport Department Odisha
36 City Bus Service at Sambalpur 4 intra - city routes; 5 inter city routes; through 32 buses each of 28 seats capacity - Transport Urban public transport Completed Commerce and Transport Department Odisha
37 City Bus Service at Berhampur (Berhampur- Gopalpur - Chatrapur - Hinjlicut urban cluster) 4 intra - city routes; 3 inter city routes; through 32 buses each of 28 seats capacit - Transport Urban public transport Completed Commerce and Transport Department Odisha
38 Sambalpur Rourkela Expressway Section of SH 10 from Km 4.900 to 167.900km, 4 lane paved shoulders 1481.7 Transport Roads and bridges Completed Commerce and Transport Department Odisha
39 Dhamra Port - Phase 1 25.0 MTPA (Metric Tonne Per Annum) 10016 Transport Ports (excluding captive) Completed Commerce and Transport Department Odisha
40 Gopalpur Port Not Available 1500 Transport Ports (excluding captive) Completed Commerce and Transport Department Odisha
41 Development of storage and warehousing infrastructure for rice (as per State PEG Scheme 2013) 2500 MT each 20.5 Social and Commercial Infrastructure Post-harvest storage infrastructure for agriculture and horticulture produce including cold storage Completed Odisha State Civil Supply Corporation Ltd. Odisha
42 Ropeway at Nandankanan Zoological Park 618 meter long monocable ( 12 cabins at 6 persons each) 15 Social and Commercial Infrastructure Tourism Completed Forests, Environment and Climate Change Department Odisha
43 Long term lease of Hockey World Cup Village, Rourkela for Operation and Management 225 rooms 182.45 Social and Commercial Infrastructure Tourism Completed Sports and Youth Services Department Odisha
44 Rooftop solar project in Bhubaneswar and Cuttack 4 MW for 199 government buildings 32 Energy Renewable enrgy Completed Energy Department/ (GEDCOL) Odisha
45 Programmatic Street Lighting in different Urban Local Bodies (ULBs) Not Available 29.1 Energy Renewable enrgy Completed Housing and Urban Development Department Odisha
46 Greenfield energy efficient street lighting project in different Urban Local Bodies (ULBs) 113 ULBS in 30 districts 227 Energy Renewable enrgy Completed Housing and Urban Development Department Odisha
47 Affordable housing project under model 3 of the “Policy on Housing for All in Urban Areas” 2015 (at Chandrasekharpur) 2960 EWS units over 22.746 acres 320 Social and Commercial Infrastructure Housing Completed Housing and Urban Development Department Odisha
48 Slum rehabilitation and redevelopment housing project (Shanti Nagar Awas Yoiana) under model 4 of the "Policy on Housing for All in Urban Areas" 2015 Phase II 1300 EWS units over 10 acres 120 Social and Commercial Infrastructure Housing Completed Housing and Urban Development Department Odisha
49 Development of intregated residential complex over 12 acres at Shankarpur, Bhubaneswar by BDA (TATA Ariana project) 12 Acres 210 Social and Commercial Infrastructure Housing Completed Housing and Urban Development Department Odisha
50 Integrated Residential & Commercial Complex at Gadakana 5.05 Acres 95 Social and Commercial Infrastructure Housing Completed Housing and Urban Development Department Odisha
51 Mahodadhi Nivas Hotel in Puri 25 rooms over 2.49 acres 10 Social and Commercial Infrastructure Tourism Completed Odisha Tourism Development Corporation Odisha
52 Eco-resort, Ramachandi 5 acres 30 Social and Commercial Infrastructure Tourism Completed Odisha Tourism Development Corporation Odisha
53 Development and operation of existing tourism accomodation units (Bid Process for Lease - cum - Development of DoT properties ) Not Available _ Social and Commercial Infrastructure Tourism Completed Department of Tourism Odisha
54 MITS Mega food park at Rayagada 50.5 acres 80.17 Social and Commercial Infrastructure Common infrastructure for industrial parks, SEZ Completed IDCO Odisha
55 NOCCi Plastic and Polymer Park, Balasore Not Available 80.76 Social and Commercial Infrastructure Common infrastructure for industrial parks, SEZ Completed IDCO Odisha
56 Bulk water supply for various Institutions and adjoining Industries of Bhubaneswar 70.0 MLD (Millons Liter per day) 188 Water Sanitation Water supply pipeline Completed Industries Department Odisha
57 Establishment of Institute for Training of Trainers (IToTs) in PPP 200 trainees annually 10 Social and Commercial Infrastructure Education Completed Skill Development and Technical Education Department Odisha
58 Establishment & Operation of laboratories for testing and quality monitoring of water and waste water Not Available 66.21 Social and Commercial Infrastructure Common infrastructure for industrial parks, SEZ Completed MSME Odisha
59 Construction of Hemodialysis unit at Zonal Hospital, Dharamshala 6.0 Machines 0 Social and Commercial Infrastructure Health Care Operation and Maintenance Stage Department of Health and Family Welfare, Government of Himachal Pradesh Himachal Pradesh 05-Dec-2019
60 Teesta IV Project - 520 MW 520.0 MW (Mega Watt) 5878 Energy Renewable energy (grid) Under Construction NHPC Limited Sikkim 05-Dec-2019
61 2 laning with PSS of Salasar to Haryana border section of NH65 and capacity augmentation in 2021 for 4 laning on BOT(Toll) basis 154.1 KM (Kilometer) 530.07 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Rajasthan 04-Dec-2019
62 4 laning of Patna-Muzaffarpur stretch of NH77 from 0-46.3 km and construction of Muzzafarpur bypass on BOT(Annuity) Basis 46.3 KM (Kilometer) 570.06 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Bihar 04-Dec-2019
63 6 laning of Chenagapjalli to Start of Coimbatore bypass & 4 laning of end of Coimbatore bypass to TN/Kerala Boarder of NH 47 54.8 KM (Kilometer) 852.74 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Multi State/ Centre 04-Dec-2019
64 Berth No. 15 of New Western Dock for handling coal # 3.0 MTPA (Metric Tonne Per Annum) 376.52 Transport Ports (excluding captive) Operation and Maintenance Stage New Mangalore Port Trust Karnataka 04-Dec-2019
65 Biomass power project at Sattenapalli 6.0 MW (Mega Watt) 26 Energy Electricity generation (grid) Operation and Maintenance Stage Andhra Pradesh Electricity Regulatory Commission Andhra Pradesh 04-Dec-2019
66 Bus Terminal (Vadnagar) Project Not Available 10.53 Transport Urban public transport (except rolling stock) Operation and Maintenance Stage Gujarat State Road Development Corporation (GSRDC) Gujarat 04-Dec-2019
67 Construction of Dhola-Sadia Ghats bridges in length of 9.15 km 9.1 KM (Kilometer) 945.96 Transport Roads and bridges Operation and Maintenance Stage Ministry of Road Transport and Highways Assam 04-Dec-2019
68 Construction of multi chamber cold storage with a capacity of 4000 MT in Barmer# 4000.0 MT (Metric Tonne ) 7.38 Social and Commercial Infrastructure Cold Chain Operation and Maintenance Stage Rajasthan State Agriculture Marketing Board Rajasthan 04-Dec-2019
69 Development of 1000 TPD solid waste management in Ahmedabad # 1000.0 TPD (Tonne per day) 240 Water Sanitation Solid waste management Under Construction Ahmedabad Municipal Corporation Gujarat 04-Dec-2019
70 Development of integrated multi level automatic car parking at Khilwat in Hyderabad district #* 1.2 Acres 73 Transport Urban public transport (except rolling stock) Pre-construction Stage Greater Hyderabad Municipal Corporation Telangana 04-Dec-2019
71 Development of Offshore Multipurpose Cargo Berth at Mumbai Port in the State of Maharashtra on DBFOT basis* Not Available 696.27 Transport Ports (excluding captive) Pre-construction Stage Ministry of Shipping Maharashtra 04-Dec-2019
72 Eco Tourism (Sabujdweep Island) Project 75.0 Acres 54 Social and Commercial Infrastructure Common infrastructure for industrial parks, SEZ Under Construction Department of Tourism, West Bengal West Bengal 04-Dec-2019
73 Four laning of Chikhali-Tarsod section in length of 62.7 km in Buldana 62.7 KM (Kilometer) 1071.61 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Maharashtra 04-Dec-2019
74 International Cricket Stadium (Lucknow) Project # Not Available 360 Social and Commercial Infrastructure Tourism Under Construction Lucknow Development Authority Uttar Pradesh 04-Dec-2019
75 Machilipatnam Port Development * # 17.0 MTPA (Metric Tonne Per Annum) 1860 Transport Ports (excluding captive) Under Construction Department of Ports, Andhra Pradesh Andhra Pradesh 04-Dec-2019
76 Mechanism of Coal Handling facilities and upgradation of General Cargo Berth at Outer Harbour of Visakhapatnam Port 10.18 MMTPA (million metric tonnes per annum) 640.4 Transport Ports (excluding captive) Operation and Maintenance Stage Ministry of Shipping Andhra Pradesh 04-Dec-2019
77 Multipurpose Cargo Port (Redi) Project 53.0 MMTPA (million metric tonnes per annum) 4413.7 Transport Ports (excluding captive) Pre-construction Stage Maharashtra Maritime Board (MMB) Maharashtra 04-Dec-2019
78 Operation and Maintenance of North East Tribal Museum and Cultural Centre at Nazirakhat, Sonapur, Kamrup (M), Assam * 90.0 Acres 50 Social and Commercial Infrastructure Tourism Under Construction Cultural Affairs Department, Government of Assam Assam 04-Dec-2019
79 Parule Airport Project 400.0 Passengers 520 Transport Airports Operation and Maintenance Stage Maharashtra Industrial Development Corporation Maharashtra 04-Dec-2019
80 Setting up 20 MW hydel based power unit at Telbeila in Pune 20.0 MW (Mega Watt) 115.44 Energy Renewable energy (grid) Pre-construction Stage Water Resources Department, Maharashtra Maharashtra 04-Dec-2019
81 Setting up of 10 TPD solid waste management unit at Pernem # 10.0 TPD (Tonne per day) 15 Water Sanitation Solid waste management Under Construction State Urban Development Agency, Goa Goa 04-Dec-2019
82 Setting up of 9 MW Fozal hydel power unit in Kullu district 9.0 MW (Mega Watt) 49.16 Energy Renewable energy (grid) Under Construction Directorate of Energy, Himachal Pradesh Himachal Pradesh 04-Dec-2019
83 Setting up of Iron ore handling facilities on BOT basis at New Mangalore Port * 9.0 MMTPA (million metric tonnes per annum) 277.11 Transport Ports (excluding captive) Pre-construction Stage New Mangalore Port Trust Karnataka 04-Dec-2019
84 Water Supply Scheme (Nanjangud) * 10.7 MLD (Millons Liter per day) 28.55 Water Sanitation Water supply pipeline Under Construction Town Municipal Council, Nanjangud Karnataka 04-Dec-2019
85 Dhamra Port # 25.0 MTPA (Metric Tonne Per Annum) 10016 Transport Ports (excluding captive) Operation and Maintenance Stage Department of Commerce and Transport, Odisha Odisha 03-Dec-2019
86 Angre Port - Jaigad Not Available 431 Transport Ports (excluding captive) Operation and Maintenance Stage Maharashtra Maritime Board (MMB) Maharashtra 25-Nov-2019
87 Construction of central bus terminal on 6.3 acres at Makarpura in Vadodara 6.30 Acres 60.28 Transport Urban public transport (except rolling stock) Operation and Maintenance Stage Gujarat State Road Transport Corporation Gujarat 25-Nov-2019
88 Construction of Deep draught coal berth on BOT basis by Paradip Port Trust 10.0 MMTPA (million metric tonnes per annum) 656 Transport Ports (excluding captive) Under Construction Paradip Port Trust Odisha 25-Nov-2019
89 Production of CNG from Raw biogas at Delawas STP Unit-II Not Available 0 Energy Renewable energy (grid) Operation and Maintenance Stage Jaipur Municipal Corporation Rajasthan 25-Nov-2019
90 Setting up of Liquid Cargo Handling Jetty at Shalukkhali, Haldia Dock-II through PPP mode 2.43 MTPA (Metric Tonne Per Annum) 172.52 Transport Ports (excluding captive) Under Construction Kolkata Port Trust West Bengal 25-Nov-2019
91 Setting up of MSW Processing plant adopting Waste to Energy Technology with Sanitary landfill at Langdiyawas for jaipur 0 214 Water Sanitation Solid waste management Pre-construction Stage Jaipur Municipal Corporation Rajasthan 25-Nov-2019
92 Modernization of Delhi International Airport 119.0 MPPA (Million Passenger Per Annum) 12508.94 Transport Airports Operation and Maintenance Stage Airports Authority of India (AAI) Delhi (UT) 24-Nov-2019
93 Conversion of Delhi-Gurgaon section of NH-8 into an access controlled eight/six lane highway 28.0 KM (Kilometer) 800 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Multi State/ Centre 21-Nov-2019
94 Electricity Distribution Nagpur City Not Available 652.29 Energy Electricity Distribution Operation and Maintenance Stage Maharashtra State Electricity Distribution Company Limited Maharashtra 20-Nov-2019
95 Four laning of Narketpally-Addanki-Medarametla Road Project 212.5 KM (Kilometer) 1760.53 Transport Roads and bridges Operation and Maintenance Stage Andhra Pradesh Road Development Corporation Andhra Pradesh 20-Nov-2019
96 Six laning of Kishangarh -Udaipur- Ahmedabad section of NH 79A, NH79, NH 76 and NH 8 under NHDP Phase V, length 555.50 km 555.0 KM (Kilometer) 5387.3 Transport Roads and bridges Operation and Maintenance Stage Ministry of Road Transport and Highways Rajasthan 20-Nov-2019
97 Ambala - Zirakpur 35.09 KM (Kilometer) 298 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Multi State/ Centre 15-Nov-2019
98 City side development of Udaipur Airport through PPP * Not Available 0 Transport Airports Pre-construction Stage Ministry of Civil Aviation Rajasthan 15-Nov-2019
99 Design, Construction, Development, Finance,O&M (Salem)Start of proposed flyover on Namakkal Bypass 41.5 KM (Kilometer) 253.55 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Tamil Nadu 15-Nov-2019
100 Development of Triangle portion of the Lakota lake 1.8 1.8 Km periphery 45,000 Sq.m paved area 45 Social and Commercial Infrastructure Tourism Operation and Maintenance Stage Jamnagar Municipal Corporation Gujarat 15-Nov-2019
101 Four laning of Chapra - Hazipur section on NH 19 in Bihar * 64.0 KM (Kilometer) 691 Transport Roads and bridges Under Construction National Highways Authority of India (NHAI) Bihar 15-Nov-2019
102 Four/Six lanning of Patna - Bakhtiyarpur section from Km 176.60 to Km 230 of NH 30 in the State of Bihar 50.6 KM (Kilometer) 600.54 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Bihar 15-Nov-2019
103 Khambatki Ghat Project 8.0 KM (Kilometer) 45 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Maharashtra 15-Nov-2019
104 Operation and Maintenance of Bargawan-Waidhan road in length of 27.3 Km 28.0 KM (Kilometer) 39.41 Transport Roads and bridges Operation and Maintenance Stage Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 15-Nov-2019
105 Road Upgradation (Farukhnagar - Kottakata) Project-Package-II 46.1 KM (Kilometer) 471 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Andhra Pradesh 15-Nov-2019
106 Road Upgradation Project (Raipuriya-Paitalvad-Bamaniya) Project 18.18 KM (Kilometer) 25.73 Transport Roads and bridges Operation and Maintenance Stage Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 15-Nov-2019
107 Road Upgradation Project (Tikamgarh-Orchha & Orchha Bypass) Project 10.0 KM (Kilometer) 58 Transport Roads and bridges Operation and Maintenance Stage Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 15-Nov-2019
108 Upgradation of existing facility & creation of new facility at Visakhapatnam Port Trust, for Iron Ore Handling 23.0 MMTPA (million metric tonnes per annum) 845.41 Transport Ports (excluding captive) Under Construction Visakhapatnam Port Trust Andhra Pradesh 15-Nov-2019
109 Basin Bridge Diesel-Fired Power Plant * 200.0 MW (Mega Watt) 490.23 Energy Electricity generation (grid) Under Construction Tamil Nadu State Electricity Board Tamil Nadu 14-Nov-2019
110 Bulk Cargo Berth No.12 (New Mangalore Port) Project 6.73 MTPA (Metric Tonne Per Annum) 469.46 Transport Ports (excluding captive) Under Construction New Mangalore Port Trust Karnataka 14-Nov-2019
111 Development of Amusement park, Swimming pool, Water sports complex and Conventional hall at Wadeghar 14.0 Acres 7 Social and Commercial Infrastructure Tourism Under Construction Kalyan Dombivli Municipal Corporation Maharashtra 14-Nov-2019
112 Development of passenger ropeway from Bypass (TIC)-Lift Mall Road in length of 3.6 Km in Shimla district # 3.6 KM (Kilometer) 296.67 Social and Commercial Infrastructure Tourism Pre-construction Stage Shimla Municipal Corporation Himachal Pradesh 14-Nov-2019
113 Multilevel Parking (Vikasnagar) Project 174.0 ECS 15 Transport Urban public transport (except rolling stock) Under Construction Shimla Municipal Corporation Himachal Pradesh 14-Nov-2019
114 Multipurpose Cargo Port (Mankhurd) Project - Phase I 4.5 MMTPA (million metric tonnes per annum) 75 Transport Ports (excluding captive) Under Construction Maharashtra Maritime Board (MMB) Maharashtra 14-Nov-2019
115 Truck Terminal (First Avenue Business Park & Parking Plaza) (Kalyan) Project Not Available 10.16 Social and Commercial Infrastructure Common infrastructure for industrial parks, SEZ Under Construction Kalyan Dombivli Municipal Corporation Maharashtra 14-Nov-2019
116 Approval for VGF Support for Construction of Silos by FCI at Sahnewal, Punjab - roposed by FPD 50000.0 MT (Metric Tonne ) 42.37 Social and Commercial Infrastructure Post-harvest storage infrastructure for agriculture and horticulture produce including cold storage Pre-construction Stage Food Corporation of India Punjab 13-Nov-2019
117 Construction of 4 laned ROB including its approach on Delhi Agra Railway Line near Bata Chowk Not Available 15.62 Transport Roads and bridges Operation and Maintenance Stage Public Works Department, Haryana Haryana 13-Nov-2019
118 Development of community centre and shopping complex at Kalyan 1.30 Acres 6.24 Social and Commercial Infrastructure Tourism Under Construction Kalyan Dombivli Municipal Corporation Maharashtra 13-Nov-2019
119 Development of Ganga Driveway and Riverfront Development from Digha to Didarganj at Patna on BOT (Toll) basis. 21.50 KM (Kilometer) 2234.46 Transport Roads and bridges Under Construction Bihar State Road Development Corporation Limited Bihar 13-Nov-2019
120 Development of modern food silo for storage of wheat on DBFOT at Katihar (Bihar) - Proposed by FPD 50000.0 MT (Metric Tonne ) 44.62 Social and Commercial Infrastructure Post-harvest storage infrastructure for agriculture and horticulture produce including cold storage Under Construction Food Corporation of India Bihar 13-Nov-2019
121 Development of passenger ropeway of 2 Km from Kullu bypass to Bijili Mahadev Temple in kullu district 600.0 Passengers 94.19 Social and Commercial Infrastructure Tourism Under Construction Department of Tourism and Civil Aviation, Himachal Pradesh Himachal Pradesh 13-Nov-2019
122 Development of ropeway between Dharamshala to Mcleod Ganj with a capacity of 600 Passenger in Kangra district 600.0 Passengers 150 Social and Commercial Infrastructure Tourism Under Construction Department of Tourism and Civil Aviation, Himachal Pradesh Himachal Pradesh 13-Nov-2019
123 Electricity distribution Bharatpur City (BESL) Not Available 33.35 Energy Electricity Distribution Operation and Maintenance Stage Jaipur Vidyut Vitran Nigam Limited Rajasthan 13-Nov-2019
124 Electricity distribution Kota City (KEDL) Not Available 252.83 Energy Electricity Distribution Operation and Maintenance Stage Jaipur Vidyut Vitran Nigam Limited Rajasthan 13-Nov-2019
125 Gurgaon Metro South Extension (RMGSL) project 12.0 KM (Kilometer) 2150 Transport Urban public transport (except rolling stock) Operation and Maintenance Stage Haryana Urban Development Authority Haryana 13-Nov-2019
126 Laying of ropeway at Hemkund in Chamoli district * 150000.0 Passengers 50.7 Social and Commercial Infrastructure Tourism Under Construction Uttarakhand Tourism Development Board Uttarakhand 13-Nov-2019
127 Laying of ropeway from Palchan to Gulaba, Gulaba to Marhi and Marhi to Rohtang in Kangra district 1500.0 Passengers 340 Social and Commercial Infrastructure Tourism Under Construction Department of Tourism and Civil Aviation, Himachal Pradesh Himachal Pradesh 13-Nov-2019
128 Passenger Ropeway (Solang Valley-Kullu) Project 1200.0 Passengers 36.57 Social and Commercial Infrastructure Tourism Operation and Maintenance Stage Department of Tourism and Civil Aviation, Himachal Pradesh Himachal Pradesh 13-Nov-2019
129 Re-development of Berth 8, 9 and Barge Berth at Port of Marmugao, Goa 19.2 MMTPA (million metric tonnes per annum) 1145 Transport Ports (excluding captive) Pre-construction Stage Mormugao Port Trust Goa 13-Nov-2019
130 Ropeway (Himani-Chamunda) Project 1000.0 Passengers 289.24 Social and Commercial Infrastructure Tourism Under Construction Department of Tourism and Civil Aviation, Himachal Pradesh Himachal Pradesh 13-Nov-2019
131 Waste to Power Plant, 1000 TPD, Surat 1000.0 TPD (Tonne per day) 209 Energy Electricity generation (grid) Under Construction Surat Municipal Corporation Gujarat 13-Nov-2019
132 Delhi-Meerut Expressway Project [Package-III] 22.2 KM (Kilometer) 1058 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Uttar Pradesh 11-Nov-2019
133 Development of Delhi-Meerut Expressway in length of 8.7 Km in Delhi 8.7 KM (Kilometer) 841.5 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Delhi (UT) 11-Nov-2019
134 Development, O & M of Hanumangarh to Abohar section of SH-7A (up to Punjab border) on DBFOT Toll basis.* 42.6 KM (Kilometer) 61.67 Transport Roads and bridges Under Construction Public Works Department, Rajasthan Rajasthan 11-Nov-2019
135 Four laning Indore-Ujjain Road Project 48.9 KM (Kilometer) 298 Transport Roads and bridges Operation and Maintenance Stage Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 11-Nov-2019
136 Four Laning Nashik � Niphad � Vaijapur - Aurangabad Road 40.0 KM (Kilometer) 174.58 Transport Roads and bridges Operation and Maintenance Stage Public Works Department, Maharashtra Maharashtra 11-Nov-2019
137 Four laning of Bareilly-Sitapur section of NH 24 in the State of Uttar Pradesh on BOT basis under NHDP III 151.2 KM (Kilometer) 1046 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Uttar Pradesh 11-Nov-2019
138 Four laning of Hadapsar- Saswad- Belsar-Phata (SH-64) to Belha-Pabal-Uralikanchan-Jejuri-Nira (SH-61) road 41.1 KM (Kilometer) 358.4 Transport Roads and bridges Under Construction Public Works Department, Maharashtra Maharashtra 11-Nov-2019
139 Four Laning of Mahuva to Kagavadar section in 39.8 Km under NHDP-IV 40.02 KM (Kilometer) 763.23 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Gujarat 11-Nov-2019
140 Four Laning of Stand Alone Ring Road/Bypass for Nagpur City 61.5 KM (Kilometer) 1170 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Maharashtra 11-Nov-2019
141 Road Upgradation (Kodinar-Veraval) Project 41.74 KM (Kilometer) 829.97 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Gujarat 11-Nov-2019
142 Six laning of Varanasi-Aurangabad section of NH 2from Km 786.00 to km 978.40 in the State of UP/Bihar under NHDP V on BOT basis 192.4 KM (Kilometer) 2588.38 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Multi State/ Centre 11-Nov-2019
143 Two laning of Chittorgarh-Neemach section of NH 79 and Nimbahera-Pratapgarh section of NH 113 under VGF Scheme 113.0 KM (Kilometer) 511.21 Transport Roads and bridges Operation and Maintenance Stage Public Works Department, Rajasthan Rajasthan 11-Nov-2019
144 Two laning of Shirur Tajband-Mukhed-Narsi & 2 laning with paved shoulder of Narsi-Biloli to State Border, sections of SH-225 105.0 KM (Kilometer) 318 Transport Roads and bridges Operation and Maintenance Stage Public Works Department, Maharashtra Maharashtra 11-Nov-2019
145 Two/Four laning of Nanded-Narsi Road sector of SH-6 77.7 KM (Kilometer) 238.79 Transport Roads and bridges Operation and Maintenance Stage Public Works Department, Maharashtra Maharashtra 11-Nov-2019
146 "DBFOMT" of existing state highway (SH-3 & 33) from Malavalli to Pavagada (Approx Length 193.344 Km) in Karnataka 193.34 KM (Kilometer) 559.75 Transport Roads and bridges Operation and Maintenance Stage Public Works, Ports and Inland Water Transport Department, Karnataka Karnataka 09-Nov-2019
147 "DBFOMT" of SH18 from Mudhol - Nippani - MH Border (Approx Length 107.937) in Karnataka 107.9 KM (Kilometer) 317.6 Transport Roads and bridges Operation and Maintenance Stage Public Works, Ports and Inland Water Transport Department, Karnataka Karnataka 09-Nov-2019
148 2 lane with paved shoulders of Bhopal Sanchi section under NHDP phase III* 53.77 KM (Kilometer) 305 Transport Roads and bridges Under Construction National Highways Authority of India (NHAI) Madhya Pradesh 09-Nov-2019
149 2 laning with paved shoulder�of Jabalpur-Mandala-Chilpi section�from 3.4 to 192.4 km under NHDP - IV 177.75 KM (Kilometer) 811.74 Transport Roads and bridges Under Construction Ministry of Road Transport and Highways Madhya Pradesh 09-Nov-2019
150 2 laning with paved shoulders of Nagaur-Bikaner section of NH89 from km 171 to km 267.325 of NH 89 (including bypass at Nagaur) 108.3 KM (Kilometer) 378.07 Transport Roads and bridges Operation and Maintenance Stage Public Works Department, Rajasthan Rajasthan 09-Nov-2019
151 2 laning with Paved Side Shoulders of Nagaur-Jodhpur of NH-65 from km 166.26 to km 296.07 on DBFOT (Toll) basis.* 134.64 KM (Kilometer) 439.96 Transport Roads and bridges Under Construction Ministry of Road Transport and Highways Rajasthan 09-Nov-2019
152 2/4 laning of NH 12 from km 256.55 to km 346.539(Kota-Jhalwar section) on BOT(Toll) basis basis�* Not Available 530.01 Transport Roads and bridges Under Construction Ministry of Road Transport and Highways Rajasthan 09-Nov-2019
153 2/4 laning of section between Madurai to Ramanathapuram and 2 lane with paved shoulders from 79.34 - 118.795 km of NH 49 115.11 KM (Kilometer) 683 Transport Roads and bridges Operation and Maintenance Stage Ministry of Road Transport and Highways Tamil Nadu 09-Nov-2019
154 24x7 Nagpur Water Supply Scheme * Not Available 387.86 Water Sanitation Water supply pipeline Under Construction Nagpur Municipal Corporation Maharashtra 09-Nov-2019
155 3 Star Hotel at Amritsar * Not Available 175 Social and Commercial Infrastructure Tourism Under Construction Punjab Urban Development Authority Punjab 09-Nov-2019
156 4 Laning of Rimuli Roxy Rajamunda Section of NH 215 from 163 -269 km in Orissa under NHDP Phase IIIA on BOT Basis. 106.0 KM (Kilometer) 654 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Odisha 09-Nov-2019
157 4 laning of Sahajahanpur-Hardoi-Lucknow Road (SH-25) on DBFOT toll basis* 162.4 KM (Kilometer) 1161.62 Transport Roads and bridges Under Construction Public Works Department, Government of Uttar Pradesh Uttar Pradesh 09-Nov-2019
158 4 laning of Tirupati-Tiruthani-Chennai section of NH 205 from 274.8-341.6 km in AP and km 0 to 59.60 in Tamil Nadu on BOT Basis 124.7 KM (Kilometer) 801.8 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Multi State/ Centre 09-Nov-2019
159 4 laning of Trichy Karaikkudi section of NH-210 (10-94 km) and Trichy Bypass (ch 109.558-ch 135.39) in Tamil Nadu on BOT basis. 110.9 KM (Kilometer) 374 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Tamil Nadu 09-Nov-2019
160 4-laning of Etah Sikohabad Road (SH-85) from km 0.000 to km 51.415 on DBFOT toll basis* 51.41 KM (Kilometer) 344.61 Transport Roads and bridges Under Construction Public Works Department, Government of Uttar Pradesh Uttar Pradesh 09-Nov-2019
161 4/6 laning of Dewas Bypass from Km 0/00 on sH-18 to km. to 19/800 on NH-3 on DBFOT basis. 19.8 KM (Kilometer) 267.3 Transport Roads and bridges Pre-construction Stage Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 09-Nov-2019
162 4/6 laning of Maharashtra/Goa Border to Panaji-Goa/Karnataka Border to be executed as BOT(Toll) on DBFO pattern* Not Available 2078 Transport Roads and bridges Under Construction Ministry of Road Transport and Highways Goa 09-Nov-2019
163 5 Star Hotel at Amritsar * Not Available 250 Social and Commercial Infrastructure Tourism Under Construction Punjab Urban Development Authority Punjab 09-Nov-2019
164 5 Star Hotel at Bhatinda * Not Available 200 Social and Commercial Infrastructure Tourism Under Construction Not Available Punjab 09-Nov-2019
165 5 Star Hotel-cum-Convention Centre, Amritsar * Not Available 175 Social and Commercial Infrastructure Tourism Under Construction Punjab Urban Development Authority Punjab 09-Nov-2019
166 5 Star Hotel-cum-Convention Centre, Ludhiana * Not Available 175 Social and Commercial Infrastructure Tourism Under Construction Greater Ludhiana Area Development Authority Punjab 09-Nov-2019
167 5 Star Hotel-cum-Convention Centre, Mohali * Not Available 350 Social and Commercial Infrastructure Tourism Under Construction Greater Mohali Area Development Authority Punjab 09-Nov-2019
168 6 laning of Ahmedabad Vadodara Section of NH 8 and improvement of Ahmedabad Vadodara Expressway in Gujarat under NHDP Phase V 102.3 KM (Kilometer) 4880 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Gujarat 09-Nov-2019
169 6 laning(and Construction of additional 4 lane Bridge across River Narmada) of Vadodara-Surat Section of NH-8 on BOT(Toll) basis Not Available 473.24 Transport Roads and bridges Under Construction Ministry of Road Transport and Highways Gujarat 09-Nov-2019
170 6-laning of Indore-Dewas section of NH-3 Madhya Pradesh NHDP-V to be executed as BOT (Toll) project on"DBFOT" pattern 45.0 KM (Kilometer) 325 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Madhya Pradesh 09-Nov-2019
171 6-Laning(Chengapalli &4-Laning on end of TNKerala Border Sec.of NH47 Tamil Nadu under NHDP-11 on DBFOT(Toll)basi 54.80 KM (Kilometer) 852 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Tamil Nadu 09-Nov-2019
172 6/8 laning of JNPT Port Road Project at NH 4B (A1 - E section), NH-4B (D-G section), SH-54 and on Amra Marg 43.912 KM (Kilometer) 1822 Transport Roads and bridges Operation and Maintenance Stage Ministry of Road Transport and Highways Maharashtra 09-Nov-2019
173 8/6 Laning of Delhi Meerut Expressway from Km. 8.36- Km. 27.74 (UP Border to Dasna) oh NH-24 on HAM(Package II)* Not Available 1989 Transport Roads and bridges Under Construction Ministry of Road Transport and Highways Uttar Pradesh 09-Nov-2019
174 Adityapur Water Supply Phase I * Not Available 150 Water Sanitation Water supply pipeline Not Available Department of Industries, Jharkhand Jharkhand 09-Nov-2019
175 Amusement Park at Gurgaon * 17.0 Acres 100 Social and Commercial Infrastructure Tourism Under Construction Haryana Urban Development Authority Haryana 09-Nov-2019
176 Augmentation of Parallel Water Supply Scheme in length of 1200.0 km in Aurangabad district * 1200.0 KM (Kilometer) 720 Water Sanitation Water supply pipeline Under Construction Aurangabad Municipal Corporation Maharashtra 09-Nov-2019
177 Badnagar - Sundarawad - Kharsodkalan - Unhel* 51.31 KM (Kilometer) 141 Transport Roads and bridges Not Available Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 09-Nov-2019
178 Baretha - Ghoradongri 15.1 KM (Kilometer) 39.53 Transport Roads and bridges Operation and Maintenance Stage Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 09-Nov-2019
179 Batala - Beas (MDR-66)* Not Available 87 Transport Roads and bridges Under Construction Public Works Department, Punjab Punjab 09-Nov-2019
180 Berth (EQ 1A & EQ 1) Project * 7.3 MMTPA (million metric tonnes per annum) 313.39 Transport Ports (excluding captive) Under Construction Visakhapatnam Port Trust Andhra Pradesh 09-Nov-2019
181 Biotech Park (Andharua) * 64.0 Acres 100 Social and Commercial Infrastructure Common infrastructure for industrial parks, SEZ Under Construction Odisha Industrial Infrastructure Development Corporation Odisha 09-Nov-2019
182 Border Check Posts (Madhya Pradesh) Project* 24.0 Numbers 1350 Transport Roads and bridges Under Construction Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 09-Nov-2019
183 Bridge (Haldwani-Ramnagar) Project* 1.075 KM (Kilometer) 26 Transport Roads and bridges Under Construction Public Works Department, Uttarakhand Uttarakhand 09-Nov-2019
184 Chandikole - Paradeep Section, km 0.000 to 76.618� of NH - 5A� under NHDP V on BOT (Toll)* 76.618 KM (Kilometer) 1014.36 Transport Roads and bridges Under Construction Ministry of Road Transport and Highways Odisha 09-Nov-2019
185 City Development (Mankapur) Project * Not Available 48 Social and Commercial Infrastructure Common infrastructure for industrial parks, SEZ Under Construction Nagpur Municipal Corporation Maharashtra 09-Nov-2019
186 Cold chain project for Fruit and vegetables * 512.0 MT (Metric Tonne ) 50.41 Social and Commercial Infrastructure Cold Chain Under Construction Ministry of Food Processing Industries Maharashtra 09-Nov-2019
187 Commercial Centre at Chinchwad * Not Available 20.94 Social and Commercial Infrastructure Common infrastructure for industrial parks, SEZ Under Construction Pimpri Chinchwad Municipal Corporation Maharashtra 09-Nov-2019
188 Commercial development of Animal Husbandry and Veterinery Science land on Hebbal road * Not Available 250 Social and Commercial Infrastructure Common infrastructure for industrial parks, SEZ Not Available Department of Agriculture, Horticulture, Animal Husbandry and Fisheries, Karnataka Karnataka 09-Nov-2019
189 Common Effluent Treatment (Adityapur) Project * Not Available 12 Water Sanitation Sewage collection, treatment and disposal system Under Construction Adityapur Municipal Council Jharkhand 09-Nov-2019
190 Construction and area development under GMDA at Borsajal, Guwahati, Assam * Not Available 0 Social and Commercial Infrastructure Tourism Not Available Guwahati Metropolitan Development Authority Assam 09-Nov-2019
191 Construction of bus terminal on 6.5 acres at Adajan in Surat * 6.5 Acres 155.09 Transport Urban public transport (except rolling stock) Under Construction Gujarat State Road Transport Corporation Gujarat 09-Nov-2019
192 Construction of funicular railway at Haji Malang Gad in Thane district * 60.0 Passengers 45.91 Social and Commercial Infrastructure Tourism Under Construction Public Works Department, Maharashtra Maharashtra 09-Nov-2019
193 Construction of Gavanphata Interchange road 18.3 KM (Kilometer) 593.26 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Maharashtra 09-Nov-2019
194 Construction of Gurgaon Recreation Park * Not Available 71 Social and Commercial Infrastructure Common infrastructure for industrial parks, SEZ Under Construction Haryana State Industrial and Infrastructure Development Corporation Haryana 09-Nov-2019
195 Construction of KSRTC offices guest house and commercial complex on KSRTC Site at Mangaluru district * 1.10 Acres 20.7 Social and Commercial Infrastructure Common infrastructure for industrial parks, SEZ Under Construction Karnataka State Road Transport Corporation (KSRTC) Karnataka 09-Nov-2019
196 Construction of NH-4B from km.21.200 to Km.27.270 and from km.0.000 to Km.4.492 of JNPT Phase-II (PKG-IV)* 10.60 KM (Kilometer) 590 Transport Roads and bridges Under Construction National Highways Authority of India (NHAI) Maharashtra 09-Nov-2019
197 Construction of Nimbahera bye-pass # 13.50 KM (Kilometer) 31.48 Transport Roads and bridges Completed Public Works Department, Rajasthan Rajasthan 09-Nov-2019
198 Construction of Pali Bye pass on Jodhpur - Sumerpur Road # 11.50 KM (Kilometer) 30 Transport Roads and bridges Completed Public Works Department, Rajasthan Rajasthan 09-Nov-2019
199 Construction of railway over bridge on Vadodara-Savli-Timba road in length of 60.0 Km in Vadodara district* 60.0 KM (Kilometer) 21.98 Transport Roads and bridges Pre-construction Stage Roads and Buildings Department, Gujarat Gujarat 09-Nov-2019
200 Container Terminal at Diamond Harbour (Kolkata Port) * Not Available 705.88 Transport Ports (excluding captive) Not Available Kolkata Port Trust West Bengal 09-Nov-2019
201 Delhi-Meerut Expressway and other connecting roads including 6/8 laning of NH24, NH58,NH235 on DBFOT(Toll) basis* 150.147 KM (Kilometer) 10000 Transport Roads and bridges Under Construction Ministry of Road Transport and Highways Multi State/ Centre 09-Nov-2019
202 Design Construction finance O&M of 2 lane bridge across Musi river of Miryalguda Kodad Road including approa* 0.54 14.5 Transport Roads and bridges Under Construction Andhra Pradesh Road Development Corporation Andhra Pradesh 09-Nov-2019
203 Design Construction Finance Operation and Maintenance of Four Laning of Khammam Tallada Devarapalli Road under PPP* Not Available 660 Transport Roads and bridges Not Available Andhra Pradesh Road Development Corporation Andhra Pradesh 09-Nov-2019
204 Design Construction Finance Operation and Maintenance of Four Laning of Perecherla Thokapalli Road under PPP* Not Available 522 Transport Roads and bridges Not Available Andhra Pradesh Road Development Corporation Andhra Pradesh 09-Nov-2019
205 Design Construction Finance Operation and Maintenance of Four Laning of Warangal Khammam Road under PPP* Not Available 476 Transport Roads and bridges Not Available Andhra Pradesh Road Development Corporation Andhra Pradesh 09-Nov-2019
206 Development of 7 MLD water supply project at Bekal Kasargod Dist * 7.0 MLD (Millons Liter per day) 17 Water Sanitation Water supply pipeline Under Construction Bekal Resorts Development Corporation Limited Kerala 09-Nov-2019
207 Development of Adiquate Road Connectivity to Chennai -Ennore Port Connectivity* 29.0 KM (Kilometer) 600 Transport Roads and bridges Under Construction National Highways Authority of India (NHAI) Tamil Nadu 09-Nov-2019
208 Development of CBD in South TT Nagar Bhopal * Not Available 1500 Social and Commercial Infrastructure Common infrastructure for industrial parks, SEZ Not Available Madhya Pradesh Housing Board Madhya Pradesh 09-Nov-2019
209 Development of existing 4-lane road from Bangalore to Hunsur via Mysore and other Connecting roads into 6-lane roads* 201.12 KM (Kilometer) 621.46 Transport Roads and bridges Not Available Karnataka Road Development Corporation Limited (KRDCL) Karnataka 09-Nov-2019
210 Development of Four lane of Mangwan to MP/UP border section (km 98/2 to km 46/6) of NH 27 on DBFOT (Toll) basis 52.1 KM (Kilometer) 410.7 Transport Roads and bridges Under Construction Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 09-Nov-2019
211 Development of Hoshiarpur - Phagwara Road Project* 35.5 KM (Kilometer) 32.53 Transport Roads and bridges Under Construction Public Works Department, Punjab Punjab 09-Nov-2019
212 Development of Integrated Solid Waste Treatment (100 TPD) and Landfill Facilities at Belgaum * 100.0 TPD (Tonne per day) 5.12 Water Sanitation Solid waste management Under Construction Belagavi City Corporation Karnataka 09-Nov-2019
213 Development of International Convention Centre at Devanahalli * Not Available 1050 Social and Commercial Infrastructure Tourism Under Construction Department of Tourism, Karnataka Karnataka 09-Nov-2019
214 Development of logistic park at Batasingaram on 40 acres * 40.0 Acres 20 Social and Commercial Infrastructure Common infrastructure for industrial parks, SEZ Pre-construction Stage Hyderabad Metropolitan Development Authority Telangana 09-Nov-2019
215 Development of logistic park at Mangalpalli on 22 acres * 22.0 Acres 20 Social and Commercial Infrastructure Common infrastructure for industrial parks, SEZ Under Construction Hyderabad Metropolitan Development Authority Telangana 09-Nov-2019
216 Development of minor sea port at vizhinjam on DBFOT basis * 600,000.0 TEU (Twenty-foot Equivalent Units) 4089 Transport Ports (excluding captive) Under Construction Vizhinjam International Sea Port Limited Kerala 09-Nov-2019
217 Development of multi-cargo berth no. 13 at Deendayal Port * 100,000.0 TEU (Twenty-foot Equivalent Units) 0 Transport Ports (excluding captive) Not Available Deendayal Port Trust Gujarat 09-Nov-2019
218 Development of Navlakhi Port with a capacity of 4.5 MMTPA in Rajkot district * 4.5 MMTPA (million metric tonnes per annum) 450 Transport Ports (excluding captive) Under Construction Gujarat Maritime Board (GMB) Gujarat 09-Nov-2019
219 Development of Railway Over Bridges in Gujarat* Not Available 198 Transport Roads and bridges Pre-construction Stage Roads and Buildings Department, Gujarat Gujarat 09-Nov-2019
220 Development of resorts at Bekal in Kasaragod District * 9999 55 Social and Commercial Infrastructure Tourism Under Construction Bekal Resorts Development Corporation Limited Kerala 09-Nov-2019
221 Development of road from Afzalpur-Ghattarga Sarasamba with Ribbanapalli and other connecting roads* 253.69 KM (Kilometer) 530.09 Transport Roads and bridges Not Available Karnataka Road Development Corporation Limited (KRDCL) Karnataka 09-Nov-2019
222 Development of road from Annigere-Navalgund-Datnal-Ron and other connecting roads* 241.95 KM (Kilometer) 505.65 Transport Roads and bridges Not Available Karnataka Road Development Corporation Limited (KRDCL) Karnataka 09-Nov-2019
223 Development of road from Arsikere-Gandasi-Channarayapatna-Kikkeri-K R Pet-Chinakurali-Pandavapur SH-07 * 159.72 KM (Kilometer) 334.62 Transport Roads and bridges Not Available Karnataka Road Development Corporation Limited (KRDCL) Karnataka 09-Nov-2019
224 Development of road from Badravathi-Shimoga-Honalli-Shikaripura SH-57 and other connecting roads* 312.61 KM (Kilometer) 653.17 Transport Roads and bridges Not Available Karnataka Road Development Corporation Limited (KRDCL) Karnataka 09-Nov-2019
225 Development of road from Bangalore-Magadi-Huliyuru Durga and other connecting roads* 177.54 KM (Kilometer) 732.92 Transport Roads and bridges Not Available Karnataka Road Development Corporation Limited (KRDCL) Karnataka 09-Nov-2019
226 Development of road from Bidar to Humnabad SH-105 and other connecting roads* 112.74 KM (Kilometer) 235.59 Transport Roads and bridges Not Available Karnataka Road Development Corporation Limited (KRDCL) Karnataka 09-Nov-2019
227 Development of road from Channagiri-Davanagere-Jaglur SH-65 and other connecting road SH-45* 154.8 KM (Kilometer) 320.34 Transport Roads and bridges Not Available Karnataka Road Development Corporation Limited (KRDCL) Karnataka 09-Nov-2019
228 Development of road from Chikkaballapur NH-7 Vijipur-Vemagal-Kolar-Nandi cross and other connecting roads* 152.91 KM (Kilometer) 319.64 Transport Roads and bridges Not Available Karnataka Road Development Corporation Limited (KRDCL) Karnataka 09-Nov-2019
229 Development of road from Chikkaballapura-Nandi-Doddaballapur-Maduray-Nelamangala-Taverekere-Kengeri-Jigani-Ane* 194.23 KM (Kilometer) 406.13 Transport Roads and bridges Not Available Karnataka Road Development Corporation Limited (KRDCL) Karnataka 09-Nov-2019
230 Development of road from Devangaon bridge-Afzalpur-Gulbarga and other connecting roads* 246.08 KM (Kilometer) 514.6 Transport Roads and bridges Not Available Karnataka Road Development Corporation Limited (KRDCL) Karnataka 09-Nov-2019
231 Development of road from Devangaon-Vibuthihal-Indi-Atharga-Bijapur SH-34 and other connecting roads* 145.0 KM (Kilometer) 302.51 Transport Roads and bridges Not Available Karnataka Road Development Corporation Limited (KRDCL) Karnataka 09-Nov-2019
232 Development of road from Gangavathi -NH-63 at Koppal-Mundargi and other connecting roads* 180.31 KM (Kilometer) 735.97 Transport Roads and bridges Not Available Karnataka Road Development Corporation Limited (KRDCL) Karnataka 09-Nov-2019
233 Development of road from Gangavathi-Karatgi-Sindanoor-Kalmali joining SH-20 SH-23 and other connecting roads* 229.49 KM (Kilometer) 480.58 Transport Roads and bridges Not Available Karnataka Road Development Corporation Limited (KRDCL) Karnataka 09-Nov-2019
234 Development of road from Gorabal on SH-23-Dhadesugur-Desanur-Sindegeri-Bellary and other connecting roads* 171.44 KM (Kilometer) 697.46 Transport Roads and bridges Not Available Karnataka Road Development Corporation Limited (KRDCL) Karnataka 09-Nov-2019
235 Development of road from Haveri-Hirekeruru-Thalagundi-Soraba-Sagar road and other connecting road* 185.05 KM (Kilometer) 387.11 Transport Roads and bridges Not Available Karnataka Road Development Corporation Limited (KRDCL) Karnataka 09-Nov-2019
236 Development of road from Hoskote-Mallur-Tekal-Bangarpet-Baythmangal-AP Border SH-95 and connecting roads* 143.1 KM (Kilometer) 585.33 Transport Roads and bridges Not Available Karnataka Road Development Corporation Limited (KRDCL) Karnataka 09-Nov-2019
237 Development of road from Huliyur-Tiptur-Nuggenahalli-Shravanabelagola road SH-47 and other connecting roads* 107.36 KM (Kilometer) 227.89 Transport Roads and bridges Not Available Karnataka Road Development Corporation Limited (KRDCL) Karnataka 09-Nov-2019
238 Development of road from Hunsur-Verajpet Madakeri-Somavarpet road and other connecting roads* 273.24 KM (Kilometer) 572.1 Transport Roads and bridges Not Available Karnataka Road Development Corporation Limited (KRDCL) Karnataka 09-Nov-2019
239 Development of road from Kadur-Chikkamangalur-Mudigere-Belthangadi-Bantwal road SH-64* 161.94 KM (Kilometer) 338.13 Transport Roads and bridges Not Available Karnataka Road Development Corporation Limited (KRDCL) Karnataka 09-Nov-2019
240 Development of road from Katak-Chincholi-Jalasangi from Maharashtra border near Kamlanagar-Sangam-AP Border ne* 214.15 KM (Kilometer) 447.83 Transport Roads and bridges Not Available Karnataka Road Development Corporation Limited (KRDCL) Karnataka 09-Nov-2019
241 Development of road from Kushalnagara-Madikere-Sampaji-Sulya-Puttur joining NH-48 SH-88 and other connecting roads* 174.67 KM (Kilometer) 365.09 Transport Roads and bridges Not Available Karnataka Road Development Corporation Limited (KRDCL) Karnataka 09-Nov-2019
242 Development of road from Lokapur to Mudhol SH-34 Mudhol-Sidapur-Kanakawadi-Nipani SH-18 and other connecting roads* 181.80 KM (Kilometer) 380.22 Transport Roads and bridges Not Available Karnataka Road Development Corporation Limited (KRDCL) Karnataka 09-Nov-2019
243 Development of road from Lokapura-Halki-Mallapur to join NH-4 near Gotur and other connecting roads* 164.11 KM (Kilometer) 340.55 Transport Roads and bridges Not Available Karnataka Road Development Corporation Limited (KRDCL) Karnataka 09-Nov-2019
244 Development of road from Lokapura-Varchagal-Govanakop and other connecting roads* 283.10 KM (Kilometer) 576.97 Transport Roads and bridges Not Available Karnataka Road Development Corporation Limited (KRDCL) Karnataka 09-Nov-2019
245 Development of road from Maharashtra border to Sankeshwara - Navalihal SH-12 and other connecting roads, Belgaum* 161.50 KM (Kilometer) 335.6 Transport Roads and bridges Not Available Karnataka Road Development Corporation Limited (KRDCL) Karnataka 09-Nov-2019
246 Development of road from Mandya-Dudda-Melukote-Santhebachalli-Sravanabelagola-Channarayapatha SH-47* 284.87 KM (Kilometer) 595.56 Transport Roads and bridges Not Available Karnataka Road Development Corporation Limited (KRDCL) Karnataka 09-Nov-2019
247 Development of road from Mangalore-Shimoga NH-13 to NH-48 via Belthangadi-Kokkada SH-37 and other connecting roads* 175.22 KM (Kilometer) 366.87 Transport Roads and bridges Not Available Karnataka Road Development Corporation Limited (KRDCL) Karnataka 09-Nov-2019
248 Development of road from Mysore-Bannur-Mallavali-Maddur-Huliyuru durga-Kunigal-Tumkur-Koratagere SH-33* 313.92 KM (Kilometer) 656.6 Transport Roads and bridges Not Available Karnataka Road Development Corporation Limited (KRDCL) Karnataka 09-Nov-2019
249 Development of road from Mysore-Manadwadi SH-33 road and other connecting roads* 114.10 KM (Kilometer) 238.25 Transport Roads and bridges Not Available Karnataka Road Development Corporation Limited (KRDCL) Karnataka 09-Nov-2019
250 Development of road from Nanjangud-Chamarajnagar and other connecting roads* 250.10 KM (Kilometer) 522.45 Transport Roads and bridges Not Available Karnataka Road Development Corporation Limited (KRDCL) Karnataka 09-Nov-2019
251 Development of road from NH-13 near Hungund-Mudagal SH-20 Sindhanur-Lingasugur-Maski-Chikmudbal to NH-218 at Jewargi* 224.46 KM (Kilometer) 469.02 Transport Roads and bridges Not Available Karnataka Road Development Corporation Limited (KRDCL) Karnataka 09-Nov-2019
252 Development of road from NH-17 Kundapura-Thirthhalli road SH-52* 81.81 KM (Kilometer) 171.27 Transport Roads and bridges Not Available Karnataka Road Development Corporation Limited (KRDCL) Karnataka 09-Nov-2019
253 Development of road from NH-218 to Mulawad- Babaleshwar-Mudhol and other connecting roads* 222.41 KM (Kilometer) 464.23 Transport Roads and bridges Not Available Karnataka Road Development Corporation Limited (KRDCL) Karnataka 09-Nov-2019
254 Development of road from Raichur to Bachi Bachi to Hungund SH-20* 199.37 KM (Kilometer) 416.71 Transport Roads and bridges Not Available Karnataka Road Development Corporation Limited (KRDCL) Karnataka 09-Nov-2019
255 Development of road from Ramdurga-Chunchur-Manoli-Sogal-Bailhongal-Chikkabagewadi-Bagewai and other connecting roads* 211.78 KM (Kilometer) 442.67 Transport Roads and bridges Not Available Karnataka Road Development Corporation Limited (KRDCL) Karnataka 09-Nov-2019
256 Development of road from SH-53 near Kudachi-Raibag-Bagewadi-Zangathaal SH-73 and other connecting roads, Belgaum* 130.52 KM (Kilometer) 272.89 Transport Roads and bridges Not Available Karnataka Road Development Corporation Limited (KRDCL) Karnataka 09-Nov-2019
257 Development of road from Shiraguppi-Molwad-Ainapur SH-72 and other connecting roads* 201.0 KM (Kilometer) 410.91 Transport Roads and bridges Not Available Karnataka Road Development Corporation Limited (KRDCL) Karnataka 09-Nov-2019
258 Development of road from Tadas-Mundgod-Sirsi-Sampakhand-Kumta road SH-69* 136.74 KM (Kilometer) 285.78 Transport Roads and bridges Not Available Karnataka Road Development Corporation Limited (KRDCL) Karnataka 09-Nov-2019
259 Development of road from Tawargere - Hulihyder-Kanakgeri-Gonal-Chikka Jantakal - Kuditheni SH-29* 146.26 KM (Kilometer) 598.09 Transport Roads and bridges Not Available Karnataka Road Development Corporation Limited (KRDCL) Karnataka 09-Nov-2019
260 Development of road from TN Border-Kodihalli-Kanakpura-Ramnagar-Magadi-Solur-Davaspet-Kottigere SH-03* 223.73 KM (Kilometer) 467.92 Transport Roads and bridges Not Available Karnataka Road Development Corporation Limited (KRDCL) Karnataka 09-Nov-2019
261 Development of road from Yaragatti-Thavalgeri-Maldinni near SH-31 Nesargi to AP Border near Ananthapur SH-31* 212.55 KM (Kilometer) 869.25 Transport Roads and bridges Not Available Karnataka Road Development Corporation Limited (KRDCL) Karnataka 09-Nov-2019
262 Development of road Hassan-Arakalgud-Ramnathpura-Piriyapatna and other connecting roads* 91.63 KM (Kilometer) 377.29 Transport Roads and bridges Not Available Karnataka Road Development Corporation Limited (KRDCL) Karnataka 09-Nov-2019
263 Development of road Shimoga-Honnalli-Harapanahalli-Kudligi-Sandur-Thoranagal and other connecting roads* 216.85 KM (Kilometer) 887.05 Transport Roads and bridges Not Available Karnataka Road Development Corporation Limited (KRDCL) Karnataka 09-Nov-2019
264 Development of road Sira-Madugiri-Gowribidanur-Chikkaballapura-Shidalgatta-Chithamani-Srinivasapur-Mulbagal SH-58* 358.1 KM (Kilometer) 1464.82 Transport Roads and bridges Not Available Karnataka Road Development Corporation Limited (KRDCL) Karnataka 09-Nov-2019
265 Development of road Thamilnadu border to Attibele-Sarjapur-Hoskote-Jangamakote-Shidlgatta join SH-58 * 89.12 KM (Kilometer) 364.64 Transport Roads and bridges Not Available Karnataka Road Development Corporation Limited (KRDCL) Karnataka 09-Nov-2019
266 Development of Sirhind - Morinda - Ropar* 55.42 KM (Kilometer) 70.25 Transport Roads and bridges Under Construction Public Works Department, Punjab Punjab 09-Nov-2019
267 Development of Tourism Infrastructure Projects at Belur * 7.0 Acres 28 Social and Commercial Infrastructure Tourism Pre-construction Stage Department of Tourism, Karnataka Karnataka 09-Nov-2019
268 Development of Tourism Infrastructure Projects at Bijapur * 5.0 Acres 21 Social and Commercial Infrastructure Tourism Not Available Department of Tourism, Karnataka Karnataka 09-Nov-2019
269 Development of two lane carriageway to Dabadeh to Bhawan Mandi* Not Available 96 Transport Roads and bridges Under Construction Rajasthan State Road Development and Construction Corporation Limited Rajasthan 09-Nov-2019
270 Development of Various Tourism Facilities in Pilikula * Not Available 80 Social and Commercial Infrastructure Tourism Pre-construction Stage Department of Tourism, Karnataka Karnataka 09-Nov-2019
271 Development, Construction, Operation and Maintenance of An Integrated Municipal Waste Processing and Disposal Facility At Okhla* 950.0 TPD (Tonne per day) 65 Water Sanitation Solid waste management Under Construction New Delhi Municipal Council Delhi (UT) 09-Nov-2019
272 Development, O&M of Gadoj-Majri to Haryana/ Rajasthan Border and Majri to Neemrana under DBFOT (Toll) Basis* 46.4 KM (Kilometer) 88.01 Transport Roads and bridges Pre-construction Stage Public Works Department, Rajasthan Rajasthan 09-Nov-2019
273 District Central Library at Visakapatnam * Not Available 25 Social and Commercial Infrastructure Education Under Construction Andhra Pradesh Industrial Infrastructure Corporation Limited (APIIC) Andhra Pradesh 09-Nov-2019
274 Door to Door Collection of Solid waste Composting and Landfill at Dehradun * Not Available 24.56 Water Sanitation Solid waste management Under Construction Dehradun Nagar Nigam Uttarakhand 09-Nov-2019
275 Door to Door Collection of Solid waste Composting and Landfill at Nainital * Not Available 9.83 Water Sanitation Solid waste management Under Construction Nainital Municipality Uttarakhand 09-Nov-2019
276 Drama Theatre Complex Majiwada * 1.40 Acres 30 Social and Commercial Infrastructure Tourism Under Construction Thane Municipal Corporation Maharashtra 09-Nov-2019
277 Eastern Peripheral Expressway (NH No. NE-II) 134.95 KM (Kilometer) 6588.9 Transport Roads and bridges Operation and Maintenance Stage Ministry of Road Transport and Highways Haryana 09-Nov-2019
278 Eco Tourism Park - Rewa * 5.78 15.68 Social and Commercial Infrastructure Tourism Under Construction Madhya Pradesh Ecotourism Development Board Madhya Pradesh 09-Nov-2019
279 Establishment of 2 x 10 MWp SPV power plant at Atam Pahad, South Andaman * 20.0 MW (Mega Watt) 130.76 Energy Renewable energy (grid) Pre-construction Stage Andaman and Nicobar Administration Andaman & Nicobar Islands (UT) 09-Nov-2019
280 Four laining with PSS of Kaithal to Rajasthan Border section of NH 152/65 from km 33.250 to km 243.58 under NHDP IV 166.25 KM (Kilometer) 2290 Transport Roads and bridges Operation and Maintenance Stage Ministry of Road Transport and Highways Multi State/ Centre 09-Nov-2019
281 Four laning elevated road from Chennai Port gate No. 10 to Maduravoyal (NH 4) in the state of Tamil nadu 18.0 KM (Kilometer) 1345 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Tamil Nadu 09-Nov-2019
282 Four laning of Ambala - Kaithal section of NH-65 including Ambala Bypass inHaryana on BOT (Toll) project on DBFOT (Toll) basis 95.383 KM (Kilometer) 878 Transport Roads and bridges Operation and Maintenance Stage Ministry of Road Transport and Highways Haryana 09-Nov-2019
283 Four laning of Amravati to Chikhli Section of NH-6 from Km 166.00 to Km 360.00 in the state of Maharashtra under NHDP Phase IV 194.0 KM (Kilometer) 2288.18 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Maharashtra 09-Nov-2019
284 Four laning of Balance connectivity road from Visakhapatnam Port to NH5 4.2 KM (Kilometer) 100.32 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Andhra Pradesh 09-Nov-2019
285 Four laning of Barasat-Krishnagar section of NH 34 in West Bengal under NHDP Phase III on BOT (Annuity) basis* 84.0 KM (Kilometer) 886.73 Transport Roads and bridges Under Construction National Highways Authority of India (NHAI) West Bengal 09-Nov-2019
286 Four laning of Barhi to Hazaribagh section of NH 33 in Jharkhand� 40.5 KM (Kilometer) 562.34 Transport Roads and bridges Operation and Maintenance Stage Ministry of Road Transport and Highways Jharkhand 09-Nov-2019
287 Four laning of Bhavnagar-Talaja road in length of 46.5 km in Bhavnagar under NHDP-IV 48.04 KM (Kilometer) 998.18 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Gujarat 09-Nov-2019
288 Four laning of Bhubaneshwar - Puri section of NH 203 in Orissa� 67.25 KM (Kilometer) 500.29 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Odisha 09-Nov-2019
289 Four laning of BRT Tiger Reserve Boundary-Bengaluru section in 174.1 Km in Bengaluru district 170.9 KM (Kilometer) 1008 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Karnataka 09-Nov-2019
290 Four laning of fagne to Gujarat-Maharashtra Border section of NH 6 from Km 510 to Km 650.79 in Maharashtra under NHDP Phase IV 140.79 KM (Kilometer) 1885.74 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Maharashtra 09-Nov-2019
291 Four laning of Farakka-Raiganj section of NH 34 from km 295 to km 398 inWest Bengal on DBFOT basis unde+B218r NHDP III 103.0 KM (Kilometer) 1056.56 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) West Bengal 09-Nov-2019
292 Four laning of Goa/Karnataka Border-Kundapur road in length of 189.6 km under NHDP-IV 189.6 KM (Kilometer) 1655.01 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Multi State/ Centre 09-Nov-2019
293 Four laning of Goa/Karnataka border-Panaji, Goa stretch of NH 4A of Goa* Not Available 382.46 Transport Roads and bridges Under Construction Ministry of Road Transport and Highways Goa 09-Nov-2019
294 Four laning of Godhara to Gujarat/MP border section of NH 59 in the State of Gujarat under NHDP Phase III on DBFOT pattern Not Available 855.55 Transport Roads and bridges Operation and Maintenance Stage Ministry of Road Transport and Highways Gujarat 09-Nov-2019
295 Four laning of Guna to Biaora section of NH 3 from Km 332.100 to Km 426.100 in the state of Madhya Pradesh under NHDP phase IV 93.5 KM (Kilometer) 1081.9 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Madhya Pradesh 09-Nov-2019
296 Four laning of Gwalior - Shivpuri section of NH 3 from km 15.600 to NH 75 to km 236 inMadhya Pradesh on BOT (Toll) basis. 220.40 KM (Kilometer) 1500 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Madhya Pradesh 09-Nov-2019
297 Four laning of Haridwar-Dehradun Section of NH 58 & 72 in the state of Uttarakhand-BOT(Annuity) basis 39.0 KM (Kilometer) 1021 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Uttarakhand 09-Nov-2019
298 Four laning of Indore-Jhabua-Gujarat/MP border section of NH 59 in Madhya Pradesh on BOT (Toll) basis under NHDP III 155.15 KM (Kilometer) 1297 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Multi State/ Centre 09-Nov-2019
299 Four laning of Jalna-Deoulgaonraja-Berala Phata including Deoulgaonraja bypass* 77.41 KM (Kilometer) 125.8 Transport Roads and bridges Under Construction Public Works Department, Maharashtra Maharashtra 09-Nov-2019
300 Four laning of Jhansi-Khajuraho section in length of 85.4 km Package-II 85.40 KM (Kilometer) 1184.71 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Multi State/ Centre 09-Nov-2019
301 Four Laning of Jorabat-Barapani section from km 0 to 61.8 of NH 40 under SARDP NE Phase A on BOT Annuity basis.* 61.80 KM (Kilometer) 536 Transport Roads and bridges Under Construction National Highways Authority of India (NHAI) Meghalaya 09-Nov-2019
302 Four laning of Kagavadar-Una section in length of 40.6 km in Bhavnagar district 40.98 KM (Kilometer) 723.64 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Gujarat 09-Nov-2019
303 Four laning of Kalmath-Zarap section in length of 44.2 km in Sindhudurg district 44.20 KM (Kilometer) 914 Transport Roads and bridges Operation and Maintenance Stage Ministry of Road Transport and Highways Maharashtra 09-Nov-2019
304 Four laning of Karaikkudi-Ramanathapuram section of NH-210 (101 kms)inTamil Nadu under NHDP Phase III on BOT basis. 100.0 KM (Kilometer) 599.41 Transport Roads and bridges Operation and Maintenance Stage Ministry of Road Transport and Highways Tamil Nadu 09-Nov-2019
305 Four laning of Kashedi-Khavati to Parshuram Ghat in length in Ratnagiri district # * 43.8 KM (Kilometer) 579.5 Transport Roads and bridges Pre-construction Stage Ministry of Road Transport and Highways Maharashtra 09-Nov-2019
306 Four Laning of Kerala/ Tamil Nadu border, Kanyakumari section of NH 47 (Package II) 56.0 KM (Kilometer) 851.05 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Tamil Nadu 09-Nov-2019
307 Four laning of Khagaria-Bhaktiarpur section of NH31 in the state of Bihar* Not Available 1703.82 Transport Roads and bridges Under Construction Ministry of Road Transport and Highways Bihar 09-Nov-2019
308 Four laning of Krishnanagar-Baharampur section of NH 34 from Km 115 to km 193 in the State of West Bengal�+B235 78.0 KM (Kilometer) 708.26 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) West Bengal 09-Nov-2019
309 Four Laning of Lucknow Sultanpur Section of NH-56 on Hybrid Annuity Mode Not Available 1638.44 Transport Roads and bridges Operation and Maintenance Stage Ministry of Road Transport and Highways Uttar Pradesh 09-Nov-2019
310 Four laning of Lucknow-Sultanpur Section of NH 56 from KM 11.5 to KM 135 under NHDP IV 125.90 KM (Kilometer) 1276 Transport Roads and bridges Operation and Maintenance Stage Ministry of Road Transport and Highways Uttar Pradesh 09-Nov-2019
311 Four laning of Ludhiana-Talwandi section of NH 95 from km 92 to km 170 inPunjab under BOT (Toll) NHDP III on DBFOT� 78.0 KM (Kilometer) 479 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Punjab 09-Nov-2019
312 Four laning of Mahagaon-Yavatmal section in length of 80 km under NHDP-IV 80.19 KM (Kilometer) 1098 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Maharashtra 09-Nov-2019
313 Four Laning of Maharashtra/Karnataka Border-Sangareddy Section from 348.0 km to 423.8 km on BOT (Toll) 145.0 KM (Kilometer) 1544.18 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Multi State/ Centre 09-Nov-2019
314 Four laning of Meerut-Karnal Road in SH 82 in the State of Uttar Pradesh* 87.15 KM (Kilometer) 583.23 Transport Roads and bridges Under Construction Uttar Pradesh State Highways Authority Uttar Pradesh 09-Nov-2019
315 Four laning of MP/Maharashtra border-Nagpur section of NH7 including Kamptee-Kahnan and Nagpur bypass in Maharashtra 34.0 KM (Kilometer) 1133.84 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Maharashtra 09-Nov-2019
316 Four laning of Muzaffarnagar-Haridwar section of NH 58 from km 131 to 211 of NH 58 in the state of UP and Uttarakhand 80.0 KM (Kilometer) 1563.55 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Multi State/ Centre 09-Nov-2019
317 Four laning of Nagapatnam-Thanjavur section of NH 67 from km 1.600 to km 80.00 in Tamil Nadu on BOT (Toll) basis 78.40 KM (Kilometer) 619 Transport Roads and bridges Operation and Maintenance Stage Ministry of Road Transport and Highways Tamil Nadu 09-Nov-2019
318 Four laning of Nagina Kashipur Section of NH 74 from KM 71.614 to KM 170.407 under NHDP IV 98.793 KM (Kilometer) 2536 Transport Roads and bridges Operation and Maintenance Stage Ministry of Road Transport and Highways Multi State/ Centre 09-Nov-2019
319 Four laning of Orissa/Chhattisgarh Border - Aurang of NH-6 in length of 150.4 Km under NHDP-IV 150.4 KM (Kilometer) 1232 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Multi State/ Centre 09-Nov-2019
320 Four Laning of Osmanabad (Yedshi)- Latur- Nanded Road* Not Available 300.19 Transport Roads and bridges Under Construction Public Works Department, Maharashtra Maharashtra 09-Nov-2019
321 Four laning of Pandoh bypass to Takoli section in length of 20.7 km 20.7 KM (Kilometer) 2600 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Himachal Pradesh 09-Nov-2019
322 Four laning of Parshuram Ghat-Arawali section in length of 35.9 km in Ratnagiri district # * 35.90 KM (Kilometer) 670 Transport Roads and bridges Pre-construction Stage Ministry of Road Transport and Highways Maharashtra 09-Nov-2019
323 Four laning of Ranchi Jamshedpur section of NH33 in the State of Bihar on BoT (Annuity) under NHDP Phase III 163.5 KM (Kilometer) 1479 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Jharkhand 09-Nov-2019
324 Four laning of Sambalpur - Rourkela section of SH-10 from km 4.900 to to km 167.900 (Rourkela) under DBFOT* 163.0 KM (Kilometer) 1564.94 Transport Roads and bridges Under Construction Public Works Department, Odisha Odisha 09-Nov-2019
325 Four laning of Shiroli-Sangli-Kolhapur Project in length of 40.11 KM in Kolhapur District* 40.1 KM (Kilometer) 330 Transport Roads and bridges Under Construction Public Works Department, Maharashtra Maharashtra 09-Nov-2019
326 Four laning of Shivpuri - Dewas section of NH3 from km 15.623 to km 566.45 in Madhya Pradesh on BOT (Toll) basis. Not Available 2815 Transport Roads and bridges Operation and Maintenance Stage Ministry of Road Transport and Highways Madhya Pradesh 09-Nov-2019
327 Four laning of Singhara-Bhinjhabal Section of NH6 from KM 310.806 to KM 414.982 under NHDP IV 103.79 KM (Kilometer) 1288.07 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Odisha 09-Nov-2019
328 Four laning of Solapur-Bijapur section of� NH 13 under NHDP Phase III from 0 110.542km in Maharashtra and Karnataka 111.0 KM (Kilometer) 1377.54 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Maharashtra 09-Nov-2019
329 Four Laning of Solapur-Maharashtra/Karnataka border section in length of 99.8 km in Solapur under NHDP-III 100.06 KM (Kilometer) 923.04 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Maharashtra 09-Nov-2019
330 Four laning of Sultanpur-Varanasi Section of NH-56 from km 134.700 to km 271.300 in Uttar Pradesh on DBFOT (Toll) basis. 146.225 KM (Kilometer) 1778 Transport Roads and bridges Operation and Maintenance Stage Ministry of Road Transport and Highways Uttar Pradesh 09-Nov-2019
331 Four laning of Tarsod-Fagne section of NH-6 in length of 87.3 Km in Jalgaon district 87.3 KM (Kilometer) 1064.88 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Maharashtra 09-Nov-2019
332 Four laning of Thanjavur-Trichy road in length of 56 km on NH-67 in Tiruchirappalli under NHDP -III 56.4 KM (Kilometer) 390 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Tamil Nadu 09-Nov-2019
333 Four Laning of Trichy city Junction with NH-45 B on NH-67 to Karur on NH-67 in Tamil Nadu under NHDP Phase III A on BOT basis 79.7 KM (Kilometer) 516 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Tamil Nadu 09-Nov-2019
334 Four laning of Tuljapur-Ausa road in length of 67 km under NHDP-IV 67.4 KM (Kilometer) 904.16 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Maharashtra 09-Nov-2019
335 Four laning of Una-Kodinar road in length of 41.1 Km in Junagadh district 41.1 KM (Kilometer) 763.08 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Gujarat 09-Nov-2019
336 Four Laning of Vijaywada-Machilipatnam section of NH 9 under NHDP Phase III, length 64.611 km Not Available 1462.32 Transport Roads and bridges Operation and Maintenance Stage Ministry of Road Transport and Highways Andhra Pradesh 09-Nov-2019
337 Four laning of Waranga-Mahagaon section in length of 66.9 km 66.90 KM (Kilometer) 1059.73 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Maharashtra 09-Nov-2019
338 Four laning of Wardha-Butibori section in length of 59.2 km 59.20 KM (Kilometer) 800 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Maharashtra 09-Nov-2019
339 Four laning of Yavatmal-Wardha section in length of 64.9 km under NHDP-IV 64.9 KM (Kilometer) 988.34 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Maharashtra 09-Nov-2019
340 Four laning of Zirakpur to Patiala section of NH 64 under VGF Scheme, length 50.70 km 50.70 KM (Kilometer) 536.25 Transport Roads and bridges Operation and Maintenance Stage Ministry of Road Transport and Highways Punjab 09-Nov-2019
341 Four laning with paved shoulders of Bhopal to Biaora section in the state of Madhya Pradesh* 105.60 KM (Kilometer) 954.43 Transport Roads and bridges Under Construction Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 09-Nov-2019
342 Four laning with paved side shoulders of a section betwwen Jharpokharia Baleshwar 80.60 KM (Kilometer) 705.88 Transport Roads and bridges Operation and Maintenance Stage Ministry of Road Transport and Highways Odisha 09-Nov-2019
343 Four laning with PSS of Amritsar to Bathinda section� of NH - 15 from km 103 to km 287.5 in Punjab under NHDP - IV� 174.64 KM (Kilometer) 1899 Transport Roads and bridges Operation and Maintenance Stage Ministry of Road Transport and Highways Punjab 09-Nov-2019
344 Four laning with PSS of Aurangabad to Yedshi section on NH 211� from km 100 to km 290.2 in Maharashtra on DBFOT pattern 190.20 KM (Kilometer) 2429 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Maharashtra 09-Nov-2019
345 Four laning with PSS of Solapur to Yedshi section on NH 211� from km 0 to km 100 inMaharashtra on DBFOT pattern 100.0 KM (Kilometer) 972.5 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Maharashtra 09-Nov-2019
346 Four lanning of Binjhabahal-Telebani section in length of 78.3 km in Keonjhar district 78.31 KM (Kilometer) 1008.96 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Odisha 09-Nov-2019
347 Four-laning a section between Khed-Sinnar section of NH 50 from km 42 to km 177 in Maharashtra on BOT (Toll) basis.� 137.9 KM (Kilometer) 1348.2 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Maharashtra 09-Nov-2019
348 Four-laning a section between Yadgiri-Warangal section of NH 202 from km 54.000 to km 150.000 in AP on BOT (Toll) basis 99.103 KM (Kilometer) 1905 Transport Roads and bridges Operation and Maintenance Stage Ministry of Road Transport and Highways Andhra Pradesh 09-Nov-2019
349 Four-laning and Strengthening of the existing two lane stretches of NH5* Not Available 0 Transport Roads and bridges Not Available National Highways Authority of India (NHAI) Andhra Pradesh 09-Nov-2019
350 Four-laning Kiratpur- Ner Chowk Section from� Km 73.20 to Km 186.50 of NH-21 in Himachal Pradesh on BOT (Toll) basis 84.3 KM (Kilometer) 2291 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Himachal Pradesh 09-Nov-2019
351 Four-laning of a section under NHDP-IV, between Hubli - Hospet section of NH 63 on BOT (Toll) basis. 143.29 KM (Kilometer) 2119 Transport Roads and bridges Operation and Maintenance Stage Ministry of Road Transport and Highways Karnataka 09-Nov-2019
352 Four-Laning of Hospet, Bellary Section of NH-63 under NHDP Phase IV, length 95.44 km 95.0 KM (Kilometer) 1625 Transport Roads and bridges Operation and Maintenance Stage Ministry of Road Transport and Highways Karnataka 09-Nov-2019
353 Four-laning of Kashipur-Sitarganj Section of NH-74 from km 175 to km 252.2 in Uttarakhand and UP on BOT (Toll) basis 77.20 KM (Kilometer) 605.85 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Multi State/ Centre 09-Nov-2019
354 Four-laning of Meerut, Bulandshahar section of NH-235 from km 7.469 to km 73.156 in Uttar Pradesh on DBFOT (Toll) 65.7 KM (Kilometer) 869 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Uttar Pradesh 09-Nov-2019
355 Four/six laning of Bodare-Dhule section in length of 62.8 km under NHDP-IV 67.23 KM (Kilometer) 1315 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Andhra Pradesh 09-Nov-2019
356 Four/Six laning of Gandhidham-Mundra Port section of NH8A in Gujarat under NHDP Phase III on DBFOT pattern* 71.4 KM (Kilometer) 1315 Transport Roads and bridges Under Construction National Highways Authority of India (NHAI) Gujarat 09-Nov-2019
357 Four/Six laning of Ghaziabad-Aligarh section of NH 91under NHDP Phase III on BOT Basis. 126.0 KM (Kilometer) 1031.14 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Uttar Pradesh 09-Nov-2019
358 Four/Six Laning of Gujarat/Maharashtra Border-Surat-Hazira Port Section of NH 6 under NHDP Phase III 133.0 KM (Kilometer) 1509 Transport Roads and bridges Operation and Maintenance Stage Ministry of Road Transport and Highways Multi State/ Centre 09-Nov-2019
359 Four/Six laning of Panvel Indapur section of NH 17 in the State of Maharashtra 84.0 KM (Kilometer) 1206 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Maharashtra 09-Nov-2019
360 Four/six laning of Raipur-Bilaspur section of NH 200 from km 0.000 to km 127.650 in Chhattisgarh on BoT (Toll) basis* 126.525 KM (Kilometer) 1548.88 Transport Roads and bridges Pre-construction Stage Ministry of Road Transport and Highways Chhattisgarh 09-Nov-2019
361 Girls Polytechnic College (Baran) Project * 5.0 Acres 5.49 Social and Commercial Infrastructure Education Under Construction Directorate of Technical Education, Rajasthan Rajasthan 09-Nov-2019
362 Girls Polytechnic College (Jaisalmer) Project * 5.0 Acres 5.49 Social and Commercial Infrastructure Education Under Construction Directorate of Technical Education, Rajasthan Rajasthan 09-Nov-2019
363 Golf Course At Naya Quilla Hyderabad * Not Available 12.5 Social and Commercial Infrastructure Tourism Under Construction Andhra Pradesh Tourism Development Corporation Limited Telangana 09-Nov-2019
364 Grain Yard Project (Amravati) * Not Available 21.66 Social and Commercial Infrastructure Post-harvest storage infrastructure for agriculture and horticulture produce including cold storage Under Construction Agricultural Produce Market Committee (Amravati) Maharashtra 09-Nov-2019
365 Heritage Village Project (Amritsar) * Not Available 15 Social and Commercial Infrastructure Tourism Under Construction Punjab Heritage and Tourism Promotion Board Punjab 09-Nov-2019
366 High Level Bridge (Makhu) 0.72 KM (Kilometer) 60 Transport Roads and bridges Operation and Maintenance Stage Punjab Infrastrucrure Development Board Punjab 09-Nov-2019
367 Hop on Hop Tourist Bus Terminal * Not Available 25 Social and Commercial Infrastructure Tourism Under Construction Odisha Tourism Development Corporation (OTDC) Odisha 09-Nov-2019
368 Hospital (Dorando) Project # * 200.0 Beds 80.1 Social and Commercial Infrastructure Health Care Pre-construction Stage Ranchi Municipal Corporation Jharkhand 09-Nov-2019
369 Hospital (Wanjri) Project * Not Available 98.78 Social and Commercial Infrastructure Health Care Under Construction Nagpur Municipal Corporation Maharashtra 09-Nov-2019
370 Hubli-Dharwar Bypass* 30.0 KM (Kilometer) 68 Transport Roads and bridges Under Construction Ministry of Road Transport and Highways Karnataka 09-Nov-2019
371 I T Park (Parsodi) * Not Available 46 Social and Commercial Infrastructure Common infrastructure for industrial parks, SEZ Under Construction Nagpur Municipal Corporation Maharashtra 09-Nov-2019
372 IGIAT Multi Skill Development Centre Pulivendula, Kadappa District of AP * Not Available 25 Social and Commercial Infrastructure Education Under Construction Directorate of Employment and Training, Andhra Pradesh Andhra Pradesh 09-Nov-2019
373 Implementation of 17 MLD sewage treatment plant at Dudhali Nallah in Kolhapur * 17.0 MLD (Millons Liter per day) 21.5 Water Sanitation Sewage collection, treatment and disposal system Under Construction Kolhapur Municipal Corporation Maharashtra 09-Nov-2019
374 Implementation of 50 MLD sewage treatment plant at Ramana * 50.0 MLD (Millons Liter per day) 156 Water Sanitation Sewage collection, treatment and disposal system Pre-construction Stage Uttar Pradesh Jal Nigam Uttar Pradesh 09-Nov-2019
375 Implementation of 500 TPD, solid waste management unit at Brahmapuram * 500.0 TPD (Tonne per day) 350 Water Sanitation Solid waste management Pre-construction Stage Local Self Government Department, Kerala Kerala 09-Nov-2019
376 Implementation of common municipal solid waste management facility with a capacity of 180 TPD at Kacchar * 180.0 TPD (Tonne per day) 25.41 Water Sanitation Solid waste management Pre-construction Stage Bilaspur Municipal Corporation Chhattisgarh 09-Nov-2019
377 Implementation of integrated solid waste management project at Katni * 150.0 MTPA (Metric Tonne Per Annum) 35.4 Water Sanitation Solid waste management Under Construction Katni Municipal Corporation Madhya Pradesh 09-Nov-2019
378 Implementation of solid waste management unit in Badaun district * 55.0 TPD (Tonne per day) 13.02 Water Sanitation Solid waste management Under Construction Uttar Pradesh Jal Nigam Uttar Pradesh 09-Nov-2019
379 Implementation of solid waste management unit in Firozabad district * 130.0 TPD (Tonne per day) 13.69 Water Sanitation Solid waste management Under Construction Uttar Pradesh Jal Nigam Uttar Pradesh 09-Nov-2019
380 Implementation of solid waste management unit in Jaunpur district * 80.0 TPD (Tonne per day) 13.85 Water Sanitation Solid waste management Under Construction Uttar Pradesh Jal Nigam Uttar Pradesh 09-Nov-2019
381 Implementation of solid waste management unit in Mirzapur district * 100.0 TPD (Tonne per day) 18.1 Water Sanitation Solid waste management Under Construction Uttar Pradesh Jal Nigam Uttar Pradesh 09-Nov-2019
382 Improvements of Road from Yelahanka to Karnataka/AP border Section of SH9 on DBFOT (Toll) basis* 74.35 KM (Kilometer) 380.85 Transport Roads and bridges Under Construction Karnataka Road Development Corporation Limited (KRDCL) Karnataka 09-Nov-2019
383 Info Park (Bhubaneswar) * 54.0 Acres 500 Social and Commercial Infrastructure Common infrastructure for industrial parks, SEZ Under Construction Odisha Industrial Infrastructure Development Corporation Odisha 09-Nov-2019
384 Input Based Urban Electric Distribution Moradabad * Not Available 0 Energy Electricity Distribution Under Construction Paschimanchal Vidyut Vitran Nigam Limited Uttar Pradesh 09-Nov-2019
385 Installation of 100 Reverse Osmosis Plants in 100 villages * 100.0 Numbers 11.25 Water Sanitation Water treatment plants Under Construction Water Supply and Sanitation Department, Haryana Haryana 09-Nov-2019
386 Integrated Border Check Post (Maharashtra) Project - Modernisation* 22.0 Numbers 1000 Transport Roads and bridges Under Construction Maharashtra State Road Development Corporation Limited (MSRDC) Maharashtra 09-Nov-2019
387 Integrated Disposal & Landfill Facility (Mysuru) Project - JNNURM * 34.5 Acres 34.85 Water Sanitation Solid waste management Under Construction Mysuru City Corporation Karnataka 09-Nov-2019
388 Integrated Municipal Solid Waste Management Facility for Madurai City * 350.0 TPD (Tonne per day) 300 Water Sanitation Solid waste management Under Construction Madurai Municipal Corporation Tamil Nadu 09-Nov-2019
389 Integrated Municipal solid waste treatment Kannahalli * 500.0 MT (Metric Tonne ) 25 Water Sanitation Solid waste management Under Construction Bruhat Bengaluru Mahanagara Palike Karnataka 09-Nov-2019
390 Integrated Municipal solid waste treatment Mavalipura * 70.0 MTPD 40 Water Sanitation Solid waste management Under Construction Bruhat Bengaluru Mahanagara Palike Karnataka 09-Nov-2019
391 Integrated Solid Waste Management (Sambhal) Project * 75.0 TPD (Tonne per day) 12.23 Water Sanitation Solid waste management Under Construction Uttar Pradesh Jal Nigam Uttar Pradesh 09-Nov-2019
392 International Convention Centre in Orissa * 18.75 Acres 480 Social and Commercial Infrastructure Tourism Pre-construction Stage Odisha Industrial Infrastructure Development Corporation Odisha 09-Nov-2019
393 IT City (Lucknow) Project * 100.0 Acres 1500 Social and Commercial Infrastructure Common infrastructure for industrial parks, SEZ Under Construction Uttar Pradesh Electronics Corporation Limited Uttar Pradesh 09-Nov-2019
394 Jagraon Nakodar Road Project* 38.9 KM (Kilometer) 52.23 Transport Roads and bridges Under Construction Public Works Department, Punjab Punjab 09-Nov-2019
395 Jaipur City ring road project phase I* 47.0 KM (Kilometer) 890 Transport Roads and bridges Under Construction Jaipur development Authority Rajasthan 09-Nov-2019
396 Jal Mahal Tourism Project on 100 acres in Jaipur * 100.0 Acres 200 Social and Commercial Infrastructure Tourism Under Construction Rajasthan Tourism Development Coorporation Rajasthan 09-Nov-2019
397 Karnataka Urban Water Sector Improvement Project * Not Available 70 Water Sanitation Water supply pipeline Under Construction Karnataka Urban Infrastructure Development and Finance Corporation Karnataka 09-Nov-2019
398 Latur - Ausa - Lamjana Road 19.0 KM (Kilometer) 54 Transport Roads and bridges Operation and Maintenance Stage Public Works Department, Maharashtra Maharashtra 09-Nov-2019
399 Luxury Tourist Train Project * Not Available 32 Social and Commercial Infrastructure Tourism Under Construction Karnataka State Tourism Development Corporation Karnataka 09-Nov-2019
400 Modern Bus Terminus along with Commercial Facilities * Not Available 200 Transport Urban public transport (except rolling stock) Not Available Department of Commerce and Transport, Odisha Odisha 09-Nov-2019
401 Mrugavani National Park, Chilkur Eco-Tourism Project * Not Available 0 Social and Commercial Infrastructure Tourism Not Available Andhra Pradesh Forest Development Corporation Limited Andhra Pradesh 09-Nov-2019
402 Multiplex & Shopping Mall at Secunderabad * Not Available 26.74 Social and Commercial Infrastructure Common infrastructure for industrial parks, SEZ Under Construction Andhra Pradesh Tourism Development Corporation Limited Telangana 09-Nov-2019
403 National Games Housing Complex at Ranchi * Not Available 250 Social and Commercial Infrastructure Tourism Under Construction Department of Arts, Culture, Sports and Youth Affairs, Jharkhand Jharkhand 09-Nov-2019
404 Neyveli Lignite Fired Power Plant * 1000.0 MW (Mega Watt) 4256 Energy Electricity generation (grid) Under Construction Not Available Tamil Nadu 09-Nov-2019
405 Operation and Maintenance of 50 Skill Development Training Centres in 14 districts of Assam * Not Available 0 Social and Commercial Infrastructure Education Not Available Directorate of Welfare of Tea and Ex-Tea Garden Tribes, Assam Assam 09-Nov-2019
406 Package II Development of Tourism Infrastructure Projects at Badami Pattadakal & Aihole * 5.0 Acres 21 Social and Commercial Infrastructure Tourism Not Available Department of Tourism, Karnataka Karnataka 09-Nov-2019
407 Parking cum Logistics Hub at Mandideep for 500 trucks, Bhopal * 18.5 Acres 140 Transport Urban public transport (except rolling stock) Under Construction MP Audyogik Kendra Vikas Nigam (Indore) Limited Madhya Pradesh 09-Nov-2019
408 Parwanoo-Solan section of NH 22 in the State of Himachal Pradesh on BOT (Annuity) under NHDP Phase III 39.41 KM (Kilometer) 934.46 Transport Roads and bridges Operation and Maintenance Stage Ministry of Road Transport and Highways Himachal Pradesh 09-Nov-2019
409 Polytechnic at Sultanpur Lodhi * Not Available 15 Social and Commercial Infrastructure Education Not Available Department of Technical Education and Industrial Training, Punjab Punjab 09-Nov-2019
410 Positra Port Project * Not Available 0 Transport Ports (excluding captive) Under Construction Gujarat Maritime Board (GMB) Gujarat 09-Nov-2019
411 Raisen- Gairatganj- Rahatgarh Road 101.4 KM (Kilometer) 57.7 Transport Roads and bridges Operation and Maintenance Stage Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 09-Nov-2019
412 Rajpura Power Project 1400.0 MW (Mega Watt) 9600 Energy Electricity generation (grid) Operation and Maintenance Stage Punjab State Power Corporation Ltd. Punjab 09-Nov-2019
413 Reuse of Recycled Water Tertiary Treatment Water Plant, at Jaipur * Not Available 200 Water Sanitation Sewage collection, treatment and disposal system Not Available Public Health Engineering Department, Rajasthan Rajasthan 09-Nov-2019
414 Rice storage and management facility project at Krushnaprasad (Puri) * 2500.0 MTC 0 Social and Commercial Infrastructure Post-harvest storage infrastructure for agriculture and horticulture produce including cold storage Not Available Odisha State Civil Supplies Corporation Limited Odisha 09-Nov-2019
415 Road from AP border near Kothadoddi-Yaragara-Purthipalli to join SH-23 near Kapgal and other connecting roads* 234.34 KM (Kilometer) 488.6 Transport Roads and bridges Not Available Karnataka Road Development Corporation Limited (KRDCL) Karnataka 09-Nov-2019
416 Road from SH-17 Srirangapatana-Padavapura-Nagamandala-Chikkanayakanahalli-Hiriyuru-Challakere-Bellary-A P Border* 345.45 KM (Kilometer) 1413.06 Transport Roads and bridges Not Available Karnataka Road Development Corporation Limited (KRDCL) Karnataka 09-Nov-2019
417 Road Upgradation of Chakeri-Allahabad section of 145.3 km 145.3 KM (Kilometer) 3691 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Uttar Pradesh 09-Nov-2019
418 Road Upgradation (Ahmednagar-Kopergaon) Project* 42.0 KM (Kilometer) 110.4 Transport Roads and bridges Under Construction Public Works Department, Maharashtra Maharashtra 09-Nov-2019
419 Road Upgradation (Arawali-Kante) Project # * 40.0 KM (Kilometer) 594.33 Transport Roads and bridges Pre-construction Stage National Highways Authority of India (NHAI) Maharashtra 09-Nov-2019
420 Road Upgradation (Bar-Bilara-Jodhpur) Project # 15.0 KM (Kilometer) 8.93 Transport Roads and bridges Completed Public Works Department, Rajasthan Rajasthan 09-Nov-2019
421 Road Upgradation (Chutmalpur-Ganeshpur) Project 53.0 KM (Kilometer) 1443 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Uttar Pradesh 09-Nov-2019
422 Road Upgradation (Dausa-Lalsot-Kauthun) Project 83.5 KM (Kilometer) 688.7 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Rajasthan 09-Nov-2019
423 Road Upgradation (Gagalheri-Saharanpur-Yamunanagar) Project 51.0 KM (Kilometer) 1668 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Multi State/ Centre 09-Nov-2019
424 Road Upgradation (Greater Noida-Ballia) Project* 1047.0 KM (Kilometer) 29825 Transport Roads and bridges Under Construction Uttar Pradesh Expressways Industrial Development Authority Uttar Pradesh 09-Nov-2019
425 Road Upgradation (Gwalior-Jhansi NH-75) Project 80.0 KM (Kilometer) 604 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Madhya Pradesh 09-Nov-2019
426 Road Upgradation (Hoshangabad-Piparia-Pachmarhi) Project 126.0 KM (Kilometer) 57 Transport Roads and bridges Operation and Maintenance Stage Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 09-Nov-2019
427 Road Upgradation (Jinzira Bazzar-Batanagar) Project 6.8 KM (Kilometer) 24.3 Transport Roads and bridges Operation and Maintenance Stage Kolkata Metropolitan Development Authority West Bengal 09-Nov-2019
428 Road Upgradation (Kasaragod-Kannur) Project* 48.2 KM (Kilometer) 150.4 Transport Roads and bridges Under Construction Road Infrastructure Company Kerala Limited Kerala 09-Nov-2019
429 Road Upgradation (Kottayam-Thiruvananthapuram) Project* 58.0 KM (Kilometer) 128.91 Transport Roads and bridges Under Construction Road Infrastructure Company Kerala Limited Kerala 09-Nov-2019
430 Road Upgradation (MP/Maharashtra Border-Nagpur) Project 95.0 KM (Kilometer) 1920 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Multi State/ Centre 09-Nov-2019
431 Road Upgradation (Patna-Hajipur-Muzaffarpur) Project 63.0 KM (Kilometer) 672 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Bihar 09-Nov-2019
432 Road Upgradation (Potin-Pangin) Project # * 407.0 KM (Kilometer) 1985 Transport Roads and bridges Pre-construction Stage Ministry of Road Transport and Highways Arunachal Pradesh 09-Nov-2019
433 Road Upgradation (Rau-Pithampur) Project* 13.83 KM (Kilometer) 73 Transport Roads and bridges Pre-construction Stage Madhya Pradesh Audyogik Kendra Vikas Nigam (Indore) Limited Madhya Pradesh 09-Nov-2019
434 Road Upgradation (Rewa-Shahdol-Amarkantak) Project 242.7 KM (Kilometer) 111.3 Transport Roads and bridges Operation and Maintenance Stage Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 09-Nov-2019
435 Road Upgradation (Shivpuri-Guna) Project 97.7 KM (Kilometer) 830.36 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Madhya Pradesh 09-Nov-2019
436 Road Upgradation (Talaja-Mahuva) Project 45.46 KM (Kilometer) 834.64 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Gujarat 09-Nov-2019
437 Road Upgradation (Thrissur-Angamali NH-47) Project (KL-I) 40.0 KM (Kilometer) 604.4 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Kerala 09-Nov-2019
438 Road Upgradation (Udaipur-Rajasthan/Gujarat Border) Project 113.80 KM (Kilometer) 2100 Transport Roads and bridges Under Construction National Highways Authority of India (NHAI) Rajasthan 09-Nov-2019
439 Road upgradation of Raebareilly-Allahabad section of NH-24B in length of 106.6 Km under NHDP-IV 119.0 KM (Kilometer) 291.36 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Uttar Pradesh 09-Nov-2019
440 Road Upgradation Project (Tikamgarh-Orchha) Project 9.34 KM (Kilometer) 47.56 Transport Roads and bridges Operation and Maintenance Stage Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 09-Nov-2019
441 Ropar-Phagwara Road Project 80.66 KM (Kilometer) 70 Transport Roads and bridges Operation and Maintenance Stage Public Works Department, Punjab Punjab 09-Nov-2019
442 Saoner - Bypass Road* Not Available 125 Transport Roads and bridges Under Construction Public Works Department, Maharashtra Maharashtra 09-Nov-2019
443 School Building (Solapur) Project * 1.10 Acres 6.27 Social and Commercial Infrastructure Education Under Construction Solapur Municipal Corporation Maharashtra 09-Nov-2019
444 Second Adityapur Toll Bridge over River Kharkali* 0.27 KM (Kilometer) 55 Transport Roads and bridges Under Construction Department of Industries, Jharkhand Jharkhand 09-Nov-2019
445 Secured Engineered Landfill Facility (Vadodara) * Not Available 30.98 Water Sanitation Solid waste management Under Construction Vadodara Municipal Corporation Gujarat 09-Nov-2019
446 Setting up of 60 MW Tidong-II Hydel Power Project # * 60.0 MW (Mega Watt) 420 Energy Renewable energy (grid) Pre-construction Stage Directorate of Energy, Himachal Pradesh Himachal Pradesh 09-Nov-2019
447 Setting up of 15 MW Pitgong-I hydel power unit in Arunachal Pradesh # * 15.0 MW (Mega Watt) 112 Energy Renewable energy (grid) Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 09-Nov-2019
448 Setting up of 51 MW Bhasmey hydel power unit in East Sikkim district * 51.0 MW (Mega Watt) 297.76 Energy Renewable energy (grid) Under Construction Sikkim Power Development Corporation Limited Sikkim 09-Nov-2019
449 Setting up of Iron ore handling facilities on BOT basis at New Mangalore Port * Not Available 119.66 Transport Ports (excluding captive) Under Construction Ministry of Shipping Karnataka 09-Nov-2019
450 Setting up of Medical College and Hospital in Bolangir * 25.0 Acres 326.4 Social and Commercial Infrastructure Health Care Pre-construction Stage Department of Health & Family Welfare, Odisha Odisha 09-Nov-2019
451 Shopping-cum-Commercial Complex (Parola Road) Project * Not Available 12 Social and Commercial Infrastructure Common infrastructure for industrial parks, SEZ Under Construction Dhule Municipal Corporation Maharashtra 09-Nov-2019
452 Six laning from 90.0 km to 214.9 km of Kishangarh-Udaipur-Ahmedabad section under NHDP Phase-V 124.90 KM (Kilometer) 1239.82 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Rajasthan 09-Nov-2019
453 Six laning of Kishangarh-Gulabpura section in length of 90.0 Km NHDP-V 90.0 KM (Kilometer) 1031.95 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Rajasthan 09-Nov-2019
454 Six laning of Agra-Etawah Section of NH 2 from Km 199/660 to km 323.525 on BoT (Toll) in Uttar Pradesh under NHDP Phase V. 124.5 KM (Kilometer) 1657.2 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Uttar Pradesh 09-Nov-2019
455 Six laning of Barwa-Adda-Panagarh section of NH 2 inJharkhand and West Bengal under NHDP PhaseV on BOT (Toll) basis 122.8 KM (Kilometer) 2434.5 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Multi State/ Centre 09-Nov-2019
456 Six laning of Chandikol-Jagatpur-Bhubhaneshwar section of NH 5 from Km 413 to 418 and Km 0 to Km 62 in Orissa on BOT basis 67.0 KM (Kilometer) 1047 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Odisha 09-Nov-2019
457 Six laning of Chilkaluripet-Nellore section of NH 5 from km 1182.802 to km 1366.547 in AP on BOT (Toll) project on DBFO pattern 183.5 KM (Kilometer) 2163.9 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Andhra Pradesh 09-Nov-2019
458 Six laning of Chitradurga-Davanagere section in length of 72.7 km 72.7 KM (Kilometer) 993.16 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Karnataka 09-Nov-2019
459 Six laning of Chittorgarh - Udaipur section of NH-76 PKG-III 93.5 KM (Kilometer) 1245.75 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Rajasthan 09-Nov-2019
460 Six laning of Delhi-Agra section of NH 2 from Km 20.500 to Km 199.600 in the States of Haryana/UP under NHDP V on BOT basis 179.5 KM (Kilometer) 2960 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Multi State/ Centre 09-Nov-2019
461 Six laning of Dhankuni-Kharagpur section in length of 111.4 km on NH-6 under NHDP-V 111.4 KM (Kilometer) 1396.2 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) West Bengal 09-Nov-2019
462 Six laning of Etawah Chakeri (Kanpur) section of NH 2� under NHDP Phase V, length 160.21 km 160.2 KM (Kilometer) 1573 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Uttar Pradesh 09-Nov-2019
463 Six Laning of Gurgaon-Kotputli-Jaipur Section of NH-8 in Haryana/Rajasthan on BOT (Toll) basis following by DBFO pattern. 225.6 KM (Kilometer) 1896 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Multi State/ Centre 09-Nov-2019
464 Six Laning of Handia Varanasi Section of NH-2 from KM 713.146 to KM 785.544 in Uttar Pradesh on Hybrid Annuity Mode 72.4 KM (Kilometer) 2356.16 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Uttar Pradesh 09-Nov-2019
465 Six laning of Indore-Dewas section of NH 3 from Km 577.55 to km 610.00 and Km 0.00 to Km 12.60 inMP under NHDP V on BOT basis 45.0 KM (Kilometer) 410 Transport Roads and bridges Operation and Maintenance Stage Ministry of Road Transport and Highways Madhya Pradesh 09-Nov-2019
466 Six Laning of Kharar-Ludhiana Section of NH-95 (New NH-05) from Kharar Km 10.185 to Samrala Chowk Ludhiana Km 86.199 on HAM Mode 86.19 KM (Kilometer) 1388.34 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Multi State/ Centre 09-Nov-2019
467 Six laning of Krishnagiri-Walahjpet section of NH 46 from Km 0 to km 148.30 in the State of Tamil Nadu under NHDP V on BOT basis 148.3 KM (Kilometer) 1489.55 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Tamil Nadu 09-Nov-2019
468 Six laning of NH-8 in length of 93.2 k m of Shamlaji-Chiloda section* 93.2 KM (Kilometer) 1251 Transport Roads and bridges Pre-construction Stage National Highways Authority of India (NHAI) Gujarat 09-Nov-2019
469 Six Laning of Panipat - Jalandhar Section of NH-1 (291 Km) in Haryana and Punjab. 291.0 KM (Kilometer) 2748 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Multi State/ Centre 09-Nov-2019
470 Six laning of Udaipur bypass in length of 23.9 km under NHDP-V 23.88 KM (Kilometer) 891 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Rajasthan 09-Nov-2019
471 Six Laning of Vadakkancherry to Thrissur Section (Package No.NS-2/BOT/KL-3 30.0 KM (Kilometer) 910 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Kerala 09-Nov-2019
472 Six-laning of Vijayawada-Gundugolanu section of NH-5 section from km 1076.48 to km 1022.48 on BOT (Toll) basis 103.5 KM (Kilometer) 1684 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Andhra Pradesh 09-Nov-2019
473 Solid Waste Management (700 TPD) at Asansol UA * 700.0 TPD (Tonne per day) 44 Water Sanitation Solid waste management Under Construction Asansol Durgapur Development Authority West Bengal 09-Nov-2019
474 Solid Waste Management (Allahabad) * Not Available 30.41 Water Sanitation Solid waste management Under Construction Allahabad Municipal Corporation Uttar Pradesh 09-Nov-2019
475 Solid Waste Management (Dehradun) * Not Available 24.6 Water Sanitation Solid waste management Under Construction Dehradun Nagar Nigam Uttarakhand 09-Nov-2019
476 Solid Waste Management (Lucknow) * Not Available 42.92 Water Sanitation Solid waste management Under Construction Lucknow Municipal Corporation Uttar Pradesh 09-Nov-2019
477 Solid Waste Management (Meerut) * Not Available 22.59 Water Sanitation Solid waste management Under Construction Meerut Nagar Nigam Uttar Pradesh 09-Nov-2019
478 Solid Waste Management (PCMC) * Not Available 70.44 Water Sanitation Solid waste management Under Construction Pimpri Chinchwad Municipal Corporation Maharashtra 09-Nov-2019
479 Solid Waste Management (Shahdara) Project * 500.0 TPD (Tonne per day) 18 Water Sanitation Solid waste management Under Construction East Delhi Municipal Corporation Delhi (UT) 09-Nov-2019
480 Solid Waste Management (Varanasi) * 600.0 TPD (Tonne per day) 68.8 Water Sanitation Solid waste management Under Construction Uttar Pradesh Jal Nigam Uttar Pradesh 09-Nov-2019
481 Solid Waste Management Project (Kanjur) * 1000.0 TPD (Tonne per day) 4116.65 Water Sanitation Solid waste management Under Construction Municipal Corporation of Greater Mumbai Maharashtra 09-Nov-2019
482 Sport Complex-cum-Commercial Complex (Mouje-Navsari) * 4.1 Acres 12.37 Social and Commercial Infrastructure Tourism Under Construction Amravati Municipal Corporation Maharashtra 09-Nov-2019
483 Sports City at Village Satgarhi, Bhopal * Not Available 900 Social and Commercial Infrastructure Tourism Not Available Directorate of Institutional Finance, Govt. of Madhya Pradesh Madhya Pradesh 09-Nov-2019
484 Sports City cum International Convention Centre cum Star Hotel cum Shopping Complex cum Residential Complex * 172.0 Acres 900 Social and Commercial Infrastructure Common infrastructure for industrial parks, SEZ Under Construction Food, Civil Supplies and Consumer Affairs Department, Karnatak Karnataka 09-Nov-2019
485 Srinagar-banihal section of NH1A from 187-189.35km, km 220.7-286.11km and 187 to 220.7 on DBFOT (Annuity) in Jammu and Kashmir 67.7 KM (Kilometer) 1625 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Jammu & Kashmir 09-Nov-2019
486 Sundarabad - Runija - Khachrod - Runija - Satrunda 43.79 KM (Kilometer) 65 Transport Roads and bridges Operation and Maintenance Stage Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 09-Nov-2019
487 Terminal Market Complex (Coimbatore) * Not Available 13 Social and Commercial Infrastructure Common infrastructure for industrial parks, SEZ Under Construction Tamil Nadu State Agricultural Marketing Board Tamil Nadu 09-Nov-2019
488 Transport nagar at Ahmedabad for 600 trucks * Not Available 150 Social and Commercial Infrastructure Common infrastructure for industrial parks, SEZ Under Construction Gujarat State Road Transport Corporation Gujarat 09-Nov-2019
489 Two lane road project from KM 24.800 of NH-75 (Gwalior - Jhansi Section) to KM 19.000 upto Ghongha 5.8 KM (Kilometer) 67.38 Transport Roads and bridges Operation and Maintenance Stage Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 09-Nov-2019
490 Two lane with hard shoulder of State Highway 2 between Dausa-Dadu Road on BOT (Toll) basis Not Available 164.7 Transport Roads and bridges Under Construction Public Works Department, Rajasthan Rajasthan 09-Nov-2019
491 Two lane with paved shoulders from Sikar to Bikaner and Bikaner Bypass of NH-11 under DBFOT basis 217.6 KM (Kilometer) 734.8 Transport Roads and bridges Operation and Maintenance Stage Public Works Department, Rajasthan Rajasthan 09-Nov-2019
492 Two laning Nechipu to Hoj via Seppa, Saggali in length of 311 km* 311.0 KM (Kilometer) 1486 Transport Roads and bridges Under Construction Ministry of Road Transport and Highways Arunachal Pradesh 09-Nov-2019
493 Two laning of Hata-Fatehpur-Bajna-Dargawon road in length of 64.4 km* 64.4 KM (Kilometer) 74.25 Transport Roads and bridges Under Construction Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 09-Nov-2019
494 Two Laning of proposed Shimla Bypass (Kaithalighat to Shimla Section) of NH-22 under NHDP Phase III on Hybrid Annuity Mode 27.45 KM (Kilometer) 1583.18 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Himachal Pradesh 09-Nov-2019
495 Two laning of Rau-Mhow-Jamghat-Mandleshwar section of SH 38 in MP on BOT(Toll)* 74.4 KM (Kilometer) 176.06 Transport Roads and bridges Under Construction Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 09-Nov-2019
496 Two laning of Zojila Tunnel of 14.083 km length on NH - 1D in the State of Jammu & Kashmir on BOT annuity basis* 14.083 KM (Kilometer) 9090.13 Transport Roads and bridges Under Construction Ministry of Road Transport and Highways Jammu & Kashmir 09-Nov-2019
497 Two laning with Pave shoulder from Varanasi to Gorakhpur section Km 2 to Km 208 of NH 29 in the State of UP�* Not Available 538.88 Transport Roads and bridges Under Construction Ministry of Road Transport and Highways Uttar Pradesh 09-Nov-2019
498 Two laning with pave shoulder on Raigarh - Saraipalli from 3.800 to Km 90.460 on NH 216 in the State of Chattisgarh* Not Available 189.19 Transport Roads and bridges Under Construction Ministry of Road Transport and Highways Chhattisgarh 09-Nov-2019
499 Two laning with paved shoulder of Dindigul - Theni and Theni - Kumili in Tamil Nadu under NHDP III� 134.0 KM (Kilometer) 501 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Tamil Nadu 09-Nov-2019
500 Two laning with paved shoulder of Tindivam Krishnagiri section of NH 66 from km 38.150 to km 214 in the state of Tamil Nadu 176.5 KM (Kilometer) 828.26 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Tamil Nadu 09-Nov-2019
501 Two laning with paved shoulders of Jhansi-Khajuraho section of NH 75 in UP and MP 76.6 KM (Kilometer) 1373.28 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Multi State/ Centre 09-Nov-2019
502 Two laning with PSS of Kotkapura to Muktsar Road to on SH-16 Road on BOT (Toll) 30.0 KM (Kilometer) 66.21 Transport Roads and bridges Operation and Maintenance Stage Public Works Department, Punjab Punjab 09-Nov-2019
503 Two laning Z-Morh Tunnel section of NH-I on BOT (Annuity) in Sonamarg, Srinagar, Jammu and Kashmir�* 34.0 KM (Kilometer) 3289 Transport Roads and bridges Under Construction Ministry of Road Transport and Highways Jammu & Kashmir 09-Nov-2019
504 Two-lanning of 68.7 km, Motihari-Raxaul Road on NH-28A 68.70 KM (Kilometer) 375.09 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Bihar 09-Nov-2019
505 Two/ Four laning of Bellary to AP Border section of SH 132 in Karnataka on BOT (Toll) basis 25.67 KM (Kilometer) 169.33 Transport Roads and bridges Operation and Maintenance Stage Karnataka Road Development Corporation Limited (KRDCL) Karnataka 09-Nov-2019
506 Upgradation of Abhor-Bali-Mundara road in length of 28.5 km* 29.42 KM (Kilometer) 65.13 Transport Roads and bridges Under Construction Public Works Department, Rajasthan Rajasthan 09-Nov-2019
507 Upgradation of Alot-Gangdhar-Suwansara (MP) highway road in length of 24.6 km* 24.6 KM (Kilometer) 36.12 Transport Roads and bridges Under Construction Public Works Department, Rajasthan Rajasthan 09-Nov-2019
508 Upgradation of Bagewadi (NH-4)-Bailhongal-Saundatti road in length of 63.8 km in Bengaluru 63.8 KM (Kilometer) 238 Transport Roads and bridges Operation and Maintenance Stage Karnataka Road Development Corporation Limited (KRDCL) Karnataka 09-Nov-2019
509 Upgradation of Bameetha-Panna-Nagod-Satna road on NH-75 in length of 97.6 km* 97.6 KM (Kilometer) 275.6 Transport Roads and bridges Under Construction Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 09-Nov-2019
510 Upgradation of Banner-Sindari-Jalore road in length of 149.8 km* 149.8 KM (Kilometer) 281.64 Transport Roads and bridges Under Construction Public Works Department, Rajasthan Rajasthan 09-Nov-2019
511 Upgradation of Bidar-NH-9 (Ekhelli)-Chincholi road in length of 60 km in Bengaluru district* 60.0 KM (Kilometer) 226 Transport Roads and bridges Pre-construction Stage Karnataka Road Development Corporation Limited (KRDCL) Karnataka 09-Nov-2019
512 Upgradation of Churu-Bhaleri road in length of 35 km* 35.0 KM (Kilometer) 63.59 Transport Roads and bridges Under Construction Public Works Department, Rajasthan Rajasthan 09-Nov-2019
513 Upgradation of Deoli-Kanwas road in length of 14.8 km* 14.80 KM (Kilometer) 45.97 Transport Roads and bridges Under Construction Public Works Department, Rajasthan Rajasthan 09-Nov-2019
514 Upgradation of Hassan-Ramanathapura-Piriyapatna road in length of 73.5 Km in in Bengaluru district 73.5 KM (Kilometer) 274 Transport Roads and bridges Operation and Maintenance Stage Karnataka Road Development Corporation Limited (KRDCL) Karnataka 09-Nov-2019
515 Upgradation of Hoshangabad-Harda-Khandwa road in length of 185.6 km in Khandwa & Hoshangabad 185.0 KM (Kilometer) 81 Transport Roads and bridges Operation and Maintenance Stage Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 09-Nov-2019
516 Upgradation of Hungund-Muddebihal-Talikot road in length of 56.8 km in Bengaluru 56.8 KM (Kilometer) 205 Transport Roads and bridges Operation and Maintenance Stage Karnataka Road Development Corporation Limited (KRDCL) Karnataka 09-Nov-2019
517 Upgradation of Jaipur to Bhilwara State Highway, Rajasthan 212.0 KM (Kilometer) 322 Transport Roads and bridges Operation and Maintenance Stage Rajasthan State Road Development and Construction Corporation Limited Rajasthan 09-Nov-2019
518 Upgradation of Kanwas-Khanpur-Aklera road in length of 73.12 km* 73.12 KM (Kilometer) 136.8 Transport Roads and bridges Under Construction Public Works Department, Rajasthan Rajasthan 09-Nov-2019
519 Upgradation of Khedali-Pahadi road in length of 59 km* 59.0 KM (Kilometer) 116.01 Transport Roads and bridges Under Construction Public Works Department, Rajasthan Rajasthan 09-Nov-2019
520 Upgradation of Madurai ring road in length of 27.2 Km 27.2 KM (Kilometer) 213.69 Transport Roads and bridges Operation and Maintenance Stage Tamil Nadu Road Infrastructure Development Corporation Tamil Nadu 09-Nov-2019
521 Upgradation of Mundaragi-Hadagali-Harapanahalli road in length of 53.7 Km in Bengaluru district 53.7 KM (Kilometer) 203 Transport Roads and bridges Operation and Maintenance Stage Karnataka Road Development Corporation Limited (KRDCL) Karnataka 09-Nov-2019
522 Upgradation of Nagaur-Mukundgarh road in length of 196 km* 196.0 KM (Kilometer) 557.92 Transport Roads and bridges Under Construction Public Works Department, Rajasthan Rajasthan 09-Nov-2019
523 Upgradation of of Hirekerur-Ranibennur road in length of 58.3 Km in Bengaluru district 58.3 KM (Kilometer) 257 Transport Roads and bridges Operation and Maintenance Stage Karnataka Road Development Corporation Limited (KRDCL) Karnataka 09-Nov-2019
524 Upgradation of Peelibanga-Lukhuwali road in length of 35.5 km* 34.5 KM (Kilometer) 71.99 Transport Roads and bridges Under Construction Public Works Department, Rajasthan Rajasthan 09-Nov-2019
525 Upgradation of Salasar-Nagaur section of NH-65 under NHDP-IV 119.6 KM (Kilometer) 637.18 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Rajasthan 09-Nov-2019
526 Upgradation of Sanju-Tarnau road in length of 16.7 km* 16.7 KM (Kilometer) 34.8 Transport Roads and bridges Under Construction Public Works Department, Rajasthan Rajasthan 09-Nov-2019
527 Upgradation of Sardarshashar-Lunkaransar road in length of 76.5 km* 76.5 KM (Kilometer) 123.58 Transport Roads and bridges Under Construction Public Works Department, Rajasthan Rajasthan 09-Nov-2019
528 Upgradation of Sawai Madhopur to Bharatpur State Highway in Rajasthan* 111.0 KM (Kilometer) 350 Transport Roads and bridges Under Construction Rajasthan State Road Development and Construction Corporation Limited Rajasthan 09-Nov-2019
529 Upgradation of Seoni-Balaghat-Gondia road in length of 114 Km in Seoni and Balaghat districts 114.0 KM (Kilometer) 59.8 Transport Roads and bridges Operation and Maintenance Stage Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 09-Nov-2019
530 Upgradation of Ujjain-Jhalawad road in length of 134 Km in Shajapur district # 134.0 KM (Kilometer) 66.7 Transport Roads and bridges Completed Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 09-Nov-2019
531 Useful Conversion of Solid Waste in Ajmer * Not Available 5.16 Water Sanitation Solid waste management Under Construction Ajmer Municipal Corporation Rajasthan 09-Nov-2019
532 Useful Conversion of Solid Waste in Bikaner * Not Available 6.79 Water Sanitation Solid waste management Under Construction Bikaner Nagar Parishad Rajasthan 09-Nov-2019
533 Waste to Energy Project Mandur * 8.0 MW (Mega Watt) 73 Water Sanitation Solid waste management Under Construction Bruhat Bengaluru Mahanagara Palike Karnataka 09-Nov-2019
534 Waste Water Recycling Plant (Nagpur) # 130.0 MLD (Millons Liter per day) 275 Water Sanitation Sewage collection, treatment and disposal system Operation and Maintenance Stage Nagpur Municipal Corporation Maharashtra 09-Nov-2019
535 Water Supply Improvement (Malviya Nagar) Pilot Project # * Not Available 519.07 Water Sanitation Water supply pipeline Under Construction Delhi Jal Board Delhi (UT) 09-Nov-2019
536 Water Supply Improvement Scheme (Nangloi) * 40.0 MGD (Million Gallon per Day) 652.32 Water Sanitation Water supply pipeline Under Construction Delhi Jal Board Delhi (UT) 09-Nov-2019
537 Water Supply Scheme (Mysore) * Not Available 194.54 Water Sanitation Water supply pipeline Under Construction Mysuru City Corporation Karnataka 09-Nov-2019
538 Water Treatment Plant (Vijayapura) Project * 2.66 MLD (Millons Liter per day) 9.99 Water Sanitation Water treatment plants Under Construction Zilla Panchayat, Vijayapura Karnataka 09-Nov-2019
539 Widening and Strengthening of Bikaner - Phalodi section of NH - 15 to 4 lane and two lane with paved shoulderon BOT (Toll) mode 159.0 KM (Kilometer) 844 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Rajasthan 09-Nov-2019
540 Women Polytechnic College (Bhilwara) Project * 5.0 Acres 5.49 Social and Commercial Infrastructure Education Under Construction Directorate of Technical Education, Rajasthan Rajasthan 09-Nov-2019
541 Angul-Sukinda New Railway Line Project * 100.0 KM (Kilometer) 1202.7 Transport Railway track, tunnel, viaducts, bridges Under Construction Rail Vikas Nigam Limited Odisha 08-Nov-2019
542 Astaranga Port Project * 70.0 MMTPA (million metric tonnes per annum) 6500 Transport Ports (excluding captive) Pre-construction Stage Department of Commerce and Transport, Odisha Odisha 08-Nov-2019
543 Augumentation of Existing Water Supply Scheme including Service Reservoirs at Bhiwandi * 275.0 KM (Kilometer) 50 Water Sanitation Water supply pipeline Under Construction Bhiwandi Nizampur City Municipal Corporation Maharashtra 08-Nov-2019
544 Bus Rapid Transport System (Visakhapatnam) * 43.36 KM (Kilometer) 454.73 Transport Urban public transport (except rolling stock) Under Construction Greater Vishakhapatnam Municipalicy Andhra Pradesh 08-Nov-2019
545 Bus Stand Property (Gandhi Road) * Not Available 25 Transport Urban public transport (except rolling stock) Under Construction Uttarakhand Transport Corporation Uttarakhand 08-Nov-2019
546 Bus Terminal (Kashipur) Project - Redevelopment * 3.3 Acres 10 Transport Urban public transport (except rolling stock) Under Construction Uttarakhand Transport Corporation Uttarakhand 08-Nov-2019
547 Bus Terminal (Rudrapur) Project - Redevelopment * 3.5 Acres 10 Transport Urban public transport (except rolling stock) Under Construction Uttarakhand Transport Corporation Uttarakhand 08-Nov-2019
548 Bus Terminal (Srinagar) Project - Redevelopment * 2.9 Acres 10 Transport Urban public transport (except rolling stock) Under Construction Uttarakhand Transport Corporation Uttarakhand 08-Nov-2019
549 Chudamani Port * 10.0 MTPA (Metric Tonne Per Annum) 1500 Transport Ports (excluding captive) Under Construction Odisha Maritime Board Odisha 08-Nov-2019
550 City side development of Amritsar Airport through PPP * Not Available 0 Transport Airports Under Construction Ministry of Civil Aviation Punjab 08-Nov-2019
551 Clinker handling jetty at Azhicode/Kodungallur Port * Not Available 50 Transport Ports (excluding captive) Pre-construction Stage Ports Department, Kerala Kerala 08-Nov-2019
552 Construction of Digni-Jaigarh Port Railway Line in length of 33.70 km in Ratnagiri * 33.7 KM (Kilometer) 771.51 Transport Railway track, tunnel, viaducts, bridges Under Construction Konkan Railway Corporation Limited Maharashtra 08-Nov-2019
553 Construction of Haridaspur-Paradip BG railway line in length of 82 km in Cuttack and Jagatsingpur * 82.0 KM (Kilometer) 1800 Transport Railway track, tunnel, viaducts, bridges Under Construction Rail Vikas Nigam Limited Odisha 08-Nov-2019
554 Construction of Offshore Container Berths & Development of Container Terminal in Mumbai Harbour # 9.6 MTPA (Metric Tonne Per Annum) 2098 Transport Ports (excluding captive) Under Construction Mumbai Port Trust Maharashtra 08-Nov-2019
555 Construction of State of Art Bus Stands in Haryana * Not Available 130 Transport Urban public transport (except rolling stock) Under Construction Transport Department, Haryana Haryana 08-Nov-2019
556 Construction, operation and Maintenance of a multi-user liquid terminal at Puthuvypeen SEZ at Cochin Port * 4.1 MMTPA (million metric tonnes per annum) 240 Transport Ports (excluding captive) Under Construction Cochin Port Trust Kerala 08-Nov-2019
557 Development and Operation of an International Ship repair facility at W/Island with private sector participation * Not Available 970 Transport Ports (excluding captive) Under Construction Cochin Port Trust Kerala 08-Nov-2019
558 Development of 250 Bus Queue shelters (BQS) * Not Available 37.5 Transport Urban public transport (except rolling stock) Under Construction Transport Department, GNCTD Delhi (UT) 08-Nov-2019
559 Development of a 7.2 MMTPA Iron Ore Export Terminal at Waterfront West of the Breakwater on DBFOT basis (Mormugao Port Trust) * 7.2 MMTPA (million metric tonnes per annum) 721 Transport Ports (excluding captive) Under Construction Ministry of Shipping Goa 08-Nov-2019
560 Development of a multipurpose Berth and a Mechanised Berth at Haldia Dock -II (North), Haldia Dock Complex, Kolkata Port Trust * 1.177 MT (Metric Tonne ) 821.4 Transport Ports (excluding captive) Under Construction Ministry of Shipping West Bengal 08-Nov-2019
561 Development of a Municipal Solid Waste Management Facity for treating MSW collected from Cuttack * 800.0 TPD (Tonne per day) 200 Water Sanitation Solid waste management Under Construction Cuttack Municipal Corporation Odisha 08-Nov-2019
562 Development of a regional municipal solid waste management facility in Bhubaneswar * 800.0 MT (Metric Tonne ) 0 Water Sanitation Solid waste management Not Available Bhubaneswar Municipal Corporation Odisha 08-Nov-2019
563 Development of Bus Station with Passenger Amenities and Commercial Complex on NEKRTC site at Gulbarga * 1.72 Acres 20.2 Transport Urban public transport (except rolling stock) Under Construction North Eastern Karnataka Road Transport Corporation (NEKRTC) Karnataka 08-Nov-2019
564 Development of bus terminal and commercial development at Musheerabad * Not Available 250 Transport Urban public transport (except rolling stock) Under Construction Andhra Pradesh State Road Transport Corporation Telangana 08-Nov-2019
565 Development of Bus Terminal cum Commercial Complex (C and C Mohali Junction) at Mohali # * 7.0 Acres 530 Transport Urban public transport (except rolling stock) Under Construction Greater Mohali Area Development Authority Punjab 08-Nov-2019
566 Development of Bus Terminal cum Commercial Complex at Patiala * 13.13 Acres 175 Transport Urban public transport (except rolling stock) Under Construction Punjab Road Transport Corporation Punjab 08-Nov-2019
567 Development of bus terminal on 2.5 acres at Jagnade Square in Nagpur district * 2.5 Acres 46.8 Transport Urban public transport (except rolling stock) Under Construction Nagpur Municipal Corporation Maharashtra 08-Nov-2019
568 Development of Honnavar port in UK District of Karnataka Maritime State * Not Available 1100 Transport Ports (excluding captive) Pre-construction Stage Public Works, Ports and Inland Water Transport Department, Karnataka Karnataka 08-Nov-2019
569 Development of Integrated Multilevel Parking Infrastructure at 3 sites in NDMC Area * Not Available 8 Transport Urban public transport (except rolling stock) Under Construction New Delhi Municipal Council Delhi (UT) 08-Nov-2019
570 Development of parking & commercial complex on 9 acres at Takheda in Amravati district * 9.0 Acres 14.26 Transport Urban public transport (except rolling stock) Under Construction Nagpur Improvement Trust Maharashtra 08-Nov-2019
571 Development of parking complex with a capacity of 160 ECS Palampur in Kangra # 160.0 ECS 7 Transport Urban public transport (except rolling stock) Pre-construction Stage Municipal Council, Palampur Himachal Pradesh 08-Nov-2019
572 Development of parking complex with a capacity of 225 vehicles at Jail Road in Mandi # 225.0 ECS 20 Transport Urban public transport (except rolling stock) Pre-construction Stage Municipal Council, Mandi Himachal Pradesh 08-Nov-2019
573 Hyderabad Metro Rail Project # 71.0 KM (Kilometer) 16375 Transport Urban public transport (except rolling stock) Operation and Maintenance Stage Hyderabad Metro Rail Limited Telangana 08-Nov-2019
574 Hyderabad Multi-Modal Suburban Transportation Project - Phase II * 101.05 KM (Kilometer) 1800 Transport Railway track, tunnel, viaducts, bridges Under Construction Rail Vikas Nigam Limited Telangana 08-Nov-2019
575 Implementation of solid waste management facility of 500 TPD at Keru dumping station * 500.0 TPD (Tonne per day) 100 Water Sanitation Solid waste management Pre-construction Stage Jodhpur Municipal Corporation Rajasthan 08-Nov-2019
576 Integrated Solid Waste Management (3800 TPD) for Hyderabad * 3800.0 TPD (Tonne per day) 508 Water Sanitation Solid waste management Under Construction Greater Hyderabad Municipal Corporation Telangana 08-Nov-2019
577 Jakhau Port * Not Available 46 Transport Ports (excluding captive) Under Construction Gujarat Maritime Board (GMB) Gujarat 08-Nov-2019
578 Kirtania Port Subarnarekha Mouth * 10.0 MTPA (Metric Tonne Per Annum) 2187 Transport Ports (excluding captive) Under Construction Department of Commerce and Transport, Odisha Odisha 08-Nov-2019
579 LNG Terminal (Jafrabad) Project * 4.5 MMTPA (million metric tonnes per annum) 5000 Transport Ports (excluding captive) Under Construction Gujarat Pipavav Port Limited Gujarat 08-Nov-2019
580 Multilevel Automated car parking cum commercial complex Kamla Nagar, New Delhi * Not Available 109.39 Transport Urban public transport (except rolling stock) Under Construction Municipal Corporation of Delhi Delhi (UT) 08-Nov-2019
581 Multipurpose Berth (Visakhapatnam Port) Project # 2.0 MTPA (Metric Tonne Per Annum) 317 Transport Ports (excluding captive) Operation and Maintenance Stage Visakhapatnam Port Trust Andhra Pradesh 08-Nov-2019
582 Multipurpose Cargo Port (Rewas) Project # 198.0 MMTPA (million metric tonnes per annum) 5200 Transport Ports (excluding captive) Pre-construction Stage Maharashtra Maritime Board (MMB) Maharashtra 08-Nov-2019
583 Office cum Institutional cum Commercial Complex at Salt Lake * 4.0 Acres 500 Social and Commercial Infrastructure Common infrastructure for industrial parks, SEZ Under Construction Kolkata Metropolitan Development Authority West Bengal 08-Nov-2019
584 Oil Jetty (Kandla) Project # Not Available 233.5 Transport Ports (excluding captive) Pre-construction Stage Deendayal Port Trust Gujarat 08-Nov-2019
585 Package IA Development of Tourism Infrastructure Projects at Jog and Banavasi Package IB Development of Tourism Infrastructure* 5.0 Acres 67.5 Social and Commercial Infrastructure Tourism Not Available Department of Tourism, Karnataka Karnataka 08-Nov-2019
586 Parking Complex (Bilaspur) Project * 194.0 ECS 8 Transport Urban public transport (except rolling stock) Under Construction Municipal Council, Bilashpur Himachal Pradesh 08-Nov-2019
587 Parking Complex (Jainchu-Ka-Naun) Project * 200.0 ECS 15 Transport Urban public transport (except rolling stock) Pre-construction Stage Municipal Council, Mandi Himachal Pradesh 08-Nov-2019
588 Ponnani Port Project - Phase I * 4.0 MMTPA (million metric tonnes per annum) 763 Transport Ports (excluding captive) Under Construction Kerala State Maritime Development Corporation Limited Kerala 08-Nov-2019
589 Purnagiri Ropeway Project * 800.0 Passengers 60 Social and Commercial Infrastructure Tourism Under Construction Uttarakhand Tourism Development Board Uttarakhand 08-Nov-2019
590 Redevelopment of New delhi Railway station * Not Available 8500 Transport Railway track, tunnel, viaducts, bridges Pre-construction Stage Ministry of Railways Delhi (UT) 08-Nov-2019
591 Riverine Multipurpose Jetty at Haldia Port * Not Available 278.9 Transport Ports (excluding captive) Pre-construction Stage Kolkata Port Trust West Bengal 08-Nov-2019
592 Ropeway (Kaddukhal-Surkanda Devi Temple) Project * 0.5 KM (Kilometer) 15 Social and Commercial Infrastructure Tourism Under Construction Uttarakhand Tourism Development Board Uttarakhand 08-Nov-2019
593 Ropeway (Yamunotri-Kharsali) Project * 3.8 KM (Kilometer) 70 Social and Commercial Infrastructure Tourism Under Construction Uttarakhand Tourism Development Board Uttarakhand 08-Nov-2019
594 Setting up of 1.75 MW hydel based power unit at Bhima in Solapur 1.75 MW (Mega Watt) 6.97 Energy Renewable energy (grid) Pre-construction Stage Water Resources Department, Maharashtra Maharashtra 08-Nov-2019
595 Tornagallu Truck Terminal * Not Available 29.9 Transport Urban public transport (except rolling stock) Pre-construction Stage Bellary Urban Development Authority (BUDA) Karnataka 08-Nov-2019
596 Hurla Hydel Power Project - Stage I # 9.40 MW (Mega Watt) 62 Energy Renewable energy (grid) Pre-construction Stage Directorate of Energy, Himachal Pradesh Himachal Pradesh 04-Nov-2019
597 Alaknanda Hydro Power Co Ltd 330.0 MW (Mega Watt) 4573 Energy Renewable energy (grid) Operation and Maintenance Stage Not Available Uttarakhand 01-Nov-2019
598 Biomass Power Project, Patiala 12.0 MW (Mega Watt) 100 Energy Renewable energy (grid) Operation and Maintenance Stage Punjab Energy Development Agency Punjab 01-Nov-2019
599 Chanju Hydel Power Project - Stage I 36.0 MW (Mega Watt) 295.09 Energy Renewable energy (grid) Operation and Maintenance Stage Directorate of Energy, Himachal Pradesh Himachal Pradesh 01-Nov-2019
600 Chitaura Small Hydel Power Project * 3.0 MW (Mega Watt) 59.8 Energy Renewable energy (grid) Pre-construction Stage Uttar Pradesh Jal Vidyut Nigam Limited Uttar Pradesh 01-Nov-2019
601 Development of 400 kV Babai (Jhunjhunu) - Jaipur (North) Double Circuit Twin Moose Power Transmission line * 85.58 KM (Kilometer) 294 Energy Electricity transmission Under Construction Rajasthan Rajya Vidyut Prasaran Nigam Limited Rajasthan 01-Nov-2019
602 Development of 400 kV Suratgarh-Bikaner Double Circuit of Super Critical Thermal Power Plant at Suratgarh 400.0 KV (Kilo Volt) 160 Energy Electricity transmission Under Construction Rajasthan Rajya Vidyut Prasaran Nigam Limited Rajasthan 01-Nov-2019
603 Development of a 400 kV Bikaner Sikar D/C Power Transmission Line for evacuation of power from wind and solar power in Rajasthan 400.0 KM (Kilometer) 244 Energy Electricity transmission Operation and Maintenance Stage Rajasthan Rajya Vidyut Prasaran Nigam Limited Rajasthan 01-Nov-2019
604 Dikchu Hydro Power Plant * 96.0 MW (Mega Watt) 499 Energy Renewable energy (grid) Under Construction Sikkim Power Development Corporation Limited Sikkim 01-Nov-2019
605 Dunda Small Hydel Power Project # * 3.5 MW (Mega Watt) 28.04 Energy Renewable energy (grid) Pre-construction Stage Uttar Pradesh Jal Vidyut Nigam Limited Uttar Pradesh 01-Nov-2019
606 Electricity Distribution Bhiwandi Not Available 311 Energy Electricity Distribution Operation and Maintenance Stage Maharashtra State Electricity Distribution Company Limited Maharashtra 01-Nov-2019
607 Haindaun-Alwar Transmission line project 400.0 KV (Kilo Volt) 188.32 Energy Electricity transmission Operation and Maintenance Stage Rajasthan Rajya Vidyut Prasaran Nigam Limited Rajasthan 01-Nov-2019
608 Hydel Power (Darna) Project 4.9 MW (Mega Watt) 23.52 Energy Renewable energy (grid) Operation and Maintenance Stage Water Resources Department, Maharashtra Maharashtra 01-Nov-2019
609 Hydel Power (Kasari) Project 2.5 MW (Mega Watt) 12 Energy Renewable energy (grid) Operation and Maintenance Stage Water Resources Department, Maharashtra Maharashtra 01-Nov-2019
610 Hydel Power (Khodashi) Project 4.9 MW (Mega Watt) 23.52 Energy Renewable energy (grid) Operation and Maintenance Stage Water Resources Department, Maharashtra Maharashtra 01-Nov-2019
611 Hydel Power (Kutehr) Project 240.0 MW (Mega Watt) 105.08 Energy Renewable energy (grid) Operation and Maintenance Stage Directorate of Energy, Himachal Pradesh Himachal Pradesh 01-Nov-2019
612 Hydel Power (Palchan Bhang) Project 9.0 MW (Mega Watt) 65.36 Energy Renewable energy (grid) Pre-construction Stage Directorate of Energy, Himachal Pradesh Himachal Pradesh 01-Nov-2019
613 Hydel Power (Radhanagari) Project 10.0 MW (Mega Watt) 48 Energy Renewable energy (grid) Operation and Maintenance Stage Water Resources Department, Maharashtra Maharashtra 01-Nov-2019
614 Hydel Power (Sarsadi-II) Project 9.0 MW (Mega Watt) 62.46 Energy Renewable energy (grid) Pre-construction Stage Directorate of Energy, Himachal Pradesh Himachal Pradesh 01-Nov-2019
615 Hydel Power (Telling) Project 94.0 MW (Mega Watt) 658 Energy Renewable energy (grid) Pre-construction Stage Directorate of Energy, Himachal Pradesh Himachal Pradesh 01-Nov-2019
616 Hydel Power (Tinget) Project # 81.0 MW (Mega Watt) 567 Energy Renewable energy (grid) Pre-construction Stage Directorate of Energy, Himachal Pradesh Himachal Pradesh 01-Nov-2019
617 Hydel Power (Uhl Khad) Project 14.0 MW (Mega Watt) 115 Energy Renewable energy (grid) Pre-construction Stage Directorate of Energy, Himachal Pradesh Himachal Pradesh 01-Nov-2019
618 Hydel Power (Vajra - III) Project 1.5 MW (Mega Watt) 7.2 Energy Renewable energy (grid) Operation and Maintenance Stage Water Resources Department, Maharashtra Maharashtra 01-Nov-2019
619 Hydro Electric Power (Akole) Project 7.0 MW (Mega Watt) 43.2 Energy Renewable energy (grid) Operation and Maintenance Stage Water Resources Department, Maharashtra Maharashtra 01-Nov-2019
620 Hydro Electric Power (Bhor) Project 4.8 MW (Mega Watt) 23.04 Energy Renewable energy (grid) Operation and Maintenance Stage Water Resources Department, Maharashtra Maharashtra 01-Nov-2019
621 Hydro Electric Power (Bhusaval) Project 2.0 MW (Mega Watt) 10.56 Energy Renewable energy (grid) Under Construction Water Resources Department, Maharashtra Maharashtra 01-Nov-2019
622 Hydro Electric Power (Chikotra) Project 1.8 MW (Mega Watt) 10.5 Energy Renewable energy (grid) Operation and Maintenance Stage Water Resources Department, Maharashtra Maharashtra 01-Nov-2019
623 Hydro Electric Power (Chitri) Project 2.0 MW (Mega Watt) 9.6 Energy Renewable energy (grid) Operation and Maintenance Stage Water Resources Department, Maharashtra Maharashtra 01-Nov-2019
624 Hydro Electric Power (Dhom Balkawadi) Project 4.0 MW (Mega Watt) 19.2 Energy Renewable energy (grid) Operation and Maintenance Stage Water Resources Department, Maharashtra Maharashtra 01-Nov-2019
625 Hydro Electric Power (Gautami Godavari) Project 1.2 MW (Mega Watt) 5.76 Energy Renewable energy (grid) Operation and Maintenance Stage Water Resources Department, Maharashtra Maharashtra 01-Nov-2019
626 Hydro Electric Power (Ghataprabha) Project 8.0 MW (Mega Watt) 38.4 Energy Renewable energy (grid) Operation and Maintenance Stage Water Resources Department, Maharashtra Maharashtra 01-Nov-2019
627 Hydro Electric Power (Hetawane) Project 1.50 MW (Mega Watt) 6.8 Energy Renewable energy (grid) Operation and Maintenance Stage Water Resources Department, Maharashtra Maharashtra 01-Nov-2019
628 Hydro Electric Power (Jambre) Project 2.0 MW (Mega Watt) 14.32 Energy Renewable energy (grid) Under Construction Water Resources Department, Maharashtra Maharashtra 01-Nov-2019
629 Hydro Electric Power (Junnar) Project 3.0 MW (Mega Watt) 15.62 Energy Renewable energy (grid) Operation and Maintenance Stage Water Resources Department, Maharashtra Maharashtra 01-Nov-2019
630 Hydro Electric Power (Kadavi) Project 1.5 MW (Mega Watt) 7.2 Energy Renewable energy (grid) Completed Water Resources Department, Maharashtra Maharashtra 01-Nov-2019
631 Hydro Electric Power (Kumbhi) Project 2.5 MW (Mega Watt) 12 Energy Renewable energy (grid) Operation and Maintenance Stage Water Resources Department, Maharashtra Maharashtra 01-Nov-2019
632 Hydro Electric Power (Mukane) Project 1.45 MW (Mega Watt) 7.32 Energy Renewable energy (grid) Completed Water Resources Department, Maharashtra Maharashtra 01-Nov-2019
633 Hydro Electric Power (Nisare) Project 2.25 MW (Mega Watt) 10.8 Energy Renewable energy (grid) Pre-construction Stage Water Resources Department, Maharashtra Maharashtra 01-Nov-2019
634 Hydro Electric Power (Parseoni) Project - Package 1 1.4 MW (Mega Watt) 6.72 Energy Renewable energy (grid) Operation and Maintenance Stage Water Resources Department, Maharashtra Maharashtra 01-Nov-2019
635 Hydro Electric Power (Parseoni) Project - Package 2 4.4 MW (Mega Watt) 32.94 Energy Renewable energy (grid) Operation and Maintenance Stage Water Resources Department, Maharashtra Maharashtra 01-Nov-2019
636 Hydro Electric Power (Patgaon) Project 2.5 MW (Mega Watt) 12 Energy Renewable energy (grid) Operation and Maintenance Stage Water Resources Department, Maharashtra Maharashtra 01-Nov-2019
637 Hydro Electric Power (Satara) Project 1.20 MW (Mega Watt) 7.5 Energy Renewable energy (grid) Operation and Maintenance Stage Water Resources Department, Maharashtra Maharashtra 01-Nov-2019
638 Hydro Electric Power (Temghar) Project 4.0 MW (Mega Watt) 26.24 Energy Renewable energy (grid) Completed Water Resources Department, Maharashtra Maharashtra 01-Nov-2019
639 Hydro Electric Power (Urmodi) Project 3.0 MW (Mega Watt) 14.4 Energy Renewable energy (grid) Operation and Maintenance Stage Water Resources Department, Maharashtra Maharashtra 01-Nov-2019
640 Hydro Electric Power (Waghur) Project 1.5 MW (Mega Watt) 7.89 Energy Renewable energy (grid) Operation and Maintenance Stage Water Resources Department, Maharashtra Maharashtra 01-Nov-2019
641 Hydro Electric Power (Waki) Project 1.15 MW (Mega Watt) 6.54 Energy Renewable energy (grid) Under Construction Water Resources Department, Maharashtra Maharashtra 01-Nov-2019
642 Kilhi-Bahl Hydel Power Project # 7.5 MW (Mega Watt) 21 Energy Renewable energy (grid) Pre-construction Stage Directorate of Energy, Himachal Pradesh Himachal Pradesh 01-Nov-2019
643 Kurhed Hydel Power Project - Stage II # 7.5 MW (Mega Watt) 58.27 Energy Renewable energy (grid) Pre-construction Stage Directorate of Energy, Himachal Pradesh Himachal Pradesh 01-Nov-2019
644 Kurpan Hydel Power Project - Stage III # 14.6 MW (Mega Watt) 122.14 Energy Renewable energy (grid) Pre-construction Stage Directorate of Energy, Himachal Pradesh Himachal Pradesh 01-Nov-2019
645 Kuwarsi Hydel Power Project - Stage II 15.0 MW (Mega Watt) 95.79 Energy Renewable energy (grid) Under Construction Directorate of Energy, Himachal Pradesh Himachal Pradesh 01-Nov-2019
646 Laxman Mandwa Small Hydro Power Project * 5.0 MW (Mega Watt) 25 Energy Renewable energy (grid) Not Available Narmada Valley Development Authority Madhya Pradesh 01-Nov-2019
647 Madho-I Small Hydel Power Project # * 3.7 MW (Mega Watt) 45.97 Energy Renewable energy (grid) Pre-construction Stage Uttar Pradesh Jal Vidyut Nigam Limited Uttar Pradesh 01-Nov-2019
648 Madho-II Small Hydel Power Project # * 2.5 MW (Mega Watt) 23.05 Energy Renewable energy (grid) Pre-construction Stage Uttar Pradesh Jal Vidyut Nigam Limited Uttar Pradesh 01-Nov-2019
649 Malana Hydel Power Project - Stage III # 30.0 MW (Mega Watt) 212.66 Energy Renewable energy (grid) Pre-construction Stage Directorate of Energy, Himachal Pradesh Himachal Pradesh 01-Nov-2019
650 Mandsaur Wind Power Project in Madhya Pradesh 55.2 MW (Mega Watt) 326 Energy Renewable energy (grid) Operation and Maintenance Stage Marut-Shakti Energy India Limited Madhya Pradesh 01-Nov-2019
651 Miyar Hydel Power Project # 120.0 MW (Mega Watt) 1125.16 Energy Renewable energy (grid) Pre-construction Stage Directorate of Energy, Himachal Pradesh Himachal Pradesh 01-Nov-2019
652 Muzaffarpur -Sursand Transmission Line * 87.0 CKM (Circuit Kilo Meter) 210.7 Energy Electricity transmission Under Construction Power Grid Corpn. of India Ltd. Bihar 01-Nov-2019
653 Nazeerabad Wind Farm, Mytrah 100.0 MW (Mega Watt) 795 Energy Renewable energy (grid) Operation and Maintenance Stage Not Available Telangana 01-Nov-2019
654 Nesang Hydel Power Project # 20.0 MW (Mega Watt) 70 Energy Renewable energy (grid) Pre-construction Stage Directorate of Energy, Himachal Pradesh Himachal Pradesh 01-Nov-2019
655 Nirgajini Small Hydel Power Project * 5.0 MW (Mega Watt) 108.43 Energy Renewable energy (grid) Pre-construction Stage Uttar Pradesh Jal Vidyut Nigam Limited Uttar Pradesh 01-Nov-2019
656 Northern Region System Strengthening Scheme (NRSS-XXXI (Part-B) * Not Available 200 Energy Electricity transmission Under Construction REC Transmission Projects Company Limited Multi State/ Centre 01-Nov-2019
657 Panan Hydro Power project # * 300.0 MW (Mega Watt) 2021.9 Energy Renewable energy (grid) Pre-construction Stage Sikkim Power Development Corporation Limited Sikkim 01-Nov-2019
658 Parbati Hydel Power Project # 12.0 MW (Mega Watt) 78.35 Energy Renewable energy (grid) Pre-construction Stage Directorate of Energy, Himachal Pradesh Himachal Pradesh 01-Nov-2019
659 Power Plant Hetwane, Raigarh * 1.5 MW (Mega Watt) 6.8 Energy Electricity generation (grid) Under Construction Water Resources Department, Maharashtra Maharashtra 01-Nov-2019
660 PPP-10:5 No. transmisson line of 132 kV at various places 132.0 KV (Kilo Volt) 117.7 Energy Electricity transmission Operation and Maintenance Stage Rajasthan Rajya Vidyut Prasaran Nigam Limited Rajasthan 01-Nov-2019
661 PPP-8:1 No. transmission line of 220 kV and 5 No. 132 kV GSS at various places 220.0 KV (Kilo Volt) 149 Energy Electricity transmission Operation and Maintenance Stage Rajasthan Rajya Vidyut Prasaran Nigam Limited Rajasthan 01-Nov-2019
662 PPP-9:6 No. transmisson line of 132 kV at various places 132.0 KV (Kilo Volt) 128.81 Energy Electricity transmission Operation and Maintenance Stage Rajasthan Rajya Vidyut Prasaran Nigam Limited Rajasthan 01-Nov-2019
663 Ram Ganga Small Hydel Power Project # * 3.2 MW (Mega Watt) 30.41 Energy Renewable energy (grid) Pre-construction Stage Uttar Pradesh Jal Vidyut Nigam Limited Uttar Pradesh 01-Nov-2019
664 Rewa Ultra Mega Solar Ltd 750.0 MW (Mega Watt) 4000 Energy Renewable energy (grid) Operation and Maintenance Stage Not Available Madhya Pradesh 01-Nov-2019
665 Rongnichu Stroage Hydro Power Plant * 96.0 MW (Mega Watt) 544 Energy Renewable energy (grid) Under Construction Sikkim Power Development Corporation Limited Sikkim 01-Nov-2019
666 Rupin Hydel Power Project # 45.0 MW (Mega Watt) 292.61 Energy Renewable energy (grid) Pre-construction Stage Directorate of Energy, Himachal Pradesh Himachal Pradesh 01-Nov-2019
667 Salawa Small Hydel Power Project * 3.0 MW (Mega Watt) 54.55 Energy Renewable energy (grid) Pre-construction Stage Uttar Pradesh Jal Vidyut Nigam Limited Uttar Pradesh 01-Nov-2019
668 Sarsadi Hydel Power Project - Stage I # 9.6 MW (Mega Watt) 88.3 Energy Renewable energy (grid) Pre-construction Stage Directorate of Energy, Himachal Pradesh Himachal Pradesh 01-Nov-2019
669 Setting up a 120 MW Rangit-IV Hydel Power Project # 120.0 MW (Mega Watt) 726.16 Energy Renewable energy (grid) Under Construction Sikkim Power Development Corporation Limited Sikkim 01-Nov-2019
670 Setting up of 66 MW Rangit-II Hydel Power Project * 66.0 MW (Mega Watt) 497.17 Energy Renewable energy (grid) Under Construction Sikkim Power Development Corporation Limited Sikkim 01-Nov-2019
671 Setting up of 0.9 MW Dham hydro electric power unit at Arvi in Wardha district 0.95 MW (Mega Watt) 6.59 Energy Renewable energy (grid) Under Construction Water Resources Department, Maharashtra Maharashtra 01-Nov-2019
672 Setting up of 1.5 MW hydel based power unit at Bor in Wardha district # 1.5 MW (Mega Watt) 7.55 Energy Renewable energy (grid) Pre-construction Stage Water Resources Department, Maharashtra Maharashtra 01-Nov-2019
673 Setting up of 1.5 MW hydel based power unit at Karwand in Dhule 1.5 MW (Mega Watt) 5.67 Energy Renewable energy (grid) Pre-construction Stage Water Resources Department, Maharashtra Maharashtra 01-Nov-2019
674 Setting up of 10 MW Konal hydel power unit in Sindhudurga district 10.0 MW (Mega Watt) 67 Energy Renewable energy (grid) Operation and Maintenance Stage Water Resources Department, Maharashtra Maharashtra 01-Nov-2019
675 Setting up of 11 MW hydel based power unit at Mokhada in Thane 11.0 MW (Mega Watt) 8.57 Energy Renewable energy (grid) Pre-construction Stage Water Resources Department, Maharashtra Maharashtra 01-Nov-2019
676 Setting up of 15 MW co-generation power unit at Fazilka Sugar Mill in Ferozepur district * 15.0 MW (Mega Watt) 80 Energy Renewable energy (grid) Under Construction Punjab State Federation of Co-operative Sugar Mills Limited Punjab 01-Nov-2019
677 Setting up of 15 MW co-generation power unit at Morinda Sugar Mill in Rupnagar district * 15.0 MW (Mega Watt) 100 Energy Renewable energy (grid) Under Construction Punjab State Federation of Co-operative Sugar Mills Limited Punjab 01-Nov-2019
678 Setting up of 15 MW Taramchu small hydel based power unit in North Sikkim # * 15.0 MW (Mega Watt) 240 Energy Renewable energy (grid) Pre-construction Stage Sikkim Power Development Corporation Limited Sikkim 01-Nov-2019
679 Setting up of 2 MW hydel based power unit at Gunjawani in Pune 2.0 MW (Mega Watt) Not Available Energy Renewable energy (grid) Operation and Maintenance Stage Water Resources Department, Maharashtra Maharashtra 01-Nov-2019
680 Setting up of 24 MW hydel based power unit at Gosikhurd in Bhandara district 24.0 MW (Mega Watt) Not Available Energy Renewable energy (grid) Operation and Maintenance Stage Water Resources Department, Maharashtra Maharashtra 01-Nov-2019
681 Setting up of 2x50 MW Tidong-I hydel power unit in Kinnaur district 100.0 MW (Mega Watt) Not Applicable Energy Renewable energy (grid) Under Construction Directorate of Energy, Himachal Pradesh Himachal Pradesh 01-Nov-2019
682 Setting up of 3 MW hydel based power unit at Nardave in Sindhudurg 3.0 MW (Mega Watt) Not Applicable Energy Renewable energy (grid) Pre-construction Stage Water Resources Department, Maharashtra Maharashtra 01-Nov-2019
683 Setting up of 4 MW hydel power unit at Mula right bank canal in Rahuri district 4.0 MW (Mega Watt) 19 Energy Renewable energy (grid) Operation and Maintenance Stage Water Resources Department, Maharashtra Maharashtra 01-Nov-2019
684 Setting up of 4.5 MW Tembhu barrage hydro electric power project in Satara district 4.5 MW (Mega Watt) 34.31 Energy Renewable energy (grid) Operation and Maintenance Stage Water Resources Department, Maharashtra Maharashtra 01-Nov-2019
685 Setting up of 44 MW Tangnu Romai-I hydel power unit in Shimla district 44.0 MW (Mega Watt) 255 Energy Renewable energy (grid) Under Construction Directorate of Energy, Himachal Pradesh Himachal Pradesh 01-Nov-2019
686 Setting up of 5 MW hydel based power unit at Tarali in Satara 5.0 MW (Mega Watt) 39.18 Energy Renewable energy (grid) Pre-construction Stage Water Resources Department, Maharashtra Maharashtra 01-Nov-2019
687 Setting up of 500 MW Teesta-VI hydel power unti in Southern Sikkim # 500.0 MW (Mega Watt) 5400 Energy Renewable energy (grid) Under Construction Sikkim Power Development Corporation Limited Sikkim 01-Nov-2019
688 Setting up of 850 MW hydel power unit at Kishtwar in Doda district * 850.0 MW (Mega Watt) 5500 Energy Renewable energy (grid) Under Construction Jammu and Kashmir State Power Development Corporation Limited Jammu & Kashmir 01-Nov-2019
689 Setting up of 99 MW Singoli Bhatwari hydroelectric power plant in Rudraprayag district # 99.0 MW (Mega Watt) 666.47 Energy Renewable energy (grid) Under Construction Uttar Pradesh Jal Vidyut Nigam Limited Uttarakhand 01-Nov-2019
690 Shangling Hydel Power Project # 44.0 MW (Mega Watt) 308 Energy Renewable energy (grid) Pre-construction Stage Directorate of Energy, Himachal Pradesh Himachal Pradesh 01-Nov-2019
691 Sharni Hydel Power Project # 9.6 MW (Mega Watt) 87.02 Energy Renewable energy (grid) Pre-construction Stage Directorate of Energy, Himachal Pradesh Himachal Pradesh 01-Nov-2019
692 Small Hydel Power (Kareri) Project 5.0 MW (Mega Watt) 34.16 Energy Renewable energy (grid) Under Construction Himachal Pradesh Energy Development Agency Himachal Pradesh 01-Nov-2019
693 Small Hydel Power (Lower Sumej) Project 5.0 MW (Mega Watt) 42.38 Energy Renewable energy (grid) Pre-construction Stage Himachal Pradesh Energy Development Agency Himachal Pradesh 01-Nov-2019
694 Small Hydel Power (Tauhak ) Project 4.5 MW (Mega Watt) 28.6 Energy Renewable energy (grid) Pre-construction Stage Himachal Pradesh Energy Development Agency Himachal Pradesh 01-Nov-2019
695 Solar Power (Shivajinagar) Project * 25.0 MW (Mega Watt) 200 Energy Renewable energy (grid) Under Construction Maharashtra State Power Generation Company Limited Maharashtra 01-Nov-2019
696 Suil Hydel Power Project # 13.0 MW (Mega Watt) 91 Energy Renewable energy (grid) Pre-construction Stage Directorate of Energy, Himachal Pradesh Himachal Pradesh 01-Nov-2019
697 Tangnu Romai Hydel Power Project - Stage II 6.0 MW (Mega Watt) 31.5 Energy Renewable energy (grid) Under Construction Directorate of Energy, Himachal Pradesh Himachal Pradesh 01-Nov-2019
698 Tashiding Hydro Electric Power Project 97.0 MW (Mega Watt) 494.44 Energy Renewable energy (grid) Operation and Maintenance Stage Sikkim Power Development Corporation Limited Sikkim 01-Nov-2019
699 Transmission Line (Bara-Mainpuri) Project * 765.0 KM (Kilometer) 5158.91 Energy Electricity transmission Under Construction Uttar Pradesh Power Transmission Corporation Limited Uttar Pradesh 01-Nov-2019
700 Transmission Line (Bikaner-Deedwana-Ajmer) Project 400.0 KV (Kilo Volt) 285 Energy Electricity transmission Operation and Maintenance Stage Rajasthan Rajya Vidyut Prasaran Nigam Limited Rajasthan 01-Nov-2019
701 Transmission Line (Mainpuri-Hapur) Project * 764.0 KM (Kilometer) 4706.49 Energy Electricity transmission Under Construction Uttar Pradesh Power Transmission Corporation Limited Uttar Pradesh 01-Nov-2019
702 Walipura Small Hydel Power Project * 0.4 MW (Mega Watt) 7 Energy Renewable energy (grid) Under Construction Uttar Pradesh New and Renewable Energy Development Agency Uttar Pradesh 01-Nov-2019
703 Youngthang Khab Hydel Power Project # 261.0 MW (Mega Watt) 2500 Energy Renewable energy (grid) Pre-construction Stage Directorate of Energy, Himachal Pradesh Himachal Pradesh 01-Nov-2019
704 Adani Power Maharashtra Limited 3300.0 MW (Mega Watt) 19003 Energy Electricity generation (grid) Operation and Maintenance Stage Maharashtra State Electricity Distribution Company Limited Maharashtra 30-Oct-2019
705 Adani Power Rajasthan Limited 1320.0 MW (Mega Watt) 8323 Energy Electricity generation (grid) Operation and Maintenance Stage Jaipur Vidyut Vitran Nigam Ltd, Jodhpur Vidyut Vitran Nigam Ltd, Ajmer Vidyut Vitran Nigam Ltd Rajasthan 30-Oct-2019
706 Bara Bangahal Hydel Power Project - Stage I # 92.0 MW (Mega Watt) 644 Energy Renewable energy (grid) Pre-construction Stage Directorate of Energy, Himachal Pradesh Himachal Pradesh 30-Oct-2019
707 Bara Bangahal Hydel Power Project - Stage II # 108.0 MW (Mega Watt) 756 Energy Renewable energy (grid) Operation and Maintenance Stage Directorate of Energy, Himachal Pradesh Himachal Pradesh 30-Oct-2019
708 Baspa Hydel Power Project - Stage II 300.0 MW (Mega Watt) 1629.84 Energy Renewable energy (grid) Operation and Maintenance Stage Directorate of Energy, Himachal Pradesh Himachal Pradesh 30-Oct-2019
709 Bhang Hydel Power Project # 9.0 MW (Mega Watt) 81.78 Energy Renewable energy (grid) Pre-construction Stage Directorate of Energy, Himachal Pradesh Himachal Pradesh 30-Oct-2019
710 Bharmour Hydel Power Project - Stage I Bharmour Hydel Power Project - Stage I # 24.0 MW (Mega Watt) 254.2 Energy Renewable energy (grid) Pre-construction Stage Directorate of Energy, Himachal Pradesh Himachal Pradesh 30-Oct-2019
711 Bharmour Hydel Power Project - Stage II # 21.0 MW (Mega Watt) 167.5 Energy Renewable energy (grid) Pre-construction Stage Directorate of Energy, Himachal Pradesh Himachal Pradesh 30-Oct-2019
712 Bina thermal power project 500.0 MW (Mega Watt) 3518.83 Energy Electricity generation (grid) Operation and Maintenance Stage Madhya Pradesh Electricity Regulatory Commission Madhya Pradesh 30-Oct-2019
713 Brua Hydel Power Project 9.0 MW (Mega Watt) 70.18 Energy Renewable energy (grid) Operation and Maintenance Stage Directorate of Energy, Himachal Pradesh Himachal Pradesh 30-Oct-2019
714 Chango-Yangthang Hydel Power Project # 180.0 MW (Mega Watt) 2077.29 Energy Renewable energy (grid) Pre-construction Stage Directorate of Energy, Himachal Pradesh Himachal Pradesh 30-Oct-2019
715 Chanju Hydel Power Project - Stage II # 19.8 MW (Mega Watt) 161 Energy Renewable energy (grid) Pre-construction Stage Directorate of Energy, Himachal Pradesh Himachal Pradesh 30-Oct-2019
716 Chatru Hydel Power Project # 126.0 MW (Mega Watt) 540.33 Energy Renewable energy (grid) Pre-construction Stage Directorate of Energy, Himachal Pradesh Himachal Pradesh 30-Oct-2019
717 Dhancho Hydel Power Project # 18.0 MW (Mega Watt) 135.51 Energy Renewable energy (grid) Pre-construction Stage Directorate of Energy, Himachal Pradesh Himachal Pradesh 30-Oct-2019
718 Electricity Distribution Ahmedabad, Surat, Gandhinagar and Dahej cities Not Available 4632.54 Energy Electricity Distribution Operation and Maintenance Stage Gujarat Urja Vikas Nigam Limited Gujarat 30-Oct-2019
719 Electricity distribution Ajmer City (TPADL) Not Available 208.1 Energy Electricity Distribution Operation and Maintenance Stage Ajmer Vidyut Vitran Nigam Limited Rajasthan 30-Oct-2019
720 Electricity distribution Bikaner City Circle (BkESL) Not Available 114.61 Energy Electricity Distribution Operation and Maintenance Stage Jodhpur Vidyut Vitran Nigam Limited Rajasthan 30-Oct-2019
721 Electricity Distribution Delhi (TPDDL) Not Available 5836.02 Energy Electricity Distribution Operation and Maintenance Stage Tata Power Delhi Distribution Limited (TPDDL) Delhi (UT) 30-Oct-2019
722 Electricity Distribution Delhi city (BYPL) Not Available 3080.5 Energy Electricity Distribution Operation and Maintenance Stage BSES YAMUNA POWER LIMITED (BYPL) Delhi (UT) 30-Oct-2019
723 Electricity Distribution in various parts of Odisha (Khurda, Balugaon, Puri and Nayagarh) Not Available 80.47 Energy Electricity Distribution Operation and Maintenance Stage Orissa Electricity Regulatory Commission Odisha 30-Oct-2019
724 Electricity Distribution Jamshedpur city Not Available 181.43 Energy Electricity Distribution Operation and Maintenance Stage Jamshedpur Utility Services Company Limited(JUSCO) Jharkhand 30-Oct-2019
725 Electricity Distribution New Delhi city (BRPL) Not Available 6021 Energy Electricity Distribution Operation and Maintenance Stage BSES RajdhaniPowerLimited (BRPL) Delhi (UT) 30-Oct-2019
726 Electricity Distribution Noida city (NPCL) Not Available 1457.1 Energy Electricity Distribution Operation and Maintenance Stage NOIDA POWER COMPANY LIMITED (NPCL) Uttar Pradesh 30-Oct-2019
727 ESSAR Power-Hazira, Power Plant Project 515.0 MW (Mega Watt) 1600 Energy Electricity generation (grid) Operation and Maintenance Stage Energy & Petrochemicals Department, Gujarat Gujarat 30-Oct-2019
728 Gas based power plants and Thermal based power plants in Vadodara and Surat 815.0 MW (Mega Watt) 2037 Energy Electricity generation (grid) Operation and Maintenance Stage Gujarat Industries Power Company Limited Gujarat 30-Oct-2019
729 Gujarat Paguthan Energy Corporation Power Plant Project 655.0 MW (Mega Watt) 2247 Energy Electricity generation (grid) Completed Gujarat Urja Vikas Nigam Limited Gujarat 30-Oct-2019
730 Gurha Lignite Power Project * 70.0 MW (Mega Watt) 0 Energy Electricity generation (grid) Under Construction Rajasthan Rajya Vidyut Prasaran Nigam Limited Rajasthan 30-Oct-2019
731 Haldia Coal based power project 600.0 MW (Mega Watt) 3307 Energy Electricity generation (grid) Operation and Maintenance Stage India Power Corpn (Haldia) Limited West Bengal 30-Oct-2019
732 Hydel Power (Sachkhas) Project 267.0 MW (Mega Watt) 2845.75 Energy Renewable energy (grid) Pre-construction Stage Directorate of Energy, Himachal Pradesh Himachal Pradesh 30-Oct-2019
733 Hydel Power (Bharari) Project 6.0 MW (Mega Watt) 41.62 Energy Renewable energy (grid) Pre-construction Stage Directorate of Energy, Himachal Pradesh Himachal Pradesh 30-Oct-2019
734 Hydel Power (Chirchind-II) Project 12.9 MW (Mega Watt) 67.46 Energy Renewable energy (grid) Operation and Maintenance Stage Directorate of Energy, Himachal Pradesh Himachal Pradesh 30-Oct-2019
735 Hydel Power (Choned) Project 15.0 MW (Mega Watt) 114.72 Energy Renewable energy (grid) Pre-construction Stage Directorate of Energy, Himachal Pradesh Himachal Pradesh 30-Oct-2019
736 Hydel Power (Harsar Stage-I) Project 28.5 MW (Mega Watt) 199.5 Energy Renewable energy (grid) Pre-construction Stage Directorate of Energy, Himachal Pradesh Himachal Pradesh 30-Oct-2019
737 Hydel Power (Harsar Stage-II) Project 22.5 MW (Mega Watt) 212.31 Energy Renewable energy (grid) Pre-construction Stage Directorate of Energy, Himachal Pradesh Himachal Pradesh 30-Oct-2019
738 Hydel Power (Harsar Stage-III) Project 19.0 MW (Mega Watt) 178.57 Energy Renewable energy (grid) Pre-construction Stage Directorate of Energy, Himachal Pradesh Himachal Pradesh 30-Oct-2019
739 Hydel Power (Holi-II) Project 7.0 MW (Mega Watt) 64.9 Energy Renewable energy (grid) Under Construction Directorate of Energy, Himachal Pradesh Himachal Pradesh 30-Oct-2019
740 Hydel Power (Shirikhand) Project 8.0 MW (Mega Watt) 45.9 Energy Renewable energy (grid) Pre-construction Stage Directorate of Energy, Himachal Pradesh Himachal Pradesh 30-Oct-2019
741 Hydel Power (Uhl) Project 14.0 MW (Mega Watt) 140 Energy Renewable energy (grid) Operation and Maintenance Stage Directorate of Energy, Himachal Pradesh Himachal Pradesh 30-Oct-2019
742 Hydel Power (Umli) Project 10.0 MW (Mega Watt) 99.62 Energy Renewable energy (grid) Operation and Maintenance Stage Directorate of Energy, Himachal Pradesh Himachal Pradesh 30-Oct-2019
743 Jegurupadu Combined Cycle Power Project 445.0 MW (Mega Watt) 1025 Energy Electricity generation (grid) Operation and Maintenance Stage Andhra Pradesh State Electricity Board Andhra Pradesh 30-Oct-2019
744 Jobrie Hydel Power Project 12.0 MW (Mega Watt) 84 Energy Renewable energy (grid) Pre-construction Stage Directorate of Energy, Himachal Pradesh Himachal Pradesh 30-Oct-2019
745 Krishnapatnam Ultra Mega Power Project # * 4000.0 MW (Mega Watt) 1015 Energy Electricity generation (grid) Under Construction Power Finance Corporation Ltd Andhra Pradesh 30-Oct-2019
746 KSK Mahanadi Power Co Limited 3600.0 MW (Mega Watt) 14969 Energy Electricity generation (grid) Operation and Maintenance Stage Not Available Chhattisgarh 30-Oct-2019
747 Kudgi TPS Transmission Line Project * 482.0 KM (Kilometer) 1350 Energy Electricity transmission Under Construction Kudgi Transmission Limited Karnataka 30-Oct-2019
748 Malana Hydel Power Project - Stage I 86.0 MW (Mega Watt) 341.91 Energy Renewable energy (grid) Operation and Maintenance Stage Directorate of Energy, Himachal Pradesh Himachal Pradesh 30-Oct-2019
749 Masrang Selti Hydel Power Project 24.0 MW (Mega Watt) 215.74 Energy Renewable energy (grid) Under Construction Directorate of Energy, Himachal Pradesh Himachal Pradesh 30-Oct-2019
750 Mundra Ultra Mega Power Project 4000.0 MW (Mega Watt) 17900 Energy Electricity generation (grid) Operation and Maintenance Stage Not Available Gujarat 30-Oct-2019
751 Nagarjuna Power Project 1015.0 MW (Mega Watt) 5496 Energy Electricity Distribution Operation and Maintenance Stage Karnataka Power Transmission Corporation Limited (KPTCL) Karnataka 30-Oct-2019
752 Nardana coal based thermal power plant # 300.0 MW (Mega Watt) 2485 Energy Electricity generation (grid) Operation and Maintenance Stage Not Available Maharashtra 30-Oct-2019
753 Natural Gas based 220 MW, Kakinada Power project 220.0 MW (Mega Watt) 600 Energy Electricity generation (grid) Operation and Maintenance Stage Not Available Andhra Pradesh 30-Oct-2019
754 Nawapara coal based power project, Raigarh 600.0 MW (Mega Watt) 2844 Energy Electricity generation (grid) Operation and Maintenance Stage Chhattisgarh State Electricity Board Chhattisgarh 30-Oct-2019
755 Nigrie Super Thermal Power Project 1320.0 MW (Mega Watt) 12350 Energy Electricity generation (grid) Operation and Maintenance Stage Not Available Madhya Pradesh 30-Oct-2019
756 Reoli Dugli Hydel Power Project # * 429.0 MW (Mega Watt) 2132.19 Energy Renewable energy (grid) Pre-construction Stage Directorate of Energy, Himachal Pradesh Himachal Pradesh 30-Oct-2019
757 Sasan Ultra Mega Power Project 3960.0 MW (Mega Watt) 25186 Energy Electricity generation (grid) Operation and Maintenance Stage Central Electricity Regulatory Commission Madhya Pradesh 30-Oct-2019
758 Setting up of 45 MW Saskangrong hydel power unit in West Kameng # * 45.0 MW (Mega Watt) 25186 Energy Renewable energy (grid) Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 30-Oct-2019
759 Setting up of 10 MW Pein hydel power unit in Lower Subansiri# * 10.0 MW (Mega Watt) 71 Energy Renewable energy (grid) Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 30-Oct-2019
760 Setting up of 10 MW Pitgong-II hydel power unit in Arunachal Pradesh # * 10.0 MW (Mega Watt) 77 Energy Renewable energy (grid) Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 30-Oct-2019
761 Setting up of 100 MW Malana II hydel power unit in Kullu district 100.0 MW (Mega Watt) 981.91 Energy Renewable energy (grid) Operation and Maintenance Stage Directorate of Energy, Himachal Pradesh Himachal Pradesh 30-Oct-2019
762 Setting up of 100 MW Sissiri hydel power unit in Lower Dibang Valley # * 100.0 MW (Mega Watt) 699 Energy Renewable energy (grid) Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 30-Oct-2019
763 Setting up of 100 MW Sorang hydel power unit in Kinnaur district 100.0 MW (Mega Watt) 586 Energy Renewable energy (grid) Under Construction Directorate of Energy, Himachal Pradesh Himachal Pradesh 30-Oct-2019
764 Setting up of 1000 MW Karchham Wangtoo hydel power unit in Kinnaur district # 1000.0 MW (Mega Watt) 6900 Energy Renewable energy (grid) Operation and Maintenance Stage Directorate of Energy, Himachal Pradesh Himachal Pradesh 30-Oct-2019
765 Setting up of 1000 MW Naba hydel power unit in Arunachal Pradesh # * 1000.0 MW (Mega Watt) 6500 Energy Renewable energy (grid) Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 30-Oct-2019
766 Setting up of 1000 MW Naying hydel power unit in West Siang # * 1000.0 MW (Mega Watt) 9301.1 Energy Renewable energy (grid) Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 30-Oct-2019
767 Setting up of 1000 MW Siyom hydel power unit in West Siang district # * 1000.0 MW (Mega Watt) 12100 Energy Renewable energy (grid) Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 30-Oct-2019
768 Setting up of 1080 MW Upper Demwe hydel power unit in Lohit # * 1080.0 MW (Mega Watt) 5000 Energy Renewable energy (grid) Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 30-Oct-2019
769 Setting up of 111 MW Lower Yamne-I hydel power unit in Upper Siang # * 111.0 MW (Mega Watt) 540 Energy Renewable energy (grid) Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 30-Oct-2019
770 Setting up of 111 MW Yamne Stage-I hydel power unit in Upper Siang* 111.0 MW (Mega Watt) 775 Energy Renewable energy (grid) Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 30-Oct-2019
771 Setting up of 12 MW Pichang hydel power unit in East Kameng # * 12.0 MW (Mega Watt) 84 Energy Renewable energy (grid) Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 30-Oct-2019
772 Setting up of 12 MW Raura hydel power unit in Kinnaur district * 12.0 MW (Mega Watt) 65.95 Energy Renewable energy (grid) Under Construction Directorate of Energy, Himachal Pradesh Himachal Pradesh 30-Oct-2019
773 Setting up of 12 MW Tenga hydel power unit in West Kameng # * 12.0 MW (Mega Watt) 84 Energy Renewable energy (grid) Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 30-Oct-2019
774 Setting up of 12 MW Upper Joiner hydel power unit in Chamba district # 12.0 MW (Mega Watt) 72.25 Energy Renewable energy (grid) Operation and Maintenance Stage Directorate of Energy, Himachal Pradesh Himachal Pradesh 30-Oct-2019
775 Setting up of 120 MW Bhareli-II hydel power unit in West Kameng # * 120.0 MW (Mega Watt) 4200 Energy Renewable energy (grid) Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 30-Oct-2019
776 Setting up of 120 MW Dibbin hydel power unit in West Kameng district # * 120.0 MW (Mega Watt) 900 Energy Renewable energy (grid) Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 30-Oct-2019
777 Setting up of 1200 MW Hutong- II hydel power unit in Anjaw district* 1200.0 MW (Mega Watt) 15167 Energy Renewable energy (grid) Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 30-Oct-2019
778 Setting up of 1200 MW Kalai-II hydel power unit in Anjaw district# * 1200.0 MW (Mega Watt) 6955 Energy Renewable energy (grid) Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 30-Oct-2019
779 Setting up of 13 MW Nyikong hydel power unit in Upper Siang # * 13.0 MW (Mega Watt) 94.9 Energy Renewable energy (grid) Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 30-Oct-2019
780 Setting up of 13 MW Pith hydel power unit at Yazali# * 13.0 MW (Mega Watt) 91 Energy Renewable energy (grid) Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 30-Oct-2019
781 Setting up of 13 MW Rala hydel power unit in Kinnaur district 13.0 MW (Mega Watt) 58.04 Energy Renewable energy (grid) Under Construction Directorate of Energy, Himachal Pradesh Himachal Pradesh 30-Oct-2019
782 Setting up of 13.5 MW Upper Nanti hydel power unit in Shimla 13.5 MW (Mega Watt) 80.66 Energy Renewable energy (grid) Operation and Maintenance Stage Directorate of Energy, Himachal Pradesh Himachal Pradesh 30-Oct-2019
783 Setting up of 1304 MW Kalai-I hydel power unit in Anjaw district # * 1304.0 MW (Mega Watt) 13444 Energy Renewable energy (grid) Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 30-Oct-2019
784 Setting up of 14 MW Kaying hydel power unit in West Siang# * 14.0 MW (Mega Watt) 115.5 Energy Renewable energy (grid) Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 30-Oct-2019
785 Setting up of 14 MW nanti hydel power unit in Shimla district # 14.0 MW (Mega Watt) 66.94 Energy Renewable energy (grid) Operation and Maintenance Stage Directorate of Energy, Himachal Pradesh Himachal Pradesh 30-Oct-2019
786 Setting up of 14 MW Sumez hydel power unit in Shimla district # 14.0 MW (Mega Watt) 92.08 Energy Renewable energy (grid) Operation and Maintenance Stage Directorate of Energy, Himachal Pradesh Himachal Pradesh 30-Oct-2019
787 Setting up of 141 MW Raigam hydel power unit in Lohit# * 141.0 MW (Mega Watt) 1609.38 Energy Renewable energy (grid) Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 30-Oct-2019
788 Setting up of 144 MW Gongri hydel power unit in West Kameng # * 144.0 MW (Mega Watt) 1436.27 Energy Renewable energy (grid) Under Construction Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 30-Oct-2019
789 Setting up of 145 MW Pauk hydel power unit in West Siang # * 145.0 MW (Mega Watt) 1015 Energy Renewable energy (grid) Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 30-Oct-2019
790 Setting up of 15 MW Neogal hydel power unit in Kangra district # 15.0 MW (Mega Watt) 61.74 Energy Renewable energy (grid) Operation and Maintenance Stage Directorate of Energy, Himachal Pradesh Himachal Pradesh 30-Oct-2019
791 Setting up of 15 MW Pakke Bung-II hydel power unit in East Kameng # * 15.0 MW (Mega Watt) 105 Energy Renewable energy (grid) Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 30-Oct-2019
792 Setting up of 15 MW Pakke Bung-IV hydel power unit in East Kameng # * 15.0 MW (Mega Watt) 105 Energy Renewable energy (grid) Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 30-Oct-2019
793 Setting up of 15 MW Palin hydel power unit in Kra Daadi # * 15.0 MW (Mega Watt) 106.5 Energy Renewable energy (grid) Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 30-Oct-2019
794 Setting up of 16 MW Jongini hydel power unit in Shimla district # 16.0 MW (Mega Watt) 79.06 Energy Renewable energy (grid) Operation and Maintenance Stage Directorate of Energy, Himachal Pradesh Himachal Pradesh 30-Oct-2019
795 Setting up of 16 MW Patikari hydel power unit in Mandi district 16.0 MW (Mega Watt) 115.63 Energy Renewable energy (grid) Operation and Maintenance Stage Directorate of Energy, Himachal Pradesh Himachal Pradesh 30-Oct-2019
796 Setting up of 1750 MW Lower Demwe hydel power unit in Lohit # * 1750.0 MW (Mega Watt) 10000 Energy Renewable energy (grid) Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 30-Oct-2019
797 Setting up of 18 MW Ankaling hydel power unit in West kameng # * 18.0 MW (Mega Watt) 126 Energy Renewable energy (grid) Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 30-Oct-2019
798 Setting up of 18 MW Lower Ngorgum hydel power unit in Arunachal Pradesh # * 18.0 MW (Mega Watt) 127.8 Energy Renewable energy (grid) Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 30-Oct-2019
799 Setting up of 18 MW Pacha hydel power unit in East Kameng # * 18.0 MW (Mega Watt) 126 Energy Renewable energy (grid) Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 30-Oct-2019
800 Setting up of 180 MW Bajoli Holi hydel power unit in Chamba district * 180.0 MW (Mega Watt) 1681.82 Energy Renewable energy (grid) Under Construction Directorate of Energy, Himachal Pradesh Himachal Pradesh 30-Oct-2019
801 Setting up of 1800 MW Kamala hydel power unit in Lower Subansiri district # * 1800.0 MW (Mega Watt) 20140.77 Energy Renewable energy (grid) Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 30-Oct-2019
802 Setting up of 1800 MW Oju hydel power unit in Upper Subansiri # * 1800.0 MW (Mega Watt) 10800 Energy Renewable energy (grid) Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 30-Oct-2019
803 Setting up of 186 MW Tato-I hydel power unit in West Siang # * 186.0 MW (Mega Watt) 1302 Energy Renewable energy (grid) Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 30-Oct-2019
804 Setting up of 192 MW Allain Duhangan hydel power unit in Kullu district # 192.0 MW (Mega Watt) 2021 Energy Renewable energy (grid) Operation and Maintenance Stage Directorate of Energy, Himachal Pradesh Himachal Pradesh 30-Oct-2019
805 Setting up of 21 MW Panyor Lepa Middle hydel power unit on Ranganadi river in Arunachal Pradesh* 21.0 MW (Mega Watt) 153.3 Energy Renewable energy (grid) Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 30-Oct-2019
806 Setting up of 21 MW Papumpam hydel power unit in Papum Pare # * 21.0 MW (Mega Watt) 157.5 Energy Renewable energy (grid) Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 30-Oct-2019
807 Setting up of 21 MW Sepla hydel power unit in East Kameng # * 21.0 MW (Mega Watt) 147 Energy Renewable energy (grid) Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 30-Oct-2019
808 Setting up of 22 MW Ithipani-II hydel power unit in Lower Dibang Valley # * 22.0 MW (Mega Watt) 154 Energy Renewable energy (grid) Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 30-Oct-2019
809 Setting up of 225 MW Talong hydel power unit in East Kameng # * 225.0 MW (Mega Watt) 2172 Energy Renewable energy (grid) Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 30-Oct-2019
810 Setting up of 23 MW Keyi hydel power unit in Lower Subansiri # * 23.0 MW (Mega Watt) 161 Energy Renewable energy (grid) Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 30-Oct-2019
811 Setting up of 24 MW Baragaon hydel power unit in Kullu district 24.0 MW (Mega Watt) 174.81 Energy Renewable energy (grid) Operation and Maintenance Stage Directorate of Energy, Himachal Pradesh Himachal Pradesh 30-Oct-2019
812 Setting up of 24 MW Dikshi hydel power unit in West kameng # * 24.0 MW (Mega Watt) 168 Energy Renewable energy (grid) Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 30-Oct-2019
813 Setting up of 24 MW Kamlang hydel power unit in Lohit # * 24.0 MW (Mega Watt) 182.4 Energy Renewable energy (grid) Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 30-Oct-2019
814 Setting up of 24 MW Kut hydel power unit in Shimla district 24.0 MW (Mega Watt) 189.5 Energy Renewable energy (grid) Operation and Maintenance Stage Directorate of Energy, Himachal Pradesh Himachal Pradesh 30-Oct-2019
815 Setting up of 24 MW Pakke Bung-III hydel power unit in East Kameng # * 24.0 MW (Mega Watt) 168 Energy Renewable energy (grid) Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 30-Oct-2019
816 Setting up of 24 MW Palsi-I hydel power unit in Upper Siang # * 24.0 MW (Mega Watt) 168 Energy Renewable energy (grid) Under Construction Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 30-Oct-2019
817 Setting up of 24 MW Panyi hydel power unit # * 24.0 MW (Mega Watt) 168 Energy Renewable energy (grid) Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 30-Oct-2019
818 Setting up of 24 MW Paudital hydel power unit in Shimla district 24.0 MW (Mega Watt) 210 Energy Renewable energy (grid) Under Construction Directorate of Energy, Himachal Pradesh Himachal Pradesh 30-Oct-2019
819 Setting up of 24 MW Phudung hydel power unit in West Kameng # * 24.0 MW (Mega Watt) 172.8 Energy Renewable energy (grid) Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 30-Oct-2019
820 Setting up of 24 MW Roura-II hydel power unit in Kinnaur district 24.0 MW (Mega Watt) 159.2 Energy Renewable energy (grid) Under Construction Directorate of Energy, Himachal Pradesh Himachal Pradesh 30-Oct-2019
821 Setting up of 24 MW Sichi hydel power unit # * 24.0 MW (Mega Watt) 175.2 Energy Renewable energy (grid) Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 30-Oct-2019
822 Setting up of 24.6 MW Wanger-Homte hydel power unit in Kinnaur district 24.6 MW (Mega Watt) 274.5 Energy Renewable energy (grid) Under Construction Directorate of Energy, Himachal Pradesh Himachal Pradesh 30-Oct-2019
823 Setting up of 240 MW Heo hydel power unit in West Siang # * 240.0 MW (Mega Watt) 1680 Energy Renewable energy (grid) Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 30-Oct-2019
824 Setting up of 25 MW Adum Panyor hydel power unit on Ranganadi River in Arunachal Pradesh # * 25.0 MW (Mega Watt) 175 Energy Renewable energy (grid) Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 30-Oct-2019
825 Setting up of 25 MW Lambadug hydel power unit in Kangra district 25.0 MW (Mega Watt) 149.81 Energy Renewable energy (grid) Under Construction Directorate of Energy, Himachal Pradesh Himachal Pradesh 30-Oct-2019
826 Setting up of 252 MW Dinchang hydel power unit near Bomdila in West Kameng district # * 252.0 MW (Mega Watt) 1980 Energy Renewable energy (grid) Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 30-Oct-2019
827 Setting up of 27.5 MW Tagurshit-II hydel power unit in West Siang # * 27.5 MW (Mega Watt) 192.5 Energy Renewable energy (grid) Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 30-Oct-2019
828 Setting up of 270 MW hydel power unit in Anjaw * 270.0 MW (Mega Watt) 1890 Energy Renewable energy (grid) Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 30-Oct-2019
829 Setting up of 2700 MW Lower Siang hydel power unit in East Siang # * 2700.0 MW (Mega Watt) 20000 Energy Renewable energy (grid) Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 30-Oct-2019
830 Setting up of 275 MW Emra-I hydel power unit in Arunachal Pradesh # * 275.0 MW (Mega Watt) 1925 Energy Renewable energy (grid) Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 30-Oct-2019
831 Setting up of 30 MW Ashupani hydel power unit in Arunachal Pradesh # * 30.0 MW (Mega Watt) 210 Energy Renewable energy (grid) Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 30-Oct-2019
832 Setting up of 3097 MW Etalin hydel power unit in Dibang Valley district # * 3097.0 MW (Mega Watt) 25.296.95 Energy Renewable energy (grid) Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 30-Oct-2019
833 Setting up of 360 MW Nalo hydel power unit in Upper Subansiri # * 360.0 MW (Mega Watt) 2520 Energy Renewable energy (grid) Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 30-Oct-2019
834 Setting up of 38 MW Meyong hydel power unit in Kameng basin # * 38.0 MW (Mega Watt) 266 Energy Renewable energy (grid) Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 30-Oct-2019
835 Setting up of 390 MW Emra-II hydel power unit in Arunachal Pradesh * 390.0 MW (Mega Watt) 2730 Energy Renewable energy (grid) Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 30-Oct-2019
836 Setting up of 40 MW Pakke Bung-I hydel power unit in Arunachal Pradesh # * 40.0 MW (Mega Watt) 280 Energy Renewable energy (grid) Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 30-Oct-2019
837 Setting up of 40 MW Rapum hydel power unit in West Siang # * 40.0 MW (Mega Watt) 280 Energy Renewable energy (grid) Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 30-Oct-2019
838 Setting up of 420 MW Amulin hydel power unit in Anini district # * 420.0 MW (Mega Watt) 2940 Energy Renewable energy (grid) Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 30-Oct-2019
839 Setting up of 45 MW Lower Pachuk-II hydel power unit in Kameng # * 45.0 MW (Mega Watt) 315 Energy Renewable energy (grid) Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 30-Oct-2019
840 Setting up of 45 MW Tirap hydel power unit in Changlang # * 45.0 MW (Mega Watt) 315 Energy Renewable energy (grid) Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 30-Oct-2019
841 Setting up of 46 MW Digin hydel power unit in West Kameng # * 46.0 MW (Mega Watt) 322 Energy Renewable energy (grid) Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 30-Oct-2019
842 Setting up of 46 MW Sepia hydel power unit in Arunachal Pradesh # * 46.0 MW (Mega Watt) 322 Energy Renewable energy (grid) Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 30-Oct-2019
843 Setting up of 48 MW Ithun-II hydel power unit in Lower Dibang Valley # * 48.0 MW (Mega Watt) 336 Energy Renewable energy (grid) Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 30-Oct-2019
844 Setting up of 48 MW Lower Marjingla hydel power unit in East Kameng # * 48.0 MW (Mega Watt) 336 Energy Renewable energy (grid) Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 30-Oct-2019
845 Setting up of 48 MW Papu Valley hydel power unit in East Kameng # * 48.0 MW (Mega Watt) 345.6 Energy Renewable energy (grid) Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 30-Oct-2019
846 Setting up of 5.4 MW Sarbari-II small hydel power unit in Kullu district 5.4 MW (Mega Watt) 46 Energy Renewable energy (grid) Operation and Maintenance Stage Directorate of Energy, Himachal Pradesh Himachal Pradesh 30-Oct-2019
847 Setting up of 50 MW Tsa Chu-ILower hydel power unit in Tawang # * 50.0 MW (Mega Watt) 350 Energy Electricity transmission Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 30-Oct-2019
848 Setting up of 500 MW Emini hydel power unit in Dibang Valley district # * 500.0 MW (Mega Watt) 3500 Energy Renewable energy (grid) Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 30-Oct-2019
849 Setting up of 55 MW Para hydel power unit in Kameng # * 55.0 MW (Mega Watt) 385 Energy Electricity transmission Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 30-Oct-2019
850 Setting up of 552 MW Dengser hydel power unit in Upper Subansiri # * 552.0 MW (Mega Watt) 3864 Energy Renewable energy (grid) Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 30-Oct-2019
851 Setting up of 56 MW Taiyong hydel power unit in West Siang # * 56.0 MW (Mega Watt) 392 Energy Renewable energy (grid) Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 30-Oct-2019
852 Setting up of 6 MW Baner hydel power unit in Kangra district 6.0 MW (Mega Watt) 54.59 Energy Renewable energy (grid) Operation and Maintenance Stage Directorate of Energy, Himachal Pradesh Himachal Pradesh 30-Oct-2019
853 Setting up of 60 MW Marjingla hydel power unit in East Kameng # * 60.0 MW (Mega Watt) 432 Energy Renewable energy (grid) Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 30-Oct-2019
854 Setting up of 60 MW Pachuk-II hydel power unit in Kameng # * 60.0 MW (Mega Watt) 420 Energy Renewable energy (grid) Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 30-Oct-2019
855 Setting up of 600 MW Kameng-II hydel power unit in West Kameng district # * 600.0 MW (Mega Watt) 4200 Energy Renewable energy (grid) Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 30-Oct-2019
856 Setting up of 63 MW Dardu hydel power unit in Papum Pare# * 60.0 MW (Mega Watt) 463 Energy Renewable energy (grid) Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 30-Oct-2019
857 Setting up of 66 MW Simang-II hydel power unit in East Siang # * 66.0 MW (Mega Watt) 475.2 Energy Renewable energy (grid) Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 30-Oct-2019
858 Setting up of 67 MW Simang-I hydel power unit in East Siang # * 67.0 MW (Mega Watt) 469 Energy Renewable energy (grid) Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 30-Oct-2019
859 Setting up of 68 MW Tidding-II hydel power unit in Arunachal Pradesh # * 68.0 MW (Mega Watt) 496.4 Energy Renewable energy (grid) Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 30-Oct-2019
860 Setting up of 680 MW Attunli hydel power unit in Dibang Valley district # * 680.0 MW (Mega Watt) 7158.84 Energy Renewable energy (grid) Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 30-Oct-2019
861 Setting up of 70 MW Badao hydel power unit in Kameng # * 70.0 MW (Mega Watt) 490 Energy Electricity transmission Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 30-Oct-2019
862 Setting up of 70 MW Budhil hydel power unit in Chamba district # 70.0 MW (Mega Watt) 418.8 Energy Renewable energy (grid) Operation and Maintenance Stage Directorate of Energy, Himachal Pradesh Himachal Pradesh 30-Oct-2019
863 Setting up of 700 MW Tato-II hydel power unit in West Siang district# * 700.0 MW (Mega Watt) 6000 Energy Renewable energy (grid) Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 30-Oct-2019
864 Setting up of 74 MW Tagurshit hydel power unit at Tado Gitu in West Siang # * 74.0 MW (Mega Watt) 518 Energy Renewable energy (grid) Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 30-Oct-2019
865 Setting up of 75 MW Chela hydel power unit in Arunachal Pradesh # * 75.0 MW (Mega Watt) 525 Energy Renewable energy (grid) Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 30-Oct-2019
866 Setting up of 780 MW Nyamjang Chhu hydel power unit in Tawang # * 780.0 MW (Mega Watt) 6852.28 Energy Renewable energy (grid) Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 30-Oct-2019
867 Setting up of 8 MW hydel power unit at Kurmi in Shimla district # 8.0 MW (Mega Watt) 68.49 Energy Renewable energy (grid) Operation and Maintenance Stage Directorate of Energy, Himachal Pradesh Himachal Pradesh 30-Oct-2019
868 Setting up of 8 MW Rima hydel power unit in Changlang # * 8.0 MW (Mega Watt) 57.6 Energy Renewable energy (grid) Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 30-Oct-2019
869 Setting up of 8.0 MW Upper Joiner (Stage II) hydel power unit in Chamba 8.0 MW (Mega Watt) 50.44 Energy Renewable energy (grid) Under Construction Directorate of Energy, Himachal Pradesh Himachal Pradesh 30-Oct-2019
870 Setting up of 80 MW Chomi hydel power unit in Arunachal Pradesh # * 80.0 MW (Mega Watt) 584 Energy Renewable energy (grid) Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 30-Oct-2019
871 Setting up of 80 MW Gimliang hydel power unit in Lohit # * 80.0 MW (Mega Watt) 870.39 Energy Renewable energy (grid) Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 30-Oct-2019
872 Setting up of 80 MW Kangtangshiri hydel power unit in West Siang # * 80.0 MW (Mega Watt) 245 Energy Renewable energy (grid) Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 30-Oct-2019
873 Setting up of 80 MW Panyor hydel power unit at Yazali in Lower Subansiri # * 80.0 MW (Mega Watt) 820 Energy Renewable energy (grid) Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 30-Oct-2019
874 Setting up of 800 MW Niare hydel power unit in upper reaches of Subansiri river, Arunachal Pradesh # * 800.0 MW (Mega Watt) 5600 Energy Renewable energy (grid) Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 30-Oct-2019
875 Setting up of 84 MW Ithun-I hydel power unit in Lower Dibang Valley # * 84.0 MW (Mega Watt) 588 Energy Renewable energy (grid) Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 30-Oct-2019
876 Setting up of 84 MW Pachuk I hydel power project in Kameng # * 84.0 MW (Mega Watt) 588 Energy Electricity transmission Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 30-Oct-2019
877 Setting up of 9 MW Beas Kund hydel power unit in Kullu district # 9.0 MW (Mega Watt) 75.84 Energy Renewable energy (grid) Operation and Maintenance Stage Directorate of Energy, Himachal Pradesh Himachal Pradesh 30-Oct-2019
878 Setting up of 9 MW Upper Ngorgum hydel power unit in Arunachal Pradesh # * 9.0 MW (Mega Watt) 63.9 Energy Renewable energy (grid) Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 30-Oct-2019
879 Setting up of 9.6 MW Jeori hydel power unit in Shimla district 9.6 MW (Mega Watt) 74.16 Energy Renewable energy (grid) Under Construction Directorate of Energy, Himachal Pradesh Himachal Pradesh 30-Oct-2019
880 Setting up of 9.9 MW Rajpur hydel power unit in Shimla district 9.9 MW (Mega Watt) 42.03 Energy Renewable energy (grid) Under Construction Directorate of Energy, Himachal Pradesh Himachal Pradesh 30-Oct-2019
881 Setting up of 90 MW Papu hydel power unit in Kameng # * 90.0 MW (Mega Watt) 620 Energy Electricity transmission Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 30-Oct-2019
882 Setting up of 92 MW Jidu hydel power unit in Upper Siang # * 92.0 MW (Mega Watt) 644 Energy Renewable energy (grid) Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 30-Oct-2019
883 Setting up of 93 MW Rho hydel power unit in Tawang # * 93.0 MW (Mega Watt) 1160.75 Energy Renewable energy (grid) Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 30-Oct-2019
884 Setting up of 96 MW Mago Chu hydel power unit in Tawang # * 96.0 MW (Mega Watt) 1048 Energy Renewable energy (grid) Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 30-Oct-2019
885 Setting up of 96 MW Nyukcharong Chu hydel power unit in Tawang # * 96.0 MW (Mega Watt) 995.9 Energy Renewable energy (grid) Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 30-Oct-2019
886 Setting up of 96 MW Pango hydel power unit in Upper Siang # * 96.0 MW (Mega Watt) 672 Energy Renewable energy (grid) Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 30-Oct-2019
887 Setting up of 96 MW Pema Selphu hydel power unit in West Siang # * 96.0 MW (Mega Watt) 672 Energy Renewable energy (grid) Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 30-Oct-2019
888 Setting up of 96 MW Sippi hydel power unit in Upper Siang # * 96.0 MW (Mega Watt) 672 Energy Renewable energy (grid) Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 30-Oct-2019
889 Setting up of 98 MW Tidding-I hydel power unit in Arunachal Pradesh # * 98.0 MW (Mega Watt) 686 Energy Renewable energy (grid) Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 30-Oct-2019
890 Setting up of Nafra 96 MW hydel power unit in West Kameng # * 96.0 MW (Mega Watt) 672 Energy Renewable energy (grid) Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 30-Oct-2019
891 Teesta III-Kishanganj Transmission Line # * 211.0 CKM (Circuit Kilo Meter) 1032 Energy Electricity transmission Under Construction Power Grid Corpn. of India Ltd. Multi State/ Centre 30-Oct-2019
892 Wardha Power Company (WPCL) - Coal based power plant 540.0 MW (Mega Watt) 2811 Energy Electricity generation (grid) Operation and Maintenance Stage Maharashtra Electricity Regulatory Commission Maharashtra 30-Oct-2019
893 Waste Based Power (Ranchi) Project * 11.0 MW (Mega Watt) 77 Energy Electricity generation (grid) Pre-construction Stage Ranchi Municipal Corporation Jharkhand 30-Oct-2019
894 "DCFOMT" of a Regional Municipal Solid Waste to Energy & Land fill facility at Patna in Bihar * 11.5 MW (Mega Watt) 15 Energy Renewable energy (grid) Under Construction Bihar Urban Infrastructure Development Corporation Limited Bihar 25-Oct-2019
895 Balighat Small Hydro Power Project * 5.5 MW (Mega Watt) 41.32 Energy Renewable energy (grid) Under Construction Department of Energy, Uttarakhand Uttarakhand 25-Oct-2019
896 Burthing Small Hydro Power Project * 5.0 MW (Mega Watt) 34.99 Energy Renewable energy (grid) Under Construction Department of Energy, Uttarakhand Uttarakhand 25-Oct-2019
897 Desang Small Hydro Power (Dillighat) Project # * 9.0 MW (Mega Watt) 73.8 Energy Renewable energy (grid) Pre-construction Stage Assam Power Project Development Company Limited Assam 25-Oct-2019
898 Development of 20 MW Power Station at Port Blair * 20.0 MW (Mega Watt) 0 Energy Renewable energy (grid) Not Available Andaman and Nicobar Administration Andaman & Nicobar Islands (UT) 25-Oct-2019
899 Establishment of 20 MW DG power plant at Bambooflat, South Andaman District # 20.0 MW (Mega Watt) 74.96 Energy Electricity generation (grid) Completed Andaman and Nicobar Administration Andaman & Nicobar Islands (UT) 25-Oct-2019
900 Establishment of 5 MWp SPV power plant at Garacharama, South Andaman 5.0 MW (Mega Watt) 60 Energy Renewable energy (grid) Operation and Maintenance Stage Andaman and Nicobar Administration Andaman & Nicobar Islands (UT) 25-Oct-2019
901 Hinduja National Power Corp Ltd (HNPCL) - Thermal Power plant at Visakhapatnam 1040.0 MW (Mega Watt) 7987 Energy Electricity generation (grid) Operation and Maintenance Stage Andhra Pradesh Electricity Regulatory Commission Andhra Pradesh 25-Oct-2019
902 Implementation of 11.5 MW municipal solid waste based power unit at Giddenahalli in Bengaluru district * 11.5 MW (Mega Watt) 233.06 Energy Renewable energy (grid) Under Construction Bruhat Bengaluru Mahanagara Palike Karnataka 25-Oct-2019
903 Khutani Small Hydro Power Project * 21.0 MW (Mega Watt) 189.53 Energy Renewable energy (grid) Under Construction Department of Energy, Uttarakhand Uttarakhand 25-Oct-2019
904 Phulibagar Small Hydro Power Project * 5.0 MW (Mega Watt) 29.02 Energy Renewable energy (grid) Under Construction Department of Energy, Uttarakhand Uttarakhand 25-Oct-2019
905 Setting up of 18 MW Dengzi hydel power unit at Kalaktang # * 18.0 MW (Mega Watt) 133.2 Energy Renewable energy (grid) Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 25-Oct-2019
906 Setting up of 2000 MW Upper Subansiri hydel power unit at Menga village * 2000.0 MW (Mega Watt) 16100 Energy Renewable energy (grid) Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 25-Oct-2019
907 Setting up of 31 MW Rebby hydel power unit in Kameng # * 31.0 MW (Mega Watt) 217 Energy Electricity transmission Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 25-Oct-2019
908 Setting up of 36 MW Tarang Warang hydel power unit in Kameng # * 36.0 MW (Mega Watt) 252 Energy Electricity transmission Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 25-Oct-2019
909 Setting up of 400 MW Mihumdon hydel power unit in Arunachal Pradesh * 400.0 MW (Mega Watt) 2800 Energy Renewable energy (grid) Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 25-Oct-2019
910 Setting up of 41 MW Lachung hydel power unit in Kameng # * 41.0 MW (Mega Watt) 287 Energy Electricity transmission Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 25-Oct-2019
911 Setting up of 45 MW Phanchung hydel power unit in Kameng # * 45.0 MW (Mega Watt) 415 Energy Electricity transmission Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 25-Oct-2019
912 Setting up of 52 MW Par hydel power unit in Papum Pare # * 65.0 MW (Mega Watt) 461 Energy Renewable energy (grid) Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 25-Oct-2019
913 Setting up of 60 MW New Melling hydel power unit in Tawang # * 60.0 MW (Mega Watt) 1086 Energy Renewable energy (grid) Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 25-Oct-2019
914 Setting up of 63 MW Turu hydel power unit in Papum Pare# * 90.0 MW (Mega Watt) 630 Energy Renewable energy (grid) Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 25-Oct-2019
915 Setting up of 66 MW Khuitam hydel power unit in West Kameng # * 66.0 MW (Mega Watt) 462 Energy Renewable energy (grid) Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 25-Oct-2019
916 Setting up of 75 MW Lower Yamne-II hydel power unit in Upper Siang # * 75.0 MW (Mega Watt) 609 Energy Renewable energy (grid) Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 25-Oct-2019
917 Setting up of 80 MW Rapum hydel power unit in West Siang # * 80.0 MW (Mega Watt) 560 Energy Renewable energy (grid) Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 25-Oct-2019
918 Setting up of 90 MW Jameri hydel power unit in Kameng # * 90.0 MW (Mega Watt) 355 Energy Renewable energy (grid) Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 25-Oct-2019
919 Setting up of 90 MW Tsa Chu-II hydel power unit in Tawang * 90.0 MW (Mega Watt) 630 Energy Renewable energy (grid) Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 25-Oct-2019
920 Setting up of 96 MW Barpu hydel power unit in Arunachal Pradesh# * 96.0 MW (Mega Watt) 490 Energy Renewable energy (grid) Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 25-Oct-2019
921 Setting up of 96 MW Lower Yamne-II hydel power unit in Upper Siang # * 96.0 MW (Mega Watt) 681.6 Energy Renewable energy (grid) Pre-construction Stage Department of Hydro Power Development, Arunachal Pradesh Arunachal Pradesh 25-Oct-2019
922 Electricity Distribution Agra City Not Available 400 Energy Electricity Distribution Operation and Maintenance Stage Torrent Power Limited Uttar Pradesh 24-Oct-2019
923 Hydro Electric Power (Hetavane) Project 0.35 MW (Mega Watt) 5.16 Energy Renewable energy (grid) Pre-construction Stage Water Resources Department, Maharashtra Maharashtra 22-Oct-2019
924 Bangalore International Airport (Expanded Terminal) 17.2 MPPA (Million Passenger Per Annum) 1547 Transport Airports Operation and Maintenance Stage Airports Authority of India (AAI) Karnataka 03-Oct-2019
925 Bangalore International Airport Project 11.5 MPPA (Million Passenger Per Annum) 2353 Transport Airports Operation and Maintenance Stage Airports Authority of India (AAI) Karnataka 03-Oct-2019
926 Cochin International Airport Not Available 303 Transport Airports Operation and Maintenance Stage Kochi International Airport Society (KIAS) Kerala 03-Oct-2019
927 Development of Common user Coal Terminal 10.0 MMTPA (million metric tonnes per annum) 351.08 Transport Ports (excluding captive) Operation and Maintenance Stage Kamarajar Port Limited Tamil Nadu 03-Oct-2019
928 International Airport (Mopa) Project 13.1 MPPA (Million Passenger Per Annum) 3100 Transport Airports Under Construction Government of Goa Goa 03-Oct-2019
929 2nd Container Terminal (NSICT) JNPT 15.0 MTPA (Metric Tonne Per Annum) 750 Transport Ports (excluding captive) Operation and Maintenance Stage Jawaharlal Nehru Port Trust Maharashtra 01-Oct-2019
930 3rd Container Terminal (GTIPL) JNPT 22.5 MTPA (Metric Tonne Per Annum) 1078 Transport Ports (excluding captive) Operation and Maintenance Stage Jawaharlal Nehru Port Trust Maharashtra 01-Oct-2019
931 Aircraft Maintenance Hangar (Kochi) Not Available 42 Transport Airports Operation and Maintenance Stage Cochin International Airport Limited Kerala 01-Oct-2019
932 Airport Metro Express Line - New Delhi Railway Station to IGI Airport to Sector 21, Dwarka, New Delhi 23.0 KM (Kilometer) 5700 Transport Urban public transport (except rolling stock) Operation and Maintenance Stage Delhi Metro Rail Corporation Limited, Delhi (UT) 01-Oct-2019
933 Bus cum Truck Terminal at Alisha PS & District Burdwan Not Available 65 Transport Urban public transport (except rolling stock) Operation and Maintenance Stage Burdwan Development Authority West Bengal 01-Oct-2019
934 Bus cum Truck Terminal at Nababhat Not Available 35 Transport Urban public transport (except rolling stock) Operation and Maintenance Stage Burdwan Development Authority West Bengal 01-Oct-2019
935 Bus Rapid Transport System (Ahmedabad) Phase IA 12.0 KM (Kilometer) 87.6 Transport Urban public transport (except rolling stock) Operation and Maintenance Stage Gujarat Infrastructure Development Board Gujarat 01-Oct-2019
936 Bus Terminal (Alambagh) Project 50.0 Numbers 201 Transport Urban public transport (except rolling stock) Operation and Maintenance Stage Uttar Pradesh State Road Transport Corporation Uttar Pradesh 01-Oct-2019
937 Chhara Port Project - Phase I 5.5 MMTPA (million metric tonnes per annum) 1200 Transport Ports (excluding captive) Under Construction Gujarat Maritime Board (GMB) Gujarat 01-Oct-2019
938 Construction and Operation of Two Multipurpose Bulk Cargo Berths (5A & 6A) at the Port of Mormugao 5.0 MMTPA (million metric tonnes per annum) 250 Transport Ports (excluding captive) Operation and Maintenance Stage Mormugao Port Trust Goa 01-Oct-2019
939 Construction of bus terminal on 2.8 acres of land in Rajkot 2.80 Acres 128.01 Transport Urban public transport (except rolling stock) Pre-construction Stage Gujarat State Road Transport Corporation Gujarat 01-Oct-2019
940 Construction of bus terminal on 3.1 acres of land in Bhuj 3.10 Acres 28.85 Transport Urban public transport (except rolling stock) Pre-construction Stage Gujarat State Road Transport Corporation Gujarat 01-Oct-2019
941 Construction of bus terminal on 4.2 acres of land in Amreli 4.20 Acres 40.43 Transport Urban public transport (except rolling stock) Pre-construction Stage Gujarat State Road Transport Corporation Gujarat 01-Oct-2019
942 Construction of bus terminal on 5 acres of land at Nadiad 5.0 Acres 50.71 Transport Urban public transport (except rolling stock) Pre-construction Stage Gujarat State Road Transport Corporation Gujarat 01-Oct-2019
943 Construction of bus terminal on 5.3 acres of land in Bharuch 5.30 Acres 74.49 Transport Urban public transport (except rolling stock) Pre-construction Stage Gujarat State Road Transport Corporation Gujarat 01-Oct-2019
944 Construction of bus terminal on 7.3 acres of land at Palanpur 7.30 Acres 75.8 Transport Urban public transport (except rolling stock) Pre-construction Stage Gujarat State Road Transport Corporation Gujarat 01-Oct-2019
945 Construction of bus terminal on 7.3 acres of land in Navsari 7.30 Acres 64.64 Transport Urban public transport (except rolling stock) Pre-construction Stage Gujarat State Road Transport Corporation Gujarat 01-Oct-2019
946 Construction of bus terminal on 7.4 acres of land at Modasa 7.40 Acres 60.47 Transport Urban public transport (except rolling stock) Pre-construction Stage Gujarat State Road Transport Corporation Gujarat 01-Oct-2019
947 Construction of bus terminal on 7.7 acres of land in Patan 7.70 Acres 52.5 Transport Urban public transport (except rolling stock) Pre-construction Stage Gujarat State Road Transport Corporation Gujarat 01-Oct-2019
948 Construction of central bus terminal on 14.9 acres at Geeta Mandir in Ahmedabad 14.90 Acres 186.67 Transport Urban public transport (except rolling stock) Operation and Maintenance Stage Gujarat State Road Transport Corporation Gujarat 01-Oct-2019
949 Construction of central bus terminal on 21.6 acres at Modhera cross road in Mehsana 21.60 Acres 57.16 Transport Urban public transport (except rolling stock) Operation and Maintenance Stage Gujarat State Road Transport Corporation Gujarat 01-Oct-2019
950 Construction of central bus terminal on 5.4 acres at Subhash bridge in Ahmedabad 5.40 Acres 77.91 Transport Urban public transport (except rolling stock) Operation and Maintenance Stage Gujarat State Road Transport Corporation Gujarat 01-Oct-2019
951 Construction of Deep draught iron ore berth on BOT basis by Paradip Port Trust 10.0 MMTPA (million metric tonnes per annum) 740 Transport Ports (excluding captive) Under Construction Ministry of Shipping Odisha 01-Oct-2019
952 DCDFO&M of eight Lane access controlled expressway under Phase II A Programme, in Telangana 11.7 KM (Kilometer) 502 Transport Urban public transport (except rolling stock) Operation and Maintenance Stage Hyderabad Metropolitan Development Authority Telangana 01-Oct-2019
953 Development of a Coal Terminal at Port of Mormugao, Goa on Design, Build, Finance, Operate and Transfer (DBFOT) Basis 4.61 MMTPA (million metric tonnes per annum) 404.97 Transport Ports (excluding captive) Operation and Maintenance Stage Mormugao Port Trust Goa 01-Oct-2019
954 Development of a Container Terminal at Tuna Tekra in Kandla Port Kutch region in the State of Gujarat on DBFOT basis 14.11 MTPA (Metric Tonne Per Annum) 5991.71 Transport Ports (excluding captive) Pre-construction Stage Ministry of Shipping Gujarat 01-Oct-2019
955 Development of a multipurpose Berth and a Mechanised Berth at Haldia Dock -II (South), Haldia Dock Complex, Kolkata Port Trust Not Available 886.1 Transport Ports (excluding captive) Operation and Maintenance Stage Ministry of Shipping West Bengal 01-Oct-2019
956 Development of a new terminal termed as the extension of the existing container terminal, Outer Harbour at Visakhapatnam Port Not Available 635.11 Transport Ports (excluding captive) Operation and Maintenance Stage Ministry of Shipping Andhra Pradesh 01-Oct-2019
957 Development of an integrated bus station-cum-commercial complex at KSRTC Bus Station, Puttur in Dakshina Kannada district 2.4 Acres 33 Transport Urban public transport (except rolling stock) Operation and Maintenance Stage Karnataka State Road Transport Corporation (KSRTC) Karnataka 01-Oct-2019
958 Development of Container Terminal at Ennore Port, Tiruvallur District in the State of Tamil Nadu 16.8 MTPA (Metric Tonne Per Annum) 1436 Transport Ports (excluding captive) Operation and Maintenance Stage Kamarajar Port Limited Tamil Nadu 01-Oct-2019
959 Development of Dry Bulk Terminal at Tekra near Tuna on BOT basis 14.0 MMTPA (million metric tonnes per annum) 1410 Transport Ports (excluding captive) Operation and Maintenance Stage Ministry of Shipping Gujarat 01-Oct-2019
960 Development of Eighth Berth as Container Terminal on Build Operate & Transfer (BOT) basis at Tuticorin Port 7.20 MMTPA (million metric tonnes per annum) 312.23 Transport Ports (excluding captive) Operation and Maintenance Stage V.O. Chidambaranar Port Trust Tamil Nadu 01-Oct-2019
961 Development of EQ-10 berth in the northern arm of inner harbour of Visakhapatnam port 1.8 MTPA (Metric Tonne Per Annum) 55.38 Transport Ports (excluding captive) Operation and Maintenance Stage Visakhapatnam Port Trust Andhra Pradesh 01-Oct-2019
962 Development of Fourth Container Terminal at Jawahar Lal Nehru Port Trust 60.0 MMTPA (million metric tonnes per annum) 7915 Transport Ports (excluding captive) Operation and Maintenance Stage Ministry of Shipping Maharashtra 01-Oct-2019
963 Development of Modern Bus Terminal at Amritsar 90000.0 Passengers 12.75 Transport Urban public transport (except rolling stock) Operation and Maintenance Stage Director State Transport / Government of Punjab Punjab 01-Oct-2019
964 Development of Modern Bus Terminal at Jalandhar 100000.0 Passengers 12 Transport Urban public transport (except rolling stock) Operation and Maintenance Stage Director State Transport / Government of Punjab Punjab 01-Oct-2019
965 Development of multilevel car parking on 0.6 acres of land at Nungambakkam Not Available 43 Transport Urban public transport (except rolling stock) Operation and Maintenance Stage Greater Chennai Corporation Tamil Nadu 01-Oct-2019
966 Development of Multipurpose Berth to handle clean cargo including containers on BOT basis at Paradip Port 5.0 MMTPA (million metric tonnes per annum) 431 Transport Ports (excluding captive) Operation and Maintenance Stage Paradip Port Trust Odisha 01-Oct-2019
967 Development of North Cargo Berth II for handling bulk cargo at Tuticorin Port on DBFOT basis 7.0 MMTPA (million metric tonnes per annum) 335 Transport Ports (excluding captive) Operation and Maintenance Stage V.O. Chidambaranar Port Trust Tamil Nadu 01-Oct-2019
968 Development of North Cargo Berth-IV to handle bulk cargo, Thermal Coal and Copper Concentrate at V.O Chidambaranar Port on DBFOT Not Available 355 Transport Ports (excluding captive) Under Construction Ministry of Shipping Tamil Nadu 01-Oct-2019
969 Development of Standalone container handling facility with a quay length of 300m towards North at Jahawar Lal Nehru Port Trust 10.0 MTPA (Metric Tonne Per Annum) 600 Transport Ports (excluding captive) Operation and Maintenance Stage Jawaharlal Nehru Port Trust Maharashtra 01-Oct-2019
970 Development of WQ-6 berth in the northern arm of inner harbour of Vishakhapatnam Port for handling dry bulk cargo on DBFOT basis 2.08 MMTPA (million metric tonnes per annum) 139.9 Transport Ports (excluding captive) Operation and Maintenance Stage Visakhapatnam Port Trust Andhra Pradesh 01-Oct-2019
971 Dholera Port Not Available 551 Transport Ports (excluding captive) Under Construction Gujarat Maritime Board (GMB) Gujarat 01-Oct-2019
972 Establishment of Container Terminal and O & M of handling equipment at multipurpose berth, Visakhapatnam Port Not Available 108 Transport Ports (excluding captive) Operation and Maintenance Stage Visakhapatnam Port Trust Andhra Pradesh 01-Oct-2019
973 Hazira LNG Terminal 5.0 MMTPA (million metric tonnes per annum) 1150 Transport Ports (excluding captive) Operation and Maintenance Stage Gujarat Maritime Board (GMB) Gujarat 01-Oct-2019
974 Krishnapatnam Port Project - Phase I 13.5 MTPA (Metric Tonne Per Annum) 1200 Transport Ports (excluding captive) Operation and Maintenance Stage Department of Ports, Andhra Pradesh Andhra Pradesh 01-Oct-2019
975 Mechanization of EQ 1,2,3 Berths at Paradip Port on BOT basis under PPP Mode Not Available 1437.76 Transport Ports (excluding captive) Under Construction Ministry of Shipping Odisha 01-Oct-2019
976 Multi Cargo Terminal (Tamil Nadu) Project 2.0 MMTPA (million metric tonnes per annum) 151 Transport Ports (excluding captive) Operation and Maintenance Stage Kamarajar Port Limited Tamil Nadu 01-Oct-2019
977 Multi Level Parking (Ashok Marg) Project 400.0 PCU (Passenger Car Unit) 30 Transport Urban public transport (except rolling stock) Under Construction Jaipur Municipal Corporation Rajasthan 01-Oct-2019
978 Multi purpose berth 4A at HDC Kolkata Port Trust 3.1 MTPA (Metric Tonne Per Annum) 150 Transport Ports (excluding captive) Operation and Maintenance Stage Kolkata Port Trust West Bengal 01-Oct-2019
979 Multilevel Parking at Sector 17 Not Available 60 Transport Urban public transport (except rolling stock) Operation and Maintenance Stage Chandigarh Municipal Corporation Haryana 01-Oct-2019
980 Multipurpose Berth No. 12 at HDC KoPT 1.12 MTPA (Metric Tonne Per Annum) 37 Transport Ports (excluding captive) Operation and Maintenance Stage Kolkata Port Trust West Bengal 01-Oct-2019
981 Multipurpose Cargo Port (Dighi) Project 7.5 MTPA (Metric Tonne Per Annum) 13556.11 Transport Ports (excluding captive) Operation and Maintenance Stage Maharashtra Maritime Board (MMB) Maharashtra 01-Oct-2019
982 Multipurpose Cargo Port (Jaigad) Project 18.0 MTPA (Metric Tonne Per Annum) 3000 Transport Ports (excluding captive) Operation and Maintenance Stage Maharashtra Maritime Board (MMB) Maharashtra 01-Oct-2019
983 Multipurpose Cargo Port (Vijaydurg) Project 75.0 MTPA (Metric Tonne Per Annum) 2275 Transport Ports (excluding captive) Operation and Maintenance Stage Maharashtra Maritime Board (MMB) Maharashtra 01-Oct-2019
984 O & M of Rajiv Gandhi Container Terminal &amp; Development, Operation of International Container Terminal 4.0 MTEU 2118 Transport Ports (excluding captive) Operation and Maintenance Stage Cochin Port Trust Kerala 01-Oct-2019
985 Pipavav Greenfield port - phase - I 12.6 MMTPA (million metric tonnes per annum) 731 Transport Ports (excluding captive) Operation and Maintenance Stage Gujarat Maritime Board (GMB) Gujarat 01-Oct-2019
986 Second Container Terminal (Chennai) Project 29.5 MTPA (Metric Tonne Per Annum) 783.32 Transport Ports (excluding captive) Operation and Maintenance Stage Chennai Port Trust Tamil Nadu 01-Oct-2019
987 Surendranagar-Pipapav Rail Project 271.0 KM (Kilometer) 373 Transport Railway track, tunnel, viaducts, bridges Operation and Maintenance Stage Ministry of Railways Gujarat 01-Oct-2019
988 Upgradation of existing facilities of OB-1, OB-2 at Outer Harbour and WQ-1 Berth at Inner Harbour of Visakhapatnam Port 15.0 MTPA (Metric Tonne Per Annum) 845.41 Transport Ports (excluding captive) Operation and Maintenance Stage Ministry of Shipping Andhra Pradesh 01-Oct-2019
989 Upgradation of Mechanical handling Infrastructure at V.O. Chidambaranar Port Trust (Berths I to VI & IX) 8.72 MMTPA (million metric tonnes per annum) 50.99 Transport Ports (excluding captive) Operation and Maintenance Stage V.O. Chidambaranar Port Trust Tamil Nadu 01-Oct-2019
990 Upgradation Operation and Maintenance of Ludhiana Bus Terminal 70000.0 Passengers 13.47 Transport Urban public transport (except rolling stock) Operation and Maintenance Stage Director State Transport / Government of Punjab Punjab 01-Oct-2019
991 Four Laning of Panikoili-Rimuli Section of NH 215 under NHDP Phase III, length 163 km 106.0 KM (Kilometer) 1648.92 Transport Roads and bridges Under Construction Ministry of Road Transport and Highways Odisha 19-Sep-2019
992 Jamb Wind Power Project, Satara district 28.0 MW (Mega Watt) 165.9 Energy Renewable energy (grid) Operation and Maintenance Stage Not Available Maharashtra 19-Sep-2019
993 4 laning of Chenani-Nashri section of NH 1A including 9 km long tunnel with parallel escape tunnel on BOT (Annuity) basis 41.0 KM (Kilometer) 2108 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Jammu & Kashmir 17-Sep-2019
994 4 laning of Qazigund-Banihal Section of NH 1A from 189.35-204.7km including 2 tunnels of 0.69 & 8.45 km length in J&amp;K 15.2 KM (Kilometer) 2414 Transport Roads and bridges Under Construction National Highways Authority of India (NHAI) Jammu & Kashmir 17-Sep-2019
995 6/4 Laning of Delhi-Haryana Border to Rohtak Section of NH-10 from 29.7-87 km with construction of Bahadurgarh and Rohtak Bypass 63.4 KM (Kilometer) 486 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Haryana 17-Sep-2019
996 Development and Operation of Bikaner to Suratgarh section on NH 11 from km 553.869 to km 173.000 on NH 15 172.4 KM (Kilometer) 501.08 Transport Roads and bridges Operation and Maintenance Stage Public Works Department, Rajasthan Rajasthan 17-Sep-2019
997 Development of Four lane of Sidhi to Singrauli section (km 83/4 to km 195/8) of NH 75E on DBFOT (Toll) basis 102.6 KM (Kilometer) 954.43 Transport Roads and bridges Under Construction Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 17-Sep-2019
998 Four laning of Baharampur-Farakka section of NH 34 from km 193 to km 295.700 inWest Bengal on DBFOT basis under NHDP III 101.0 KM (Kilometer) 1006.53 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) West Bengal 17-Sep-2019
999 Four laning of Cuddapah-Kurnool section (Km 167.750 to km 356.030) of NH 18 Under NHDP Phase III on BOT Basis 188.7 KM (Kilometer) 1567.31 Transport Roads and bridges Under Construction National Highways Authority of India (NHAI) Andhra Pradesh 17-Sep-2019
1000 Four laning of Nagpur-Saoner-Betul, Section of NH-69 Maharashtra and Madhya Pradesh on DBFOT (Annuity) basis 276.3 KM (Kilometer) 3515 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Multi State/ Centre 17-Sep-2019
1001 Four laning of YSR-Kurnool section in length of 188.3 km on NH-18 under NHDP-III 188.3 KM (Kilometer) 1585 Transport Roads and bridges Under Construction National Highways Authority of India (NHAI) Andhra Pradesh 17-Sep-2019
1002 Four/Six laning of Moradabad-Bareilly section of NH 24 from km 1+C28348 to km 262 inUttar Pradesh on DBFOT basis under NHDP III 114.0 KM (Kilometer) 1984 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Uttar Pradesh 17-Sep-2019
1003 Rehabilitation strengthening and 4 laning of Jammu-Udhampur sec of NH 1A from 15-67km on BOT basis on DBFO pattern 52.0 KM (Kilometer) 1939 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Jammu & Kashmir 17-Sep-2019
1004 Six laning of Pune-Satara section of NH 4 from km 725 to km 865.35 in Maharashtra on BOT (Toll) basis on DBFO pattern 140.3 KM (Kilometer) 1948.77 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Maharashtra 17-Sep-2019
1005 Construction of Four-lane Bhopal By-pass in Madhya Pradesh 52.0 KM (Kilometer) 305 Transport Roads and bridges Operation and Maintenance Stage Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 16-Sep-2019
1006 Four laning of Bangalore Maddur State Highway SH-17 in length of 62.5 km 62.5 KM (Kilometer) 188 Transport Roads and bridges Operation and Maintenance Stage Karnataka Road Development Corporation Limited (KRDCL) Karnataka 16-Sep-2019
1007 Four Laning of Nelamangala Junction on NH-4 with NH-48 to Devihalli under NHDP phase III A on BOT basis 80.0 KM (Kilometer) 742.07 Transport Roads and bridges Operation and Maintenance Stage Ministry of Road Transport and Highways Karnataka 16-Sep-2019
1008 Four laning of Pune-Sholapur section of NH 9 under NHDP Phase III, length 110.05 km� Package II 110.0 KM (Kilometer) 1110 Transport Roads and bridges Operation and Maintenance Stage Ministry of Road Transport and Highways Maharashtra 16-Sep-2019
1009 Road Upgradation (Salem-Karur) (NS-2/TN-3) Project 33.4 KM (Kilometer) 205.6 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Tamil Nadu 16-Sep-2019
1010 The Project of LNG Port & Terminal Facility in the Puthuvypeen sea at Cochin Port 5.0 MMTPA (million metric tonnes per annum) 4182 Transport Ports (excluding captive) Operation and Maintenance Stage Cochin Port Trust Kerala 16-Sep-2019
1011 100 MLD Sea Water Desalination Plant-Reverse Osmosis 237.0 MLD (Millons Liter per day) 550 Water Sanitation Water treatment plants Operation and Maintenance Stage Chennai Metropolitan Water Supply and Sewerage Board (CMWSSB) Tamil Nadu 13-Sep-2019
1012 Brackish Water Desalination Plant 20.0 MLD (Millons Liter per day) 300 Water Sanitation Water treatment plants Operation and Maintenance Stage Rajasthan State Mines and Minerals Limited Rajasthan 13-Sep-2019
1013 Bulk Water Supply Project for IIT Bhubaneshwar, NISAR, INFO City and adjoining areas, Bhubaneshwar 70.0 MLD (Millons Liter per day) 187.71 Water Sanitation Water supply pipeline Under Construction Public Health Engineering Organisation, Odisha Odisha 13-Sep-2019
1014 Cold Storage Project (Sikar) 2000.0 MT (Metric Tonne ) 17.3 Social and Commercial Infrastructure Cold Chain Operation and Maintenance Stage Rajasthan State Agriculture Marketing Board Rajasthan 13-Sep-2019
1015 Construction of multi chamber cold storage having capacity 4000 MT at Bhawani mandi 4000.0 MT (Metric Tonne ) 7.37 Social and Commercial Infrastructure Cold Chain Operation and Maintenance Stage Rajasthan State Agriculture Marketing Board Rajasthan 13-Sep-2019
1016 Door to Dump waste disposal Central zone, Ahmedabad Not Available 30 Water Sanitation Solid waste management Operation and Maintenance Stage Ahmedabad Municipal Corporation Gujarat 13-Sep-2019
1017 Door to Dump waste disposal North zone, Ahmedabad Not Available 34 Water Sanitation Solid waste management Operation and Maintenance Stage Ahmedabad Municipal Corporation Gujarat 13-Sep-2019
1018 High-Tech Amusement Park (Surat) Project 15.0 Acres 228.77 Social and Commercial Infrastructure Tourism Operation and Maintenance Stage Surat Municipal Corporation Gujarat 13-Sep-2019
1019 Implementation of 8.0 MLD water supply and sewerage scheme at Salt Lake 8.0 MLD (Millons Liter per day) 72 Water Sanitation Sewage collection, treatment and disposal system Operation and Maintenance Stage Kolkata Metropolitan Development Authority West Bengal 13-Sep-2019
1020 Setting up of 50,000 MT modern food silo complex at Bhopal 50000.0 MT (Metric Tonne ) 30.63 Social and Commercial Infrastructure Post-harvest storage infrastructure for agriculture and horticulture produce including cold storage Operation and Maintenance Stage Madhya Pradesh Warehousing and Logistics Corporation (MPWLC) Madhya Pradesh 13-Sep-2019
1021 Setting up of 50,000 MT modern food silo complex at Dewas District Village Durgapura 50000.0 MT (Metric Tonne ) 29.43 Social and Commercial Infrastructure Post-harvest storage infrastructure for agriculture and horticulture produce including cold storage Operation and Maintenance Stage Madhya Pradesh Warehousing and Logistics Corporation (MPWLC) Madhya Pradesh 13-Sep-2019
1022 Setting up of 50,000 MT modern food silo complex at Harda District Village Bhadawad 50000.0 MT (Metric Tonne ) 28.97 Social and Commercial Infrastructure Post-harvest storage infrastructure for agriculture and horticulture produce including cold storage Operation and Maintenance Stage Madhya Pradesh Warehousing and Logistics Corporation (MPWLC) Madhya Pradesh 13-Sep-2019
1023 Setting up of 50,000 MT modern food silo complex at Hoshangabad District Village Junheta Bankhedi 50000.0 MT (Metric Tonne ) 28.82 Social and Commercial Infrastructure Post-harvest storage infrastructure for agriculture and horticulture produce including cold storage Operation and Maintenance Stage Madhya Pradesh Warehousing and Logistics Corporation (MPWLC) Madhya Pradesh 13-Sep-2019
1024 Setting up of 50,000 MT modern food silo complex at Indore 50000.0 MT (Metric Tonne ) 30.64 Social and Commercial Infrastructure Post-harvest storage infrastructure for agriculture and horticulture produce including cold storage Operation and Maintenance Stage Madhya Pradesh Warehousing and Logistics Corporation (MPWLC) Madhya Pradesh 13-Sep-2019
1025 Setting up of 50,000 MT modern food silo complex at Satna District Village Mohari 50000.0 MT (Metric Tonne ) 28.95 Social and Commercial Infrastructure Post-harvest storage infrastructure for agriculture and horticulture produce including cold storage Operation and Maintenance Stage Madhya Pradesh Warehousing and Logistics Corporation (MPWLC) Madhya Pradesh 13-Sep-2019
1026 Setting up of 50,000 MT modern food silo complex at Sehore District Village Murli 50000.0 MT (Metric Tonne ) 30.55 Social and Commercial Infrastructure Post-harvest storage infrastructure for agriculture and horticulture produce including cold storage Operation and Maintenance Stage Madhya Pradesh Warehousing and Logistics Corporation (MPWLC) Madhya Pradesh 13-Sep-2019
1027 Setting up of 50,000 MT modern food silo complex at Ujjain District Village Manpur 50000.0 MT (Metric Tonne ) 29.6 Social and Commercial Infrastructure Post-harvest storage infrastructure for agriculture and horticulture produce including cold storage Operation and Maintenance Stage Madhya Pradesh Warehousing and Logistics Corporation (MPWLC) Madhya Pradesh 13-Sep-2019
1028 Setting up of 50,000 MT modern food silo complex at Vidisha District Village Patheri Haveli 50000.0 MT (Metric Tonne ) 30.96 Social and Commercial Infrastructure Post-harvest storage infrastructure for agriculture and horticulture produce including cold storage Operation and Maintenance Stage Madhya Pradesh Warehousing and Logistics Corporation (MPWLC) Madhya Pradesh 13-Sep-2019
1029 Shivpuri Water Supply Project 60.0 MLD (Millons Liter per day) 80.71 Water Sanitation Water supply pipeline Operation and Maintenance Stage Nagar Palika Parishad Shivpuri Madhya Pradesh 13-Sep-2019
1030 Visakhapatnam Industrial Water Supply Project 388.0 MLD (Millons Liter per day) 453 Water Sanitation Water treatment plants Operation and Maintenance Stage Andhra Pradesh Industrial Infrastructure Corporation Limited (APIIC) Andhra Pradesh 13-Sep-2019
1031 Water Supply Improvement (Mehrauli) Project Not Available 201 Water Sanitation Water supply pipeline Operation and Maintenance Stage Delhi Jal Board Delhi (UT) 13-Sep-2019
1032 Water Supply Scheme ( Naba Diganta Industrial Township) Not Available 68.01 Water Sanitation Water supply pipeline Operation and Maintenance Stage Kolkata Metropolitan Development Authority West Bengal 13-Sep-2019
1033 Water Supply Scheme (Khandwa) - Augmentation Not Available 115.32 Water Sanitation Water supply pipeline Operation and Maintenance Stage Khandwa Municipal Corporation Madhya Pradesh 13-Sep-2019
1034 Kantaphod - Nachabhor 39.22 KM (Kilometer) 196.47 Transport Roads and bridges Operation and Maintenance Stage Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 30-Aug-2019
1035 Dedicated Container Terminal at Pipavav Port 1000.0 MMTPA (million metric tonnes per annum) 2000 Transport Ports (excluding captive) Operation and Maintenance Stage Gujarat Maritime Board (GMB) Gujarat 21-Aug-2019
1036 Laying of ropeway at Jakhu in Shimla district 600.0 Passengers 40 Social and Commercial Infrastructure Tourism Operation and Maintenance Stage Department of Tourism and Civil Aviation, Himachal Pradesh Himachal Pradesh 21-Aug-2019
1037 Madivala Commercial Plaza. 6.88 Acres 30 Social and Commercial Infrastructure Tourism Operation and Maintenance Stage Bruhat Bangalore Mahanagar Palike Karnataka 21-Aug-2019
1038 Solid Waste Management (Rajkot) Not Available 8.67 Water Sanitation Solid waste management Operation and Maintenance Stage Rajkot Municipal Corporation Gujarat 21-Aug-2019
1039 4-laning of Muzaffarnagar-Saharanpur Road (SH-59) from Km.0.000 to Km.52.950 on DBFOT toll basis 52.9 KM (Kilometer) 752.88 Transport Roads and bridges Operation and Maintenance Stage Uttar Pradesh State Highways Authority Uttar Pradesh 20-Aug-2019
1040 Development of modern food silo for storage of wheat on DBFOT at Whitefield, Bangalore (Karnataka) - Proposed by FPD 25000.0 MT (Metric Tonne ) 28.52 Social and Commercial Infrastructure Post-harvest storage infrastructure for agriculture and horticulture produce including cold storage Under Construction Food Corporation of India Karnataka 20-Aug-2019
1041 Four laning with paved shoulder in Bareilly-Almora section of SH 37 in the State of Uttar Pradesh on DBFOT basis 54.0 KM (Kilometer) 604.55 Transport Roads and bridges Operation and Maintenance Stage Uttar Pradesh State Highways Authority Uttar Pradesh 20-Aug-2019
1042 Four-laning of Varanasi-Shaktinagar road of SH-5A in UP under DBFOT basis 115.0 KM (Kilometer) 1757.39 Transport Roads and bridges Operation and Maintenance Stage Uttar Pradesh State Highways Authority Uttar Pradesh 20-Aug-2019
1043 Multilevel Parking (Shimla) Project 700.0 ECS 46.11 Transport Urban public transport (except rolling stock) Operation and Maintenance Stage Shimla Municipal Corporation Himachal Pradesh 20-Aug-2019
1044 Roadways between Madhyakailash-Sholinganallur 22.0 KM (Kilometer) 412 Transport Roads and bridges Operation and Maintenance Stage Tamil Nadu Road Development Company Limited Tamil Nadu 20-Aug-2019
1045 Solid Waste Management (Sewapura) Project 250.0 TPD (Tonne per day) 26.34 Water Sanitation Solid waste management Operation and Maintenance Stage Jaipur Municipal Corporation Rajasthan 20-Aug-2019
1046 "Mohol � Kurul � Mandrup Kamti Project " 33.4 KM (Kilometer) 18 Transport Roads and bridges Operation and Maintenance Stage Public Works Department, Maharashtra Maharashtra 19-Aug-2019
1047 Amusement Park (Kankaria Balvatika) Not Available 32 Social and Commercial Infrastructure Tourism Operation and Maintenance Stage Ahmedabad Municipal Corporation Gujarat 19-Aug-2019
1048 Bikaner Bypass Project 28.0 KM (Kilometer) 12.02 Transport Roads and bridges Completed Public Works Department, Rajasthan Rajasthan 19-Aug-2019
1049 Construction of 2 lane Bridge across Vasista Branch of river Godavari connecting Narsapur of West Godavri District with Sakhinet Not Available 66.57 Transport Roads and bridges Operation and Maintenance Stage Andhra Pradesh Road Development Corporation Andhra Pradesh 19-Aug-2019
1050 Construction of central bus terminal on 5.1 acres in Vadodara 5.1 Acres 144 Transport Urban public transport (except rolling stock) Operation and Maintenance Stage Gujarat State Road Transport Corporation Gujarat 19-Aug-2019
1051 Construction of cold storage 6000 MT at KUMS Jodhpur 6000.0 MT (Metric Tonne ) 5.11 Social and Commercial Infrastructure Cold Chain Operation and Maintenance Stage Rajasthan State Agriculture Marketing Board Rajasthan 19-Aug-2019
1052 Construction of green field bridge across river Ganga connecting Bakhtiyarpur 50.95 KM (Kilometer) 1599.57 Transport Roads and bridges Operation and Maintenance Stage Bihar State Road Development Corporation Limited Bihar 19-Aug-2019
1053 Construction,O&M of Durg bypass on NH6 in Madhya Pradesh on BOT basis 18.0 KM (Kilometer) 123 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Chhattisgarh 19-Aug-2019
1054 Design, engineering, construction, development, finance,O&M Palanpur-Swaroopganj section,NH-14 Gujarat &amp; Rajasthan 76.0 KM (Kilometer) 498 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Multi State/ Centre 19-Aug-2019
1055 Design, Engineering, Upgradation, Development, Finance, Operation and Maintenance of Hyderabad-Bangalore section of NH 7 22.1 KM (Kilometer) 747.3 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Multi State/ Centre 19-Aug-2019
1056 Design,Engineering,Finance,Construction,O&M,highway project of Bangalore-Nelamangala section of NH:4 from Karnataka on (BOT) 19.5 KM (Kilometer) 718.59 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Karnataka 19-Aug-2019
1057 Development of East Quay-I (EQ-1) berth for handling steam coal in the inner harbour of Visakhapatnam port 6.4 MTPA (Metric Tonne Per Annum) 323.7 Transport Ports (excluding captive) Operation and Maintenance Stage Visakhapatnam Port Trust Andhra Pradesh 19-Aug-2019
1058 Four Laning from Junction of NH-68 with NH-7 near Salem to Junction of NH-68 with NH-45 near Ulundrupet in Tamil Nadu on BOT 136.3 KM (Kilometer) 1061 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Tamil Nadu 19-Aug-2019
1059 Four laning of Haryana/Punjab Border to Jind Section of NH-71 from Km 239.000 to Km 307.000 in Haryana on BOT (Toll) basis 69.35 KM (Kilometer) 438.75 Transport Roads and bridges Under Construction Ministry of Road Transport and Highways Haryana 19-Aug-2019
1060 Four laning of Pune-Solapur NH-9 road in length of 110 km under NHDP-IIIB (Pkg-I) 110.0 KM (Kilometer) 1110 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Maharashtra 19-Aug-2019
1061 Four laning of Rewa to MP/UP Border of NH 7 in the State of Madhya Pradesh 89.3 KM (Kilometer) 736.7 Transport Roads and bridges Operation and Maintenance Stage Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 19-Aug-2019
1062 Four/Six laning of Amritsar-Pathankot Section from KM 6.082 to KM 108.502 of NH 15 Under NHDP Phase III on BOT Basis 102.4 KM (Kilometer) 705 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Punjab 19-Aug-2019
1063 Four/six laning of Reengus-Sikar road in length of 43.9 km on NH-11 under NHDP-III A 43.9 KM (Kilometer) 228 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Rajasthan 19-Aug-2019
1064 Improvement of Dharwad- Ramnagar Stretch 61.75 KM (Kilometer) 237.6 Transport Roads and bridges Operation and Maintenance Stage Karnataka Road Development Corporation Limited (KRDCL) Karnataka 19-Aug-2019
1065 Improvement,O&M including strengthening and widening of existing 2 lane NH 24 (Lucknow - Sitapur section) U.P(BOT) basis 75.0 KM (Kilometer) 450.41 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Uttar Pradesh 19-Aug-2019
1066 Kharpada Bridge Project 1.4 KM (Kilometer) 32 Transport Roads and bridges Operation and Maintenance Stage Ministry of Road Transport and Highways Maharashtra 19-Aug-2019
1067 Logistics Hub (Pawarkheda) Project 115.0 Acres 138.5 Social and Commercial Infrastructure Common infrastructure for industrial parks, SEZ Operation and Maintenance Stage Madhya Pradesh State Agriculture Marketing Board Madhya Pradesh 19-Aug-2019
1068 Maheshwaram Transmission Limited 236.0 KM (Kilometer) 345 Energy Electricity transmission Operation and Maintenance Stage Not Available Telangana 19-Aug-2019
1069 Maintenance of Thane Ghodabunder Road 14.9 KM (Kilometer) 246.28 Transport Roads and bridges Operation and Maintenance Stage Maharashtra State Road Development Corporation Limited (MSRDC) Maharashtra 19-Aug-2019
1070 MIHAN Coal Based Power Project 271.6 MW (Mega Watt) 1748 Energy Electricity generation (grid) Operation and Maintenance Stage Maharashtra Airport Development Company Limited Maharashtra 19-Aug-2019
1071 Mumbai International Airport Project - Modernisation 40.0 MPPA (Million Passenger Per Annum) 12630 Transport Airports Operation and Maintenance Stage Airports Authority of India (AAI) Maharashtra 19-Aug-2019
1072 Operation & maintenance of Badnawar-Thandla road in length of 78.8 Km in Jhabua &amp; Dhar districts 78.8 KM (Kilometer) 44.12 Transport Roads and bridges Operation and Maintenance Stage Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 19-Aug-2019
1073 Operation & Maintenance of Baran-Shivpuri-Jhansi section in length of 196.1 Km of NH-27 196.1 KM (Kilometer) 19 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Maharashtra 19-Aug-2019
1074 Operation & maintenance of Bela-Govindgarh-Churhat road in length of 56.6 Km in Rewa &amp; Sidhi districts 56.74 KM (Kilometer) 60.85 Transport Roads and bridges Operation and Maintenance Stage Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 19-Aug-2019
1075 Operation & Maintenance of Borkhedi-Wadner section in length of 57.15 Km of NH-7 57.15 KM (Kilometer) 21.58 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Maharashtra 19-Aug-2019
1076 Operation & maintenance of Budhni-Rehti-Nasrullaganj-Khategaon road in length of 87.6 Km in Sehore &amp; Dewas districts 87.4 KM (Kilometer) 77.45 Transport Roads and bridges Operation and Maintenance Stage Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 19-Aug-2019
1077 Operation & maintenance of Chennai Bypass in length of 32.60 km. 32.6 KM (Kilometer) 480 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Tamil Nadu 19-Aug-2019
1078 Operation & maintenance of Edapally-Vytilla-Aroor section of NH-66 17.0 KM (Kilometer) 184 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Kerala 19-Aug-2019
1079 Operation & maintenance of multi chamber cold storages at Udaipur, Bhilwara &amp; Pali districts. 5000.0 MTPA (Metric Tonne Per Annum) 5.64 Social and Commercial Infrastructure Cold Chain Operation and Maintenance Stage Rajasthan State Agriculture Marketing Board Rajasthan 19-Aug-2019
1080 Operation & maintenance of various roads in length of 95 km in Bhopal, Vidihsa &amp; Sehore districts 95.0 KM (Kilometer) 29.2 Transport Roads and bridges Operation and Maintenance Stage Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 19-Aug-2019
1081 Operation and maintaenance of organic agriculture produces market complex at Sixmile, Khanapara, Guwahati on PPP mode 1.4 Acres 7.7 Social and Commercial Infrastructure Post-harvest storage infrastructure for agriculture and horticulture produce including cold storage Operation and Maintenance Stage Assam State Agricultural Marketing Board Assam 19-Aug-2019
1082 Patan-Tendukheda-Rehli 86.6 KM (Kilometer) 219.62 Transport Roads and bridges Operation and Maintenance Stage Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 19-Aug-2019
1083 Road Upgradation (Bilaspur-Katghora-Korba-Champa) Project 151.0 KM (Kilometer) 26.53 Transport Roads and bridges Operation and Maintenance Stage Public Works Department, Chhattisgarh Chhattisgarh 19-Aug-2019
1084 Road Upgradation (Chinchoti-Kaman-Anjurphata-Mankoli Road) Project 26.4 KM (Kilometer) 120.51 Transport Roads and bridges Operation and Maintenance Stage Public Works Department, Maharashtra Maharashtra 19-Aug-2019
1085 Road Upgradation (Kadapa-Pulivendula) KP-03 Project 18.0 KM (Kilometer) 81.32 Transport Roads and bridges Operation and Maintenance Stage Andhra Pradesh Road Development Corporation Andhra Pradesh 19-Aug-2019
1086 Road Upgradation (Makhupura-Gujarat State Border) Project 12.0 KM (Kilometer) 11.61 Transport Roads and bridges Completed Public Works Department, Rajasthan Rajasthan 19-Aug-2019
1087 Road Upgradation (Rayalapuram-Gandluru) Project 1.0 KM (Kilometer) 17.7 Transport Roads and bridges Operation and Maintenance Stage Andhra Pradesh Road Development Corporation Andhra Pradesh 19-Aug-2019
1088 Road Upgradation (Ro-Ro Point-NH-8 E) Project 14.7 KM (Kilometer) 29.36 Transport Roads and bridges Operation and Maintenance Stage Public Works Department, Gujarat Gujarat 19-Aug-2019
1089 Road Upgradation (Salumber-Banswara) Project 93.0 KM (Kilometer) 68.14 Transport Roads and bridges Operation and Maintenance Stage Public Works Department, Rajasthan Rajasthan 19-Aug-2019
1090 Road Upgradation Project (Deharda-Ishagarh ) Project 32.93 KM (Kilometer) 50.57 Transport Roads and bridges Under Construction Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 19-Aug-2019
1091 Road Upgradation Project (Mhow-Ghatabillod) Project 27.0 KM (Kilometer) 177.3 Transport Roads and bridges Operation and Maintenance Stage Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 19-Aug-2019
1092 Road Upgradation Project (Sehore-Ichhawar-Kosmi) Project 50.12 KM (Kilometer) 89 Transport Roads and bridges Operation and Maintenance Stage Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 19-Aug-2019
1093 Road Upgradation Project (Sijhata-Hinoti-Malgaon-Khamariya-Ater) Project 32.2 KM (Kilometer) 43.56 Transport Roads and bridges Operation and Maintenance Stage Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 19-Aug-2019
1094 Road Upgradation Project (Sitamau-Basai-Suwasara) Project 34.97 KM (Kilometer) 54.26 Transport Roads and bridges Operation and Maintenance Stage Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 19-Aug-2019
1095 Two laning of Ujjain Unhel Nagda Jawra Road 95.2 KM (Kilometer) 189.05 Transport Roads and bridges Operation and Maintenance Stage Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 19-Aug-2019
1096 Two laning with granular shoulder from km 0.00 to km 38.00 of Lakhnadon-Ghansore section of SH 40 on DBFOT (Toll) basis 38.0 KM (Kilometer) 79 Transport Roads and bridges Operation and Maintenance Stage Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 19-Aug-2019
1097 Upgradation of Bhuj-Nakhtrana road in length of 44.8 Km 45.0 KM (Kilometer) 35.04 Transport Roads and bridges Operation and Maintenance Stage Gujarat State Road Development Corporation Limited (GSRDC) Gujarat 19-Aug-2019
1098 Upgradation of Uchera-Nagod-Singhpur-Kalinjer road in length of 55.6 km in Raisen district 55.56 KM (Kilometer) 115.2 Transport Roads and bridges Operation and Maintenance Stage Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 19-Aug-2019
1099 Upgradation of Umari-Phoop-Pratappura road in length of 43.39 km in Madhya Pradesh 43.67 KM (Kilometer) 75.29 Transport Roads and bridges Operation and Maintenance Stage Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 19-Aug-2019
1100 Viramgam Mehsana Gauge (Railway Track) Conversion Project 90.0 KM (Kilometer) 102.22 Transport Railway track, tunnel, viaducts, bridges Operation and Maintenance Stage Western Railway Gujarat 19-Aug-2019
1101 Waste Based Power Unit (Kathonda) 11.50 MW (Mega Watt) 177.96 Energy Renewable energy (grid) Operation and Maintenance Stage Jabalpur Municipal Corporation Madhya Pradesh 19-Aug-2019
1102 Widening of Existing 2 Lane carriageway to 4/6 lane divided carriageway of Bangalore-Hoskate-Mulbagal section of NH-4 on BOT 79.7 KM (Kilometer) 565 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Karnataka 19-Aug-2019
1103 Augmentation of 200 MLD sewage treatment plant at Bhandewadi in Nagpur district 200.0 MLD (Millons Liter per day) 170 Water Sanitation Sewage collection, treatment and disposal system Operation and Maintenance Stage Nagpur Municipal Corporation Maharashtra 16-Aug-2019
1104 Sikka 2 Captive Port Terminals Not Available 3000 Transport Ports (excluding captive) Operation and Maintenance Stage Gujarat Maritime Board (GMB) Gujarat 16-Aug-2019
1105 Widening and strengthening of Wadi Raichur Road 88.0 KM (Kilometer) 82 Transport Roads and bridges Operation and Maintenance Stage Karnataka Road Development Corporation Limited (KRDCL) Karnataka 16-Aug-2019
1106 "DEFC",O&M of end of Durg bypass - Chhattisgarh/Maharashtra border sec. NH6 under NHDP 3A on(BOT) basis 82.6 KM (Kilometer) 464 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Chhattisgarh 14-Aug-2019
1107 Dahej LNG Terminal 5.0 MMTPA (million metric tonnes per annum) 2287 Transport Ports (excluding captive) Operation and Maintenance Stage Gujarat Maritime Board (GMB) Gujarat 14-Aug-2019
1108 Design, Engineering, Construction, Development, Finance, O and M near Padalur near Trichy NH-45 Tamil Nadu on (BOT) basis 40.0 KM (Kilometer) 320 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Tamil Nadu 14-Aug-2019
1109 Four laning of Ahmedabad to Godhra section of NH 59 in the State of Gujarat under NHDP Phase III on DBFOT pattern 117.6 KM (Kilometer) 1174.36 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Gujarat 14-Aug-2019
1110 Operation & Maintenance of Kanpur-Lucknow, Lucknow bypass &amp; Lucknow-Ayodhya section in length of 217.4 Km 217.4 KM (Kilometer) 965.56 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Uttar Pradesh 14-Aug-2019
1111 Operation & maintenance of Kolaghat-Haldia section of NH-41 53.0 KM (Kilometer) 622 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) West Bengal 14-Aug-2019
1112 Rehabilitation and upgrading of Forbesganj - Jogbani road 9.25 KM (Kilometer) 322 Transport Roads and bridges Under Construction National Highways Authority of India (NHAI) Bihar 14-Aug-2019
1113 Road Upgradation (Vadodara-Bharuch NH-8) Project 83.3 KM (Kilometer) 1450 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Gujarat 14-Aug-2019
1114 Two laning of Jhalawar-Ujjain section in length of 31.0 Km 31.0 KM (Kilometer) 75.88 Transport Roads and bridges Operation and Maintenance Stage Public Works Department, Rajasthan Rajasthan 14-Aug-2019
1115 Two laning of Khushkhera-Kasola Chowk in length of 8.5 Km 8.5 KM (Kilometer) 34.5 Transport Roads and bridges Operation and Maintenance Stage Public Works Department, Rajasthan Rajasthan 14-Aug-2019
1116 Yamuna Expressway Connecting Greater Noida to Agra 165.0 KM (Kilometer) 14000 Transport Roads and bridges Operation and Maintenance Stage Yamuna Expressway Industrial Development Authority (YEA) Uttar Pradesh 14-Aug-2019
1117 Bhina-Khimalsa-Malthon Road Project 39.4 KM (Kilometer) 67.3 Transport Roads and bridges Operation and Maintenance Stage Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 13-Aug-2019
1118 Manawar-Singhan-Kukshi 38.23 KM (Kilometer) 96.73 Transport Roads and bridges Operation and Maintenance Stage Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 13-Aug-2019
1119 Road Upgradation Project (Biaora- Rajasthan) Project 61.0 KM (Kilometer) 221 Transport Roads and bridges Operation and Maintenance Stage Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 13-Aug-2019
1120 140 MW Solar Photovoltaic Project in Rajasthan 140.0 MW (Mega Watt) 524.86 Energy Renewable energy (grid) Operation and Maintenance Stage Not Available Rajasthan 12-Aug-2019
1121 220 MW CCPP Tanir Bavi Barge 220.0 MW (Mega Watt) 1400 Energy Electricity generation (grid) Operation and Maintenance Stage Karnataka Power Transmission Corporation Limited (KPTCL) Karnataka 12-Aug-2019
1122 300 MW Thermal power plant in Chattisgarh 300.0 MW (Mega Watt) 3828 Energy Electricity generation (grid) Operation and Maintenance Stage Not Available Chhattisgarh 12-Aug-2019
1123 Bhesada Renew Wind Energy Project 100.8 MW (Mega Watt) 696 Energy Renewable energy (grid) Operation and Maintenance Stage Not Available Rajasthan 12-Aug-2019
1124 Dahej SEZ power project 1200.0 MW (Mega Watt) 5325.39 Energy Electricity generation (grid) Operation and Maintenance Stage Not Available Gujarat 12-Aug-2019
1125 Development of Kaman Paygon Bhiwandi road 22.0 KM (Kilometer) 14.4 Transport Roads and bridges Completed Public Works Department, Maharashtra Maharashtra 12-Aug-2019
1126 Devgarh wind power project, Rajsamand district 37.5 MW (Mega Watt) 314.5 Energy Renewable energy (grid) Operation and Maintenance Stage Not Available Rajasthan 12-Aug-2019
1127 Four Laning of Pune-Khed section in 29.8 Km under NHDP-III 29.8 KM (Kilometer) 127.6 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Maharashtra 12-Aug-2019
1128 Four Lanning of Panagarh - Palsit Road 64.4 KM (Kilometer) 517 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) West Bengal 12-Aug-2019
1129 Karaikal Port 14.5 MMTPA (million metric tonnes per annum) 2066 Transport Ports (excluding captive) Operation and Maintenance Stage Port Department, Puducherry Puducherry (UT) 12-Aug-2019
1130 Khandke Wind Farm 50.0 MW (Mega Watt) 340.88 Energy Renewable energy (grid) Operation and Maintenance Stage Not Available Maharashtra 12-Aug-2019
1131 Lalitpur Power Generation Company Ltd. 1980.0 MW (Mega Watt) 14306 Energy Electricity generation (grid) Operation and Maintenance Stage Not Available Uttar Pradesh 12-Aug-2019
1132 Liquid Cargo Berth (JNPT) Project 6.5 MMTPA (million metric tonnes per annum) 200 Transport Ports (excluding captive) Operation and Maintenance Stage Jawaharlal Nehru Port Trust Maharashtra 12-Aug-2019
1133 Mundra Thermal Power Project 4620.0 MW (Mega Watt) 22001 Energy Electricity generation (grid) Operation and Maintenance Stage Not Available Gujarat 12-Aug-2019
1134 Operation & Maintenance of Hyderabad-Bangalore section in length of 251.2 Km 251.2 KM (Kilometer) 48.6 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Andhra Pradesh 12-Aug-2019
1135 Pench IV (Godhani)water treatment plant 115.0 MLD (Millons Liter per day) 25 Water Sanitation Water treatment plants Operation and Maintenance Stage Nagpur Municipal Corporation Maharashtra 12-Aug-2019
1136 Prayagraj Power Generation Co. Ltd. - Coal based super-critical thermal power project 1980.0 MW (Mega Watt) 15537 Energy Electricity generation (grid) Operation and Maintenance Stage Prayagraj Power Generation Co. Ltd Uttar Pradesh 12-Aug-2019
1137 Sagar-Damoh Road Project 68.8 KM (Kilometer) 130.3 Transport Roads and bridges Operation and Maintenance Stage Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 12-Aug-2019
1138 Thermal Power Project in Janjgir-Champa District 1200.0 MW (Mega Watt) 8464 Energy Electricity generation (grid) Operation and Maintenance Stage Athena Chhattisgarh Power Limited�(ACPL) Chhattisgarh 12-Aug-2019
1139 Vemagiri Power Generation Limited 388.0 MW (Mega Watt) 1150 Energy Electricity generation (grid) Operation and Maintenance Stage GMR Vemagiri Power Generation Limited Andhra Pradesh 12-Aug-2019
1140 Vishnu Prayag HEP (400 MW) 400.0 MW (Mega Watt) 1694 Energy Renewable energy (grid) Operation and Maintenance Stage Not Available Uttarakhand 12-Aug-2019
1141 "DCDF", O&M of Islam Nagar Nagpur-Hyderabad sec.NH7 Andhra Pradesh NHDP-2 on BOT (Annuity) basis 53.0 KM (Kilometer) 518 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Telangana 09-Aug-2019
1142 Construction of ring road in length of 18 km in Bellary 18.0 KM (Kilometer) 90 Transport Roads and bridges Operation and Maintenance Stage Bellary Urban Development Authority (BUDA) Karnataka 09-Aug-2019
1143 Four Laning of following State Highways in Madhya Pradesh : Joura-Nnayagaon 127.8 KM (Kilometer) 730 Transport Roads and bridges Operation and Maintenance Stage Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 09-Aug-2019
1144 Hydro Electric Power (Barvi) Project 5.0 MW (Mega Watt) 53 Energy Renewable energy (grid) Operation and Maintenance Stage Maharashtra Industrial Development Corporation Maharashtra 09-Aug-2019
1145 Implementation of 600 TPD solid waste management in Faridabad 600.0 TPD (Tonne per day) 37.33 Water Sanitation Solid waste management Operation and Maintenance Stage Municipal Corporation of Faridabad Haryana 09-Aug-2019
1146 IT Expressway (Three-lane carriageway) 20.0 KM (Kilometer) 290 Transport Roads and bridges Operation and Maintenance Stage Highway Department, Government of Tamil Nadu Tamil Nadu 09-Aug-2019
1147 Nellore-Tada Road 110.5 KM (Kilometer) 511 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Andhra Pradesh 09-Aug-2019
1148 Operation & maintenance of Rajiv Gandhi Sea Link Project 5.0 KM (Kilometer) 11 Transport Roads and bridges Operation and Maintenance Stage Maharashtra State Road Development Corporation Limited (MSRDC) Maharashtra 09-Aug-2019
1149 Providing fixing & maintenance of overhead signage &amp; foot bridges on roads of JDA region Not Available 8.2 Transport Urban public transport (except rolling stock) Operation and Maintenance Stage Jaipur Development Authority Rajasthan 09-Aug-2019
1150 Road Upgradation Project (Harda-Chhipaner) Project 29.3 KM (Kilometer) 38.6 Transport Roads and bridges Operation and Maintenance Stage Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 09-Aug-2019
1151 Development of road from NH-63 near Ginigere-Gangavathi to Sindhanur 83.0 KM (Kilometer) 190.16 Transport Roads and bridges Operation and Maintenance Stage Karnataka Road Development Corporation Limited (KRDCL) Karnataka 08-Aug-2019
1152 Two laning of Whaghari- Ribbanpally stretch 141.2 KM (Kilometer) 242.75 Transport Roads and bridges Operation and Maintenance Stage Karnataka Road Development Corporation Limited (KRDCL) Karnataka 08-Aug-2019
1153 4 laning of Ghaghar Bridge(Indo Nepal Border) to Varanasi section from Km 121.8 to Km 298.45 of NH 233 in UP on BOT (Toll) basis 177.652 KM (Kilometer) 2200 Transport Roads and bridges Operation and Maintenance Stage Ministry of Road Transport and Highways Uttar Pradesh 06-Aug-2019
1154 Four laning of Muzzafarnagar-Nepali farm section of NH 58 in Uttar Pradesh and Uttrakhand from Nepali to ISBT Dehradun 97.0 KM (Kilometer) 1251.42 Transport Roads and bridges Under Construction National Highways Authority of India (NHAI) Multi State/ Centre 06-Aug-2019
1155 Four-laning of Jabalpur- Kanti- Rewa Section of NH-7 from km 242.30 to km 465.50 in MP on BOT (Toll) 65.0 KM (Kilometer) 1906.83 Transport Roads and bridges Under Construction Ministry of Road Transport and Highways Madhya Pradesh 06-Aug-2019
1156 Ichchhapore - Hazira Not Available 16 Transport Roads and bridges Operation and Maintenance Stage Roads and Buildings Department, Gujarat Gujarat 06-Aug-2019
1157 Four laning of Kundapur to Suratkal section and Mangalore-Kerala border section of NH 17 on BOT Basis 90.28 KM (Kilometer) 616 Transport Roads and bridges Under Construction Ministry of Road Transport and Highways Karnataka 31-Jul-2019
1158 Design, Engineering, Finance, Construction, Operation and Maintenance of 4 laning of Bijapur-Hungund section of NH13 on DBFOT 97.0 KM (Kilometer) 1226.37 Transport Roads and bridges Operation and Maintenance Stage Ministry of Road Transport and Highways Karnataka 25-Jul-2019
1159 Two /Four laning with PSS of Gadu to Dwaraka section on NH 8E from km 263.000 to km 473.000 inGujarat on DBFOT pattern Not Available 1528.72 Transport Roads and bridges Operation and Maintenance Stage Ministry of Road Transport and Highways Gujarat 24-Jul-2019
1160 Two laning with PSS a section, between Kerala Border to Kollegal section of NH-212 inKarnataka on BOT (Toll) basis under NHDP-IV 150.041 KM (Kilometer) 523.49 Transport Roads and bridges Under Construction Ministry of Road Transport and Highways Karnataka 24-Jul-2019
1161 Two-laning with PSS section, between Bijapur, Gulbarga, Homnabad section of NH 218 from Km 195 to Km 418 on BOT (Toll) 220.47 KM (Kilometer) 680.73 Transport Roads and bridges Operation and Maintenance Stage Ministry of Road Transport and Highways Rajasthan 24-Jul-2019
1162 Two/ four laning of Obedullaganj -Shahganj Junction, Budhni- Betul Section of NH 69� under NHDP-IV, length� 121.36 km Not Available 1152 Transport Roads and bridges Under Construction Ministry of Road Transport and Highways Madhya Pradesh 24-Jul-2019
1163 Four-laning of Rewa - Sidhi section of NH -75E in the State of Madhya Pradesh 80.6 KM (Kilometer) 627.87 Transport Roads and bridges Under Construction Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 23-Jul-2019
1164 Rehabilitation, strengthening and 4 laning of Ramban to Banihal section of NH 1A in Jammu and Kashmir 32.1 KM (Kilometer) 986 Transport Roads and bridges Under Construction Ministry of Road Transport and Highways Jammu & Kashmir 23-Jul-2019
1165 Rehabilitation, strengthening and Four laning of Udhampur to Ramban section of NH 1A from km 67 to km 89 & km 130 to km 151 40.07 KM (Kilometer) 971 Transport Roads and bridges Under Construction Ministry of Road Transport and Highways Jammu & Kashmir 23-Jul-2019
1166 2 laning from 0 to km7.95( Katni Bypass) & 4.6 to 245km of Katni-Shahdol-Anooppur to MP/CG Border section on NH-78 234.0 KM (Kilometer) 811.47 Transport Roads and bridges Operation and Maintenance Stage Ministry of Road Transport and Highways Madhya Pradesh 22-Jul-2019
1167 Development and Operation of Suratgarh-Sriganganagar section of NH 15 in the State of Rajasthan 78.11 KM (Kilometer) 224.03 Transport Roads and bridges Under Construction Public Works Department, Rajasthan Rajasthan 22-Jul-2019
1168 Four laning of Phagwara-Rupnagar of NH-344A in Punjab on Hybrid Annuity Mode (total 80.82 KM) 80.82 KM (Kilometer) 1444 Transport Roads and bridges Under Construction Ministry of Road Transport and Highways Punjab 22-Jul-2019
1169 Two-laning with Paved Side Shoulder (PSS) of Bihta- Mahabalipur-Aurangabad section of SH-2 & NH-98 118.0 KM (Kilometer) 362 Transport Roads and bridges Under Construction Bihar State Road Development Corporation Limited Bihar 22-Jul-2019
1170 2 laning with paved shoulder/4 laning of Tamil Nadu/Karnataka Border to Bangalore section of NH-209 on DBFOT (Toll) basis 191.89 KM (Kilometer) 693 Transport Roads and bridges Operation and Maintenance Stage Ministry of Road Transport and Highways Karnataka 19-Jul-2019
1171 2/4 laning of Vikravandi-Meensuruti Section of NH-45C and 2 laning with PSS from Meensuruti 93.5km to Thanjavur 164.614km 164.22 KM (Kilometer) 1090 Transport Roads and bridges Under Construction Ministry of Road Transport and Highways Tamil Nadu 19-Jul-2019
1172 4 laning of Chandikhole-Dubari-Talchar Secton of NH 200, 301.89-428.03km including km 8.5- km 15.75�in Orissa 132.5 KM (Kilometer) 1273 Transport Roads and bridges Under Construction Ministry of Road Transport and Highways Odisha 19-Jul-2019
1173 4 laning of Jorhat-Demow section from Km 453 to 534.8 (part of Nagaon-Dirbugah section) of NH 37 in Assam on BOT (Annuity) basis Not Available 562 Transport Roads and bridges Operation and Maintenance Stage Ministry of Road Transport and Highways Assam 19-Jul-2019
1174 4 laning with PSS of Jodhpur-Pali section of NH-65 and Pali bypass starting from on DBFOT (Toll) basis 70.0 KM (Kilometer) 425 Transport Roads and bridges Operation and Maintenance Stage Public Works Department, Rajasthan Rajasthan 19-Jul-2019
1175 Construction of Access Controlled Highways from Km. 10/0 to Km. 29/5 of Bangolore section of NH-4 inKarnataka on BOT basis Not Available 380 Transport Roads and bridges Operation and Maintenance Stage Ministry of Road Transport and Highways Karnataka 19-Jul-2019
1176 Construction of Elevated Six Lane Highway(Flyover) from Km 16(Delhi) to Km 20.5(Haryana) and its approaches on NH2 on BOT basis. 4.4 KM (Kilometer) 570 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Multi State/ Centre 19-Jul-2019
1177 Construction of new bridges and O&M of 4-laned road of the Baleshwar-Kharagpur section of NH60 from 0-119.3 km on BOT (Toll) 119.3 KM (Kilometer) 480.38 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Multi State/ Centre 19-Jul-2019
1178 Design Engineering,Construction,Development, Finance and Operation and maintenance of MP/Maharashtra Border Dhule section of NH3 97.0 KM (Kilometer) 1420 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Maharashtra 19-Jul-2019
1179 Design, Engineering, Finance, Construction, O&M of 4 laning of Bijapur-Hungund section of NH 13 on DBFOT basis 100.0 KM (Kilometer) 748 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Karnataka 19-Jul-2019
1180 Four -laning of Orrisa border to Aurang section of NH-6 from km 88 to km 239 in Chattisgarh on DBFOT (Toll) basis 150.0 KM (Kilometer) 1234 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Chhattisgarh 19-Jul-2019
1181 Four laning of Baihata Chariali to Tejpur Section of NH-52 (Km 0.00 to km 130.00) inAssam under NHDP Phase III on BOT basis. Not Available 1203.46 Transport Roads and bridges Operation and Maintenance Stage Ministry of Road Transport and Highways Assam 19-Jul-2019
1182 Four laning of Beawar Pali Pindwara Section of NH 14 from km 0 to km 244.12 in Rajasthan on BOT(Toll) basis� 244.12 KM (Kilometer) 2388 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Rajasthan 19-Jul-2019
1183 Four laning of Hazaribagh-Ranchi stretch of NH33 from Km 40.5 to Km114 including Kujju bypass in Jharkhand on BOT(Annuity) Basis 73.7 KM (Kilometer) 625.07 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Jharkhand 19-Jul-2019
1184 Four laning of Hospet-Chitradurga section of NH-13 from km 299 to km 418.6 in Karnataka on BoT (Toll) basis 120.0 KM (Kilometer) 1388 Transport Roads and bridges Under Construction National Highways Authority of India (NHAI) Karnataka 19-Jul-2019
1185 Four laning of Lucknow Raebarelly Section of NH-24 B from km 12.700 to km 82.700 on BoT (Annuity) under NHDP Phase-IV B inU.P. 70.0 KM (Kilometer) 635.9 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Uttar Pradesh 19-Jul-2019
1186 Four laning of Nagpur Wainganga Bridge Section of NH 6 from km 498 to km 544.2 in Maharashtra on BOT(Toll) basis� 60.0 KM (Kilometer) 484.19 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Maharashtra 19-Jul-2019
1187 Four laning of PSS of Sangrur - Punjab/Haryana border section of NH - 71 in Punjab on BOT (Toll) basis Not Available 481.59 Transport Roads and bridges Operation and Maintenance Stage Ministry of Road Transport and Highways Punjab 19-Jul-2019
1188 Four laning of Raiganj-Dalkhola section of NH 34 from km 398 to km 452.700 inWest Bangal on DBFOT basis under NHDP III 54.7 KM (Kilometer) 560.16 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) West Bengal 19-Jul-2019
1189 Four laning of Rampur-Kathgodam section of NH-87 from km 0 to km 88 in UP and Uttarakhand on BoT (Toll) basis 88.0 KM (Kilometer) 790 Transport Roads and bridges Under Construction National Highways Authority of India (NHAI) Uttarakhand 19-Jul-2019
1190 Four-laning of Rajsamand-Bhilwara section of NH-(78, 79 & 8) from km 0 to km 87.250 inRajasthan on BOT (Toll) basis. 87.2 KM (Kilometer) 677.79 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Rajasthan 19-Jul-2019
1191 Four/Six Laning of Jaipur-Tonk-Deoli section of NH 12 from km 18.7 to km 165 (length 148.77 kms) inRajasthan on BOT (Toll) basis 148.9 KM (Kilometer) 1733 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Rajasthan 19-Jul-2019
1192 Four/Two-laning of Baharagora to Sambalpur Section from km 200.00 to 566.000 Section of NH-6 in Orissa on BOT (Toll) basis 368.2 KM (Kilometer) 1948.64 Transport Roads and bridges Operation and Maintenance Stage Ministry of Road Transport and Highways Odisha 19-Jul-2019
1193 Six laning of Belgaum-Dharwad section of NH 4 from Km 515 to km 433 and Km 0 to Km62 in Karnataka under NHDP V on BOT basis 144.0 KM (Kilometer) 637.5 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Karnataka 19-Jul-2019
1194 Six Laning of Chilkaluripet-Vijayawada, including Guntur bypass and Mangalagiri bypass of Chennai-Vijayawada Section of NH-5 67.7 KM (Kilometer) 572.3 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Andhra Pradesh 19-Jul-2019
1195 Six laning of Samakhiali-Gandhidham section of NH 8A from km 306 to km 362.16 in Gujarat on BOT (Toll) basis on DBFO pattern 56.1 KM (Kilometer) 805.39 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Gujarat 19-Jul-2019
1196 Six/Four Laning of Zirakpur - Parwanoo section of NH-22 including Pinjore - Kalka - Parwanoo bypass in Punjab, Haryana and HP 28.6 KM (Kilometer) 295 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Multi State/ Centre 19-Jul-2019
1197 Two laning with paved shoulders of Raibarelly-Jaunpur Section of NH-231 from Km 0 to Km 166.4 in UP on BoT (Annuity) basis 166.4 KM (Kilometer) 993 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Uttar Pradesh 19-Jul-2019
1198 Design, Engineering, Construction, Finance and Maintenance of Jaipur Reengus section of NH 11 51.8 KM (Kilometer) 343 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Rajasthan 18-Jul-2019
1199 Development of Hyderabad-Vijayawada section and additional 2 Laning/future 6 Laning of NH 9 in Andhra Pradesh (km 160- km 221.5) 61.5 KM (Kilometer) 492 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Multi State/ Centre 18-Jul-2019
1200 Development of Hyderabad-Vijayawada section and additional 2 Laning/future 6 Laning of NH 9 in Andhra Pradesh (km 40 to km 160) 120.0 KM (Kilometer) 1740 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Multi State/ Centre 18-Jul-2019
1201 Development of Sinnar-Nashik section of NH-50 (from km 177.0001 to 201.350) with 4-lane through DBFOT (Toll)] basis. 25.31 KM (Kilometer) 312.96 Transport Roads and bridges Operation and Maintenance Stage Public Works Department, Maharashtra Maharashtra 18-Jul-2019
1202 Eight laning of Mukarba Chowk to Panipat of NH 1 (DEL-HRY) 72.0 KM (Kilometer) 2128.72 Transport Roads and bridges Under Construction National Highways Authority of India (NHAI) Haryana 18-Jul-2019
1203 Four laining of Gomti-Chauraha - Udaipur Section of NH - 8 , km 177.000 to km 260. 10 under NHDP�- IV A on BOT (Toll) Basis 83.0 KM (Kilometer) 1114.27 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Rajasthan 18-Jul-2019
1204 Four Laning from Trichy city of NH-45 to Dindigul on NH-45 in the state of Tamil Nadu under NHDP Phase III A on BOT basis 88.2 KM (Kilometer) 600 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Tamil Nadu 18-Jul-2019
1205 Four laning of Amritsar Wagha Boarder Section from Km.455.400 to Km 491.330 of NH-I in the State of Punjab on BOT basis. 35.9 KM (Kilometer) 206 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Punjab 18-Jul-2019
1206 Four laning of Armur-Adloor Yellareddy section of NH7 in the State of Andhra Pradesh 60.0 KM (Kilometer) 491 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Telangana 18-Jul-2019
1207 Four laning of Biora - Dewas section of NH-3 from Km 426.100 to Km 566.450 in the state of Madhya Pradesh under NHDP phase IV 140.4 KM (Kilometer) 1583.79 Transport Roads and bridges Under Construction National Highways Authority of India (NHAI) Madhya Pradesh 18-Jul-2019
1208 Four Laning of Devilalli Hassan Section of NH- 48 in the state of Karnataka under NHDP phase III A on BOT basis 79.0 KM (Kilometer) 453 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Karnataka 18-Jul-2019
1209 Four laning of Hoskate-Dabespet Section on NH-207 in the State of Karnataka under NHDP Phase IV on DBFOT (Toll) basis 80.02 KM (Kilometer) 720.69 Transport Roads and bridges Under Construction National Highways Authority of India (NHAI) Karnataka 18-Jul-2019
1210 Four laning of Hyderabad-Yadgiri section of NH 202 in the State of Andhra Pradesh under NHDP Phase III on BOT basis 35.6 KM (Kilometer) 514.91 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Telangana 18-Jul-2019
1211 Four laning of Jetput - Somnath Section of NH 80 in the State of Gujarat 123.0 KM (Kilometer) 828 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Gujarat 18-Jul-2019
1212 Four laning of Kazhakkuttam to Mukkola section in the State of Kerala 26.798 KM (Kilometer) 577.95 Transport Roads and bridges Under Construction Ministry of Road Transport and Highways Kerala 18-Jul-2019
1213 Four Laning of Khalghat-MP/ Maharashtra Border section of NH-3 from Km. 84.700 to Km.167.500 in the state of M.P. on BOT basis. 82.8 KM (Kilometer) 549 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Madhya Pradesh 18-Jul-2019
1214 Four laning of Kuttipuram-Edapally section of NH17 in the state of Kerala Not Available 1157.92 Transport Roads and bridges Under Construction Ministry of Road Transport and Highways Kerala 18-Jul-2019
1215 Four laning of Mangwan to� Satna to Bela section of NH 75 under VGF Scheme, length 48.04 km Not Available 320.48 Transport Roads and bridges Under Construction Ministry of Road Transport and Highways Madhya Pradesh 18-Jul-2019
1216 Four laning of Patna-Buxar section of NH 30 in the state of Bihar Not Available 1619.83 Transport Roads and bridges Under Construction Ministry of Road Transport and Highways Bihar 18-Jul-2019
1217 Four Laning of Pondicherry to Tindivanam on NH-66 in the state of Tamil Nadu under NHDP Phase III A on BOT basis 38.6 KM (Kilometer) 285 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Puducherry (UT) 18-Jul-2019
1218 Four laning of Rohtak to Bawal Section of NH 71 in the state of Haryana on DBFOT basis under NHDP III 83.6 KM (Kilometer) 669 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Haryana 18-Jul-2019
1219 Four laning of Rohtak to Panipat section of NH 71A from km 0 to km 80.858 in the state of Haryana on BOT basis under NHDP III 80.8 KM (Kilometer) 1087.83 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Haryana 18-Jul-2019
1220 Four laning of Sambalpur Baragarh of Orissa/Chhatisgarh border section of NH 6 from Km 0 to Km 88 in Orissa� 88.0 KM (Kilometer) 1142 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Odisha 18-Jul-2019
1221 Four laning of Talegaon - Amravati section of NH 6 in Maharashtra on DBFOT basis 67.8 KM (Kilometer) 610.59 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Maharashtra 18-Jul-2019
1222 Four Laning of Trivandrum, Kerala/ Tamil Nadu border including Trivandrum by-pass (Package I) Not Available 822.41 Transport Roads and bridges Under Construction Ministry of Road Transport and Highways Kerala 18-Jul-2019
1223 Four Laning of Walayar to Vadakkancherry Section (Package No.NS-2/BOT/KL-2) 58.0 KM (Kilometer) 901 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Kerala 18-Jul-2019
1224 Four-laning of Bhuban-Dubari-Chandikhole section of NH-200 in Odisha under NHDP-III on DBFOT (Toll) basis. 62.185 KM (Kilometer) 652 Transport Roads and bridges Operation and Maintenance Stage Ministry of Road Transport and Highways Odisha 18-Jul-2019
1225 Four-laning of Rohtak - Hisar Section of NH-10 connecting to NH-71, in Haryana under NHDP-III on BOT (Toll) basis 98.8 KM (Kilometer) 959.25 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Haryana 18-Jul-2019
1226 Four-laning with PSS of Jabalpur-Bhopal section of NH-12 from km 10.400 to km 301.800 under NHDP Phase III on BOT (Toll) basis 294.21 KM (Kilometer) 2485.96 Transport Roads and bridges Operation and Maintenance Stage Ministry of Road Transport and Highways Madhya Pradesh 18-Jul-2019
1227 Mechanisation of WQ-1� Berth in the Inner Harbour of Visakhapatanam� Port for handling Iron Ore on DBFOT Basis 280.0 Meter 275.2 Transport Ports (excluding captive) Under Construction Ministry of Shipping Andhra Pradesh 18-Jul-2019
1228 Six Laning of Chennai-Tada Section of NH-5 (43 Km) in Tamil Nadu 43.4 KM (Kilometer) 353.37 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Tamil Nadu 18-Jul-2019
1229 Six laning of Dankuni - Baleshwar section of NH 6 in West Bengal� 111.0 KM (Kilometer) 2034 Transport Roads and bridges Operation and Maintenance Stage Ministry of Road Transport and Highways West Bengal 18-Jul-2019
1230 Six Laning of Kishangarh-Ajmer-Beawar Section from KM 364.125 to KM 58.245 of NH 8 on BOT Basis 92.3 KM (Kilometer) 1712.77 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Rajasthan 18-Jul-2019
1231 Six laning of NH 4 from Tumkur to Chitradurga in Karnataka under NHDP Phase V on BOT (Toll) on DBFO pattern 114.0 KM (Kilometer) 1200 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Karnataka 18-Jul-2019
1232 Six laning of NH7 from Hosur to Krishnagiri on NH93 in Tamil Nadu 59.8 KM (Kilometer) 535 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Tamil Nadu 18-Jul-2019
1233 Six Laning of Pimpalgaon-Nashik-Gonde section of NH-3 in the State of Maharashtra under NHDP Phase IIIA on BOT basis. 60.0 KM (Kilometer) 1691 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Maharashtra 18-Jul-2019
1234 Six laning of Poonamallee-Walajapet section of NH 4 under NHDP V on BOT(Toll) basis 93.0 KM (Kilometer) 1548.61 Transport Roads and bridges Under Construction National Highways Authority of India (NHAI) Tamil Nadu 18-Jul-2019
1235 Six Laning of Surat-Dahisar Section of NH-8 (239 Km) in Gujarat and Maharashtra 239.0 KM (Kilometer) 2853 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Multi State/ Centre 18-Jul-2019
1236 Two laning of Deali - Kota section of NH 12 on Kota bypass in Rajasthan 83.04 KM (Kilometer) 823 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Multi State/ Centre 18-Jul-2019
1237 Two laning of Purnea-Khagaria section of NH 31 in the State of Bihar under NHDP Phase III on BOT (Annuity) basis� 140.0 KM (Kilometer) 676 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Bihar 18-Jul-2019
1238 Aurangabad Paithan and Baramati-Phaltan-Lonand-Shirwal Road projects 77.9 KM (Kilometer) 355.65 Transport Roads and bridges Under Construction Public Works Department, Maharashtra Maharashtra 17-Jul-2019
1239 Bhind-Mihona-Gopalpur Road project 50.9 KM (Kilometer) 82.1 Transport Roads and bridges Operation and Maintenance Stage Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 17-Jul-2019
1240 Construction of Bridge across river Godavari 4.15 KM (Kilometer) 1070 Transport Roads and bridges Operation and Maintenance Stage Andhra Pradesh Road Development Corporation Andhra Pradesh 17-Jul-2019
1241 Construction of new four lane connecting Lebad to Manpur 34.3 KM (Kilometer) 206.53 Transport Roads and bridges Operation and Maintenance Stage Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 17-Jul-2019
1242 Damoh- Jabalpur Road Project 98.5 KM (Kilometer) 249.6 Transport Roads and bridges Operation and Maintenance Stage Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 17-Jul-2019
1243 Development of 400 kV DCDS Sarni (Satpura)-Ashta transmission line project under DBFOT (Toll) 240.0 KM (Kilometer) 282.7 Energy Electricity transmission Operation and Maintenance Stage Madhya Pradesh Power Transmission Company Limited Madhya Pradesh 17-Jul-2019
1244 Development of Food grain Silos at Kaimur and Buxer, Bihar on DBFOT basis through PPP mode 100000.0 MT (Metric Tonne ) 65.28 Social and Commercial Infrastructure Post-harvest storage infrastructure for agriculture and horticulture produce including cold storage Pre-construction Stage Food Corporation of India Bihar 17-Jul-2019
1245 Development of Modern Silos for storage of Wheat on DBFOT basis under PPP mode at Borivali, Maharashtra 50000.0 MT (Metric Tonne ) 41.52 Social and Commercial Infrastructure Post-harvest storage infrastructure for agriculture and horticulture produce including cold storage Pre-construction Stage Food Corporation of India Maharashtra 17-Jul-2019
1246 Development of Modern Silos for storage of Wheat on DBFOT basis under PPP mode at Dhamora, Uttar Pradesh 50000.0 MT (Metric Tonne ) 37.86 Social and Commercial Infrastructure Post-harvest storage infrastructure for agriculture and horticulture produce including cold storage Pre-construction Stage Food Corporation of India Uttar Pradesh 17-Jul-2019
1247 Development of Silos for storage of wheat on DBFOT basis under PPP mode at Kotkapura, Punjab 25000.0 MT (Metric Tonne ) 35.62 Social and Commercial Infrastructure Post-harvest storage infrastructure for agriculture and horticulture produce including cold storage Operation and Maintenance Stage Ministry of Consumer Affairs, Food & Public Distribution, Government of India Punjab 17-Jul-2019
1248 Development of two lane Road of Beawer- Gomti section of NH 8 118.9 KM (Kilometer) 195 Transport Roads and bridges Under Construction Ministry of Road Transport and Highways Rajasthan 17-Jul-2019
1249 Development, operation and maintenace of Chomu chandwaji on SH-8B (total 15.4 km) 15.6 KM (Kilometer) 40 Transport Roads and bridges Operation and Maintenance Stage Public Works Department, Rajasthan Rajasthan 17-Jul-2019
1250 Four Laning of following State Highways in Madhya Pradesh : Bhopal, Devas 143.2 KM (Kilometer) 640 Transport Roads and bridges Operation and Maintenance Stage Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 17-Jul-2019
1251 Four Laning of Halol-Godhra-Shamlaji Road 173.0 KM (Kilometer) 1422 Transport Roads and bridges Operation and Maintenance Stage Gujarat State Road Development Corporation Limited (GSRDC) Gujarat 17-Jul-2019
1252 Four laning of Hyderabad-Karimnagar-Ramagundam Road Project 207.0 KM (Kilometer) 2209 Transport Roads and bridges Operation and Maintenance Stage Andhra Pradesh Road Development Corporation Telangana 17-Jul-2019
1253 Four laning of Jam Warora-Chandrapur-Rajura-Asifabad Road section of SH 266 40.0 KM (Kilometer) 228.26 Transport Roads and bridges Operation and Maintenance Stage Public Works Department, Maharashtra Maharashtra 17-Jul-2019
1254 Four laning of Lebad-Jaora section of SH 31 in Madhya Pradesh 125.0 KM (Kilometer) 682.5 Transport Roads and bridges Operation and Maintenance Stage Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 17-Jul-2019
1255 Four laning of Manjarsumba-Lokhandi-Sawargaon-Latur Not Available 203 Transport Roads and bridges Under Construction Public Works Department, Maharashtra Maharashtra 17-Jul-2019
1256 Four-laning of Ahmedabad � Viramgam - Maliya road 180.0 KM (Kilometer) 1397 Transport Roads and bridges Operation and Maintenance Stage Gujarat State Road Development Corporation Limited (GSRDC) Gujarat 17-Jul-2019
1257 Four-laning of Ahmednagar-Karmala road (SH-141) km 0.00 to km 80.6 road 59.5 KM (Kilometer) 638.2 Transport Roads and bridges Under Construction Public Works Department, Maharashtra Maharashtra 17-Jul-2019
1258 Four-laning of Rajkot-Jamnagar-Vadinar road 131.7 KM (Kilometer) 1096 Transport Roads and bridges Operation and Maintenance Stage Gujarat State Road Development Corporation Limited (GSRDC) Gujarat 17-Jul-2019
1259 Four-laning with paved shoulders of Rewa-Ring Road section from km 229.10 of NH-7 to km 6.2 of SH-9 under DBFOT (Toll) 8.3 KM (Kilometer) 74.2 Transport Roads and bridges Operation and Maintenance Stage Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 17-Jul-2019
1260 HVPNL 400 KV Jhajjar Power Transmission Project in Haryana on DBFOT basis 400.0 KV (Kilo Volt) 444 Energy Electricity transmission Operation and Maintenance Stage Haryana Vidyut Prasaran Nigam Limited Haryana 17-Jul-2019
1261 Improvement of Karanji-Chandrapur Road section of MSH - 6 & 7 on DBFOT basis 85.11 KM (Kilometer) 498.77 Transport Roads and bridges Under Construction Public Works Department, Maharashtra Maharashtra 17-Jul-2019
1262 Jam Warora-Chandrapur-Ballarpur-Bamni Road project 64.0 KM (Kilometer) 688.62 Transport Roads and bridges Operation and Maintenance Stage Public Works Department, Maharashtra Maharashtra 17-Jul-2019
1263 Providing VGF Funding for Construction of Silo at Changsari, Assam - Proposed by FPD 50000.0 MT (Metric Tonne ) 42.48 Social and Commercial Infrastructure Post-harvest storage infrastructure for agriculture and horticulture produce including cold storage Under Construction Food Corporation of India Assam 17-Jul-2019
1264 Providing VGF Funding for Construction of Silo at Narela, Delhi - Proposed by FPD 50000.0 MT (Metric Tonne ) 41.84 Social and Commercial Infrastructure Post-harvest storage infrastructure for agriculture and horticulture produce including cold storage Pre-construction Stage Food Corporation of India Delhi (UT) 17-Jul-2019
1265 Sehora-Majhgawan 39.85 KM (Kilometer) 92.65 Transport Roads and bridges Operation and Maintenance Stage Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 17-Jul-2019
1266 Strengthening and widening of Sarkhej Bhavanagar highway Not Available 883.04 Transport Roads and bridges Operation and Maintenance Stage Gujarat State Road Development Corporation Limited (GSRDC) Gujarat 17-Jul-2019
1267 Strengthening and Widening of two lane road with paved shoulders of Bhuj - Bachau Section of SH-42 in the State of Gujarat 77.0 KM (Kilometer) 256.94 Transport Roads and bridges Under Construction Gujarat State Road Development Corporation Limited (GSRDC) Gujarat 17-Jul-2019
1268 Strengthening of Chandpur-Alirajpur-Kukshi-Badwani State Highways in Madhya Pradesh 99.1 KM (Kilometer) 144 Transport Roads and bridges Operation and Maintenance Stage Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 17-Jul-2019
1269 Strengthening of Mandsaur-Sitamau Road (Upto Rajasthan Border) State Highway in Madhya Pradesh 44.0 KM (Kilometer) 42.3 Transport Roads and bridges Operation and Maintenance Stage Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 17-Jul-2019
1270 Strengthening of Matkuli-Tamia-Chindwara State Highways in Madhya Pradesh 112.0 KM (Kilometer) 213.3 Transport Roads and bridges Operation and Maintenance Stage Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 17-Jul-2019
1271 Two lane with paved side shoulders of Rawatsar-Nohar-Bhadra section of MDR 18 118.0 KM (Kilometer) 285.1 Transport Roads and bridges Operation and Maintenance Stage Road Infrastructure Development Company of Rajasthan Limited Rajasthan 17-Jul-2019
1272 Two laning of Ashoknagar-Vidisha 35.68 KM (Kilometer) 87.06 Transport Roads and bridges Operation and Maintenance Stage Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 17-Jul-2019
1273 Two laning of Betul-Sarni-Tikadhan-Junnardeo-Parasia section of SH 43 in MP on BOT(Toll) 124.1 KM (Kilometer) 238 Transport Roads and bridges Operation and Maintenance Stage Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 17-Jul-2019
1274 Two laning of Bina-Kurwal-Sironj 56.1 KM (Kilometer) 107 Transport Roads and bridges Operation and Maintenance Stage Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 17-Jul-2019
1275 Two laning of Chomu to Mahla via Renwal Jobner 89.0 KM (Kilometer) 270 Transport Roads and bridges Under Construction Public Works Department, Rajasthan Rajasthan 17-Jul-2019
1276 Two laning of Damoh - Katni section of SH-14 with NH-7 at km 366.1 under DBFOT (Toll) 117.93 KM (Kilometer) 272.07 Transport Roads and bridges Operation and Maintenance Stage Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 17-Jul-2019
1277 Two laning of Guna-Ashoknagar-Ishagarh Project (SH 20) on BOT basis 76.15 KM (Kilometer) 105.1 Transport Roads and bridges Under Construction Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 17-Jul-2019
1278 Two laning of Jhabua-Jobat-Zeerpanya-Bagh-Kukshi section of SH 39 in MP on BOT(Toll) 92.42 KM (Kilometer) 158 Transport Roads and bridges Operation and Maintenance Stage Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 17-Jul-2019
1279 Two laning of Khandwa-Dehtala-Burhanpur section of SH 50 in MP on BOT (Toll) 127.1 KM (Kilometer) 224.4 Transport Roads and bridges Operation and Maintenance Stage Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 17-Jul-2019
1280 Two laning of Morinda, Kurali, Siswan, H.P. Border Road (MDR-31)on BOT (Toll) 29.7 KM (Kilometer) 78.59 Transport Roads and bridges Operation and Maintenance Stage Public Works Department, Punjab Punjab 17-Jul-2019
1281 Two laning of Ratlam-Sailana-Banswada-section (MP - Rajasthan Border) at km 42.6 on SH-39 under DBFOT (Toll) 43.6 KM (Kilometer) 118 Transport Roads and bridges Operation and Maintenance Stage Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 17-Jul-2019
1282 Two laning with granular shoulder from km 0/10 to km 67/10 of Balaghat to Baihar section of SH 26 on DBFOT (Toll) basis 66.7 KM (Kilometer) 122.97 Transport Roads and bridges Operation and Maintenance Stage Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 17-Jul-2019
1283 Two-laning with paved side shoulder in Northern Kota Bypass 14.65 KM (Kilometer) 136.89 Transport Roads and bridges Under Construction Urban Improvement Trust, Kota Rajasthan 17-Jul-2019
1284 Upgradation of Narnaul to Kotputli- Chala- Sikar-Khud- Losal- Kuchaman State Highway Not Available 357.75 Transport Roads and bridges Operation and Maintenance Stage Rajasthan State Road Development and Construction Corporation Limited Rajasthan 17-Jul-2019
1285 Construction of 17 km long four lane Laddowal Bypass in Ludhiana district 17.0 KM (Kilometer) 392 Transport Roads and bridges Under Construction National Highways Authority of India (NHAI) Punjab 16-Jul-2019
1286 Four laning of Ajmer to Nagaur section on NH 89 from km 0.000 to km 161.000 in the State of Rajasthan 148.25 KM (Kilometer) 377.15 Transport Roads and bridges Under Construction Public Works Department, Rajasthan Rajasthan 16-Jul-2019
1287 Four Lanning of Hubli-Haveri section in length of 63.4 km 63.4 KM (Kilometer) 262.94 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Karnataka 16-Jul-2019
1288 Road Upgradation (Kante-Waked) Project 50.9 KM (Kilometer) 805.59 Transport Roads and bridges Pre-construction Stage National Highways Authority of India (NHAI) Maharashtra 16-Jul-2019
1289 Six laning of Ranastalam-Anandpuram section in length of 47 km 47.0 KM (Kilometer) 1041.62 Transport Roads and bridges Pre-construction Stage National Highways Authority of India (NHAI) Andhra Pradesh 16-Jul-2019
1290 Setting up of 9 MW Balargha small hydel power unit in Kullu district 9.0 MW (Mega Watt) 77.68 Energy Renewable energy (grid) Operation and Maintenance Stage Directorate of Energy, Himachal Pradesh Himachal Pradesh 23-Jun-2019
1291 Four laning of Ahmednagar-Kopargaon road in length of 55.5 Km 55.5 KM (Kilometer) 234 Transport Roads and bridges Operation and Maintenance Stage Public Works Department, Maharashtra Maharashtra 22-Jun-2019
1292 Aircel 2012-13 Not Available 669 Communication Telecommunication Network and Services Operation and Maintenance Stage Department of Telecom Multi State/ Centre 21-Jun-2019
1293 Aircel 2013-14 Not Available 502 Communication Telecommunication Network and Services Operation and Maintenance Stage Department of Telecom Multi State/ Centre 21-Jun-2019
1294 Aircel 2014-15 Not Available 5548 Communication Telecommunication Network and Services Operation and Maintenance Stage Department of Telecom Multi State/ Centre 21-Jun-2019
1295 Aircel 2015-16 Not Available 4758 Communication Telecommunication Network and Services Operation and Maintenance Stage Department of Telecom Multi State/ Centre 21-Jun-2019
1296 Bharat Broadband Network Limited 2012-13 Not Available 0 Communication Telecommunication Network and Services Operation and Maintenance Stage Department of Telecom Multi State/ Centre 21-Jun-2019
1297 Bharat Broadband Network Limited 2013-14 Not Available 0 Communication Telecommunication Network and Services Operation and Maintenance Stage Department of Telecom Multi State/ Centre 21-Jun-2019
1298 Bharat Broadband Network Limited 2014-15 Not Available 238 Communication Telecommunication Network and Services Operation and Maintenance Stage Department of Telecom Multi State/ Centre 21-Jun-2019
1299 Bharat Broadband Network Limited 2015-16 Not Available 1048 Communication Telecommunication Network and Services Operation and Maintenance Stage Department of Telecom Multi State/ Centre 21-Jun-2019
1300 Bharat Broadband Network Limited 2016-17 Not Available 4900 Communication Telecommunication Network and Services Operation and Maintenance Stage Department of Telecom Multi State/ Centre 21-Jun-2019
1301 Bharat Sanchar Nigam Limited 2012-13 Not Available 3892.73 Communication Telecommunication Network and Services Operation and Maintenance Stage Department of Telecom Multi State/ Centre 21-Jun-2019
1302 Bharat Sanchar Nigam Limited 2013-14 Not Available 7103.48 Communication Telecommunication Network and Services Operation and Maintenance Stage Department of Telecom Multi State/ Centre 21-Jun-2019
1303 Bharat Sanchar Nigam Limited 2014-15 Not Available 5446.24 Communication Telecommunication Network and Services Operation and Maintenance Stage Department of Telecom Multi State/ Centre 21-Jun-2019
1304 Bharat Sanchar Nigam Limited 2015-16 Not Available 3644.53 Communication Telecommunication Network and Services Operation and Maintenance Stage Department of Telecom Multi State/ Centre 21-Jun-2019
1305 Bharat Sanchar Nigam Limited 2016-17 Not Available 4719.64 Communication Telecommunication Network and Services Operation and Maintenance Stage Department of Telecom Multi State/ Centre 21-Jun-2019
1306 Bharat Sanchar Nigam Limited till 2011-12 Not Available 170671.16 Communication Telecommunication Network and Services Operation and Maintenance Stage Department of Telecom Multi State/ Centre 21-Jun-2019
1307 Bharti Airtel Limited 2012-13 Not Available 9657.1 Communication Telecommunication Network and Services Operation and Maintenance Stage Department of Telecom Multi State/ Centre 21-Jun-2019
1308 Bharti Airtel Limited 2013-14 Not Available 4614.6 Communication Telecommunication Network and Services Operation and Maintenance Stage Department of Telecom Multi State/ Centre 21-Jun-2019
1309 Bharti Airtel Limited 2014-15 Not Available 20989.7 Communication Telecommunication Network and Services Operation and Maintenance Stage Department of Telecom Multi State/ Centre 21-Jun-2019
1310 Bharti Airtel Limited 2015-16 Not Available 48446.7 Communication Telecommunication Network and Services Operation and Maintenance Stage Department of Telecom Multi State/ Centre 21-Jun-2019
1311 Bharti Airtel Limited 2016-17 Not Available 1072.8 Communication Telecommunication Network and Services Operation and Maintenance Stage Department of Telecom Multi State/ Centre 21-Jun-2019
1312 Bharti Airtel Limited investment till 2011-12 Not Available 66906.8 Communication Telecommunication Network and Services Operation and Maintenance Stage Department of Telecom Multi State/ Centre 21-Jun-2019
1313 Development of Terminal with Four Shore connected berths at Kakinada Port 40.0 MMTPA (million metric tonnes per annum) 1320 Transport Ports (excluding captive) Operation and Maintenance Stage Department of Ports, Andhra Pradesh Andhra Pradesh 21-Jun-2019
1314 Gangavaram Port Project - Phase I 100.0 MTPA (Metric Tonne Per Annum) 1696 Transport Ports (excluding captive) Operation and Maintenance Stage Department of Ports, Andhra Pradesh Andhra Pradesh 21-Jun-2019
1315 Green Field Super Speciality Hospital (Bathinda) 200.0 Beds 87.02 Social and Commercial Infrastructure Health Care Operation and Maintenance Stage Punjab Health Systems Corporation Punjab 21-Jun-2019
1316 IDEA India Limited 2012-13 Not Available 23933.9 Communication Telecommunication Network and Services Operation and Maintenance Stage Department of Telecom Multi State/ Centre 21-Jun-2019
1317 IDEA India Limited 2013-14 Not Available 4195.41 Communication Telecommunication Network and Services Operation and Maintenance Stage Department of Telecom Multi State/ Centre 21-Jun-2019
1318 IDEA India Limited 2014-15 Not Available 74690.06 Communication Telecommunication Network and Services Operation and Maintenance Stage Department of Telecom Multi State/ Centre 21-Jun-2019
1319 IDEA India Limited 2015-16 Not Available 39007.73 Communication Telecommunication Network and Services Operation and Maintenance Stage Department of Telecom Multi State/ Centre 21-Jun-2019
1320 IDEA India Limited 2016-17 Not Available 19306.62 Communication Telecommunication Network and Services Operation and Maintenance Stage Department of Telecom Multi State/ Centre 21-Jun-2019
1321 IDEA India Limited till 2011-12 Not Available 36032.31 Communication Telecommunication Network and Services Operation and Maintenance Stage Department of Telecom Multi State/ Centre 21-Jun-2019
1322 Implementation of 20 MLD sewage treatment plant at Udaipur 20.0 MLD (Millons Liter per day) 20 Water Sanitation Sewage collection, treatment and disposal system Operation and Maintenance Stage Udaipur Municipal Corporation Rajasthan 21-Jun-2019
1323 Improvement of Alwar - Bhiwari Road 79.0 KM (Kilometer) 18.62 Transport Roads and bridges Operation and Maintenance Stage Public Works Department, Rajasthan Rajasthan 21-Jun-2019
1324 Mahanagar Telephone Nigam Limited 2012-13 Not Available 526.19 Communication Telecommunication Network and Services Operation and Maintenance Stage Department of Telecom Multi State/ Centre 21-Jun-2019
1325 Mahanagar Telephone Nigam Limited 2013-14 Not Available 665.06 Communication Telecommunication Network and Services Operation and Maintenance Stage Department of Telecom Multi State/ Centre 21-Jun-2019
1326 Mahanagar Telephone Nigam Limited 2014-15 Not Available 559.11 Communication Telecommunication Network and Services Operation and Maintenance Stage Department of Telecom Multi State/ Centre 21-Jun-2019
1327 Mahanagar Telephone Nigam Limited 2015-16 Not Available 543.73 Communication Telecommunication Network and Services Operation and Maintenance Stage Department of Telecom Multi State/ Centre 21-Jun-2019
1328 Mahanagar Telephone Nigam Limited 2016-17 Not Available 311.04 Communication Telecommunication Network and Services Operation and Maintenance Stage Department of Telecom Multi State/ Centre 21-Jun-2019
1329 Mahanagar Telephone Nigam Limited till 2011-12 Not Available 30117.01 Communication Telecommunication Network and Services Operation and Maintenance Stage Department of Telecom Multi State/ Centre 21-Jun-2019
1330 Operation & maintenance of Allahabad bypass in length of 85 Km 85.0 KM (Kilometer) 1285 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Uttar Pradesh 21-Jun-2019
1331 Operation & maintenance of Garamore to Samakhiyali section in length of 52 km of NH-8A (New NH-27) 52.0 KM (Kilometer) 339 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Gujarat 21-Jun-2019
1332 Reliance Communication 2012-13 Not Available 1849 Communication Telecommunication Network and Services Operation and Maintenance Stage Department of Telecom Multi State/ Centre 21-Jun-2019
1333 Reliance Communication 2013-14 Not Available 1970 Communication Telecommunication Network and Services Operation and Maintenance Stage Department of Telecom Multi State/ Centre 21-Jun-2019
1334 Reliance Communication 2014-15 Not Available 1413 Communication Telecommunication Network and Services Operation and Maintenance Stage Department of Telecom Multi State/ Centre 21-Jun-2019
1335 Reliance Communication 2015-16 Not Available 2852 Communication Telecommunication Network and Services Operation and Maintenance Stage Department of Telecom Multi State/ Centre 21-Jun-2019
1336 Reliance Communication 2016-17 Not Available 10069 Communication Telecommunication Network and Services Operation and Maintenance Stage Department of Telecom Multi State/ Centre 21-Jun-2019
1337 Reliance Communication till 2011-12 Not Available 52455 Communication Telecommunication Network and Services Operation and Maintenance Stage Department of Telecom Multi State/ Centre 21-Jun-2019
1338 Reliance Jio Infocom Limited 2012-13 Not Available 2247 Communication Telecommunication Network and Services Operation and Maintenance Stage Department of Telecom Multi State/ Centre 21-Jun-2019
1339 Reliance Jio Infocom Limited 2013-14 Not Available 14181 Communication Telecommunication Network and Services Operation and Maintenance Stage Department of Telecom Multi State/ Centre 21-Jun-2019
1340 Reliance Jio Infocom Limited 2014-15 Not Available 43485 Communication Telecommunication Network and Services Operation and Maintenance Stage Department of Telecom Multi State/ Centre 21-Jun-2019
1341 Reliance Jio Infocom Limited 2015-16 Not Available 17100 Communication Telecommunication Network and Services Operation and Maintenance Stage Department of Telecom Multi State/ Centre 21-Jun-2019
1342 Reliance Jio Infocom Limited 2016-17 Not Available 50554 Communication Telecommunication Network and Services Operation and Maintenance Stage Department of Telecom Multi State/ Centre 21-Jun-2019
1343 Road Upgradation (Jabalpur-Narsinghpur-Piparia) Project 141.37 KM (Kilometer) 75 Transport Roads and bridges Operation and Maintenance Stage Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 21-Jun-2019
1344 Road Upgradation Project (Mundi-Punasa-Sulagoan-Sanawad) Project 67.6 KM (Kilometer) 124.8 Transport Roads and bridges Operation and Maintenance Stage Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 21-Jun-2019
1345 Road Upgradation Project (Sardarpur-Badnawar) Project 35.0 KM (Kilometer) 84 Transport Roads and bridges Operation and Maintenance Stage Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 21-Jun-2019
1346 Tata Communications 2012-13 Not Available 856.51 Communication Telecommunication Network and Services Operation and Maintenance Stage Department of Telecom Multi State/ Centre 21-Jun-2019
1347 Tata Communications 2013-14 Not Available 430.08 Communication Telecommunication Network and Services Operation and Maintenance Stage Department of Telecom Multi State/ Centre 21-Jun-2019
1348 Tata Communications 2014-15 Not Available 710.29 Communication Telecommunication Network and Services Operation and Maintenance Stage Department of Telecom Multi State/ Centre 21-Jun-2019
1349 Tata Communications 2015-16 Not Available 770.3 Communication Telecommunication Network and Services Operation and Maintenance Stage Department of Telecom Multi State/ Centre 21-Jun-2019
1350 Tata Communications 2016-17 Not Available 1463 Communication Telecommunication Network and Services Operation and Maintenance Stage Department of Telecom Multi State/ Centre 21-Jun-2019
1351 Tata Communications till 2011-12 Not Available 8805.93 Communication Telecommunication Network and Services Operation and Maintenance Stage Department of Telecom Multi State/ Centre 21-Jun-2019
1352 Telenor 2012-13 Not Available 4018 Communication Telecommunication Network and Services Operation and Maintenance Stage Department of Telecom Multi State/ Centre 21-Jun-2019
1353 Telenor 2013-14 Not Available 2198 Communication Telecommunication Network and Services Operation and Maintenance Stage Department of Telecom Multi State/ Centre 21-Jun-2019
1354 Telenor 2014-15 Not Available 1363 Communication Telecommunication Network and Services Operation and Maintenance Stage Department of Telecom Multi State/ Centre 21-Jun-2019
1355 Telenor 2015-16 Not Available 750 Communication Telecommunication Network and Services Operation and Maintenance Stage Department of Telecom Multi State/ Centre 21-Jun-2019
1356 Videocon Telecommunications 2012-13 Not Available 427 Communication Telecommunication Network and Services Operation and Maintenance Stage Department of Telecom Multi State/ Centre 21-Jun-2019
1357 Videocon Telecommunications 2013-14 Not Available 11 Communication Telecommunication Network and Services Operation and Maintenance Stage Department of Telecom Multi State/ Centre 21-Jun-2019
1358 Videocon Telecommunications 2014-15 Not Available 14 Communication Telecommunication Network and Services Operation and Maintenance Stage Department of Telecom Multi State/ Centre 21-Jun-2019
1359 Vodafone India Limited 2014-15 Not Available 14066 Communication Telecommunication Network and Services Operation and Maintenance Stage Department of Telecom Multi State/ Centre 21-Jun-2019
1360 Vodafone India Limited 2015-16 Not Available 34400 Communication Telecommunication Network and Services Operation and Maintenance Stage Department of Telecom Multi State/ Centre 21-Jun-2019
1361 Vodafone India Limited 2016-17 Not Available 12756 Communication Telecommunication Network and Services Operation and Maintenance Stage Department of Telecom Multi State/ Centre 21-Jun-2019
1362 Centralized Biomedical Waste treatment facility at Gazipur Not Available 6 Water Sanitation Solid waste management Operation and Maintenance Stage Government of National Capital Territory of Delhi Delhi (UT) 20-Jun-2019
1363 Green Field Super Speciality Hospital (Mohali) 200.0 Beds 178.82 Social and Commercial Infrastructure Health Care Operation and Maintenance Stage Punjab Health Systems Corporation Punjab 20-Jun-2019
1364 Construction of Karalphata Interchange road 5.0 KM (Kilometer) 531.13 Transport Roads and bridges Under Construction National Highways Authority of India (NHAI) Maharashtra 19-Jun-2019
1365 Design, construction , development, finance, O & M of NH-7 Madhya Pradesh on BOT (Annuity) basis 49.35 KM (Kilometer) 263.17 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Madhya Pradesh 19-Jun-2019
1366 Design, Construction, Development, Finance, O&M (Kumarpalyam,after Chengapali) on NH47 in the state of Tamil Nadu(BOT) basis 47.0 KM (Kilometer) 421 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Tamil Nadu 19-Jun-2019
1367 Design,Construction,Development,Finance,O&M,Jadcherla,end ofproposed Kotakata bypass,on NH7 Andhra Pradesh on (BOT) basis 55.42 KM (Kilometer) 373 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Andhra Pradesh 19-Jun-2019
1368 Ind-Barath Energies Thoothukudi Limited (IBETL) - Biomass based power plant 20.0 MW (Mega Watt) 74.7 Energy Renewable energy (grid) Operation and Maintenance Stage Not Available Tamil Nadu 19-Jun-2019
1369 Inter laning of Garakota-Rehli-Deori in length of 49.3 km in Sagar district 49.3 KM (Kilometer) 72.98 Transport Roads and bridges Operation and Maintenance Stage Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 19-Jun-2019
1370 Jegurupadu Combined Cycle Power Plant, Phase II 228.0 MW (Mega Watt) 725.16 Energy Electricity generation (grid) Operation and Maintenance Stage Not Available Andhra Pradesh 19-Jun-2019
1371 Konaseema Combined Cycle Power Plant 460.0 MW (Mega Watt) 2100 Energy Electricity transmission Operation and Maintenance Stage AP TRANSMISSION CORPORATION LIMITED Andhra Pradesh 19-Jun-2019
1372 Mathura (State Border) - Bharatpur 65.5 KM (Kilometer) 181.75 Transport Roads and bridges Operation and Maintenance Stage Public Works Department, Rajasthan Rajasthan 19-Jun-2019
1373 Operation & maintenance of Agra-Gwalior road of 137 Km 137.0 KM (Kilometer) 196 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Multi State/ Centre 19-Jun-2019
1374 Operation & Maintenance of Ayodhya-Gorakhpur section in length of 114.9 Km of NH-28 114.9 KM (Kilometer) 1292 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Uttar Pradesh 19-Jun-2019
1375 Operation and maintainance of Anabaru and Arasinagundi Power plants in Chitradurga and Davangere districts of karnataka 29.7 MW (Mega Watt) 210 Energy Electricity generation (grid) Operation and Maintenance Stage Not Available Karnataka 19-Jun-2019
1376 Raghu Rama Renewable Energy Limited (RRREL) 18.0 MW (Mega Watt) 57.2 Energy Electricity generation (grid) Operation and Maintenance Stage Not Available Tamil Nadu 19-Jun-2019
1377 Road (AP/Karnataka Border & Nandi Hill Crossing NH-7) Project 64.0 KM (Kilometer) 410 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Karnataka 19-Jun-2019
1378 Road Upgradation (Namakkal-Karur) Project 44.0 KM (Kilometer) 345 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Tamil Nadu 19-Jun-2019
1379 Road Upgradation Project (Bahari-Hanumana) Project 49.3 KM (Kilometer) 106.7 Transport Roads and bridges Operation and Maintenance Stage Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 19-Jun-2019
1380 Road Upgradation Project (Betul-Athner) Project 34.5 KM (Kilometer) 45.4 Transport Roads and bridges Operation and Maintenance Stage Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 19-Jun-2019
1381 Road Upgradation Project (Damoh-Patharia-Garhakota) Project 40.5 KM (Kilometer) 71.88 Transport Roads and bridges Operation and Maintenance Stage Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 19-Jun-2019
1382 Road Upgradation Project (Mandsaur-Pratapgarh-Rajasthan Border) Project 14.0 KM (Kilometer) 19.45 Transport Roads and bridges Operation and Maintenance Stage Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 19-Jun-2019
1383 Samal Hydro Electric Project 20.0 MW (Mega Watt) 116.47 Energy Renewable energy (grid) Operation and Maintenance Stage Not Available Odisha 19-Jun-2019
1384 Setting up of 12 MW co-generation power unit at sugar mill in Nawanshahr district 12.0 MW (Mega Watt) 60 Energy Renewable energy (grid) Operation and Maintenance Stage Punjab State Federation of Co-operative Sugar Mills Limited Punjab 19-Jun-2019
1385 Solar Power Plant, Mainawali minor of Norangdeshar of Hanumangarh Region 2.0 MW (Mega Watt) 26 Energy Renewable energy (grid) Operation and Maintenance Stage Rajasthan Renewable Energy Corporation Limited Rajasthan 19-Jun-2019
1386 TN Solar Power Energy Private Limited 23.0 MW (Mega Watt) 206 Energy Renewable energy (grid) Operation and Maintenance Stage Not Available Tamil Nadu 19-Jun-2019
1387 Tuppadahalli Energy India Private Limited_56MW Windfarm - Tuppadahalli onshore wind farm 56.1 MW (Mega Watt) 368.14 Energy Renewable energy (grid) Operation and Maintenance Stage Not Available Karnataka 19-Jun-2019
1388 Two laning of Tikamgarh - Mahrauni 15.7 KM (Kilometer) 29.38 Transport Roads and bridges Operation and Maintenance Stage Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 19-Jun-2019
1389 Ugradation of Beed - Mundi - Devala - Khutala - Attoot - NVDA road in length of 28.4 km in Bhopal 28.4 KM (Kilometer) 45.35 Transport Roads and bridges Operation and Maintenance Stage Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 19-Jun-2019
1390 Upgradation of Indore-Edalabad road in length of 203 km 203.0 KM (Kilometer) 124 Transport Roads and bridges Completed Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 19-Jun-2019
1391 Upgradation Operation and Maintenance of Kiratpursahib - Una Road 35.72 KM (Kilometer) 41.84 Transport Roads and bridges Operation and Maintenance Stage Public Works Department, Punjab Punjab 19-Jun-2019
1392 Vayu Urja Bharat Pvt. Ltd. 120.0 MW (Mega Watt) 299.07 Energy Renewable energy (grid) Operation and Maintenance Stage Andhra Pradesh Southern Power Distribution Company Limited Andhra Pradesh 19-Jun-2019
1393 Ahmednagar-Shirur Road 56.0 KM (Kilometer) 155.57 Transport Roads and bridges Operation and Maintenance Stage Public Works Department, Maharashtra Maharashtra 18-Jun-2019
1394 Chennai Bypass Road Project - Phase II 32.22 KM (Kilometer) 480 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Tamil Nadu 18-Jun-2019
1395 Construction of four lane connecting road at New Mangalore Port 37.0 KM (Kilometer) 168 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Karnataka 18-Jun-2019
1396 Dadupur Hydel Power Project 6.0 MW (Mega Watt) 49.92 Energy Renewable energy (grid) Operation and Maintenance Stage Uttar�Haryana Bijli�Vitran Nigam Limited Haryana 18-Jun-2019
1397 Municipal Garbage Processing Unit Not Available 15 Water Sanitation Solid waste management Operation and Maintenance Stage Department of Health, Chandigarh Chandigarh (UT) 18-Jun-2019
1398 Road Upgradation Project (Sonapipari-Umreth-Monari-Ambah) Project 22.25 KM (Kilometer) 43.73 Transport Roads and bridges Operation and Maintenance Stage Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 18-Jun-2019
1399 Upgradation Operation and Maintenance of Ferozepur - Fazilka Road 84.4 KM (Kilometer) 105.2 Transport Roads and bridges Operation and Maintenance Stage Public Works Department, Punjab Punjab 18-Jun-2019
1400 2- laning with paved shoulder of a Agra-Aligarh section of NH-93 Uttar Pradesh on (DBFOT) basis 79.0 KM (Kilometer) 250.5 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Uttar Pradesh 17-Jun-2019
1401 Construction of four lane connecting road at Cochin Port 256.71 KM (Kilometer) 193 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Kerala 17-Jun-2019
1402 Container Terminal (Kandla) Project 175000.0 TEU (Twenty-foot Equivalent Units) 200 Transport Ports (excluding captive) Operation and Maintenance Stage Deendayal Port Trust Gujarat 17-Jun-2019
1403 Crude Oil Handling for Kochi Refineries Ltd 13.5 MMTPA (million metric tonnes per annum) 703.34 Transport Ports (excluding captive) Operation and Maintenance Stage Cochin Port Trust Kerala 17-Jun-2019
1404 Design construction development, finance,O&M,(Kadtal) (Armur) on NH7 (NHDP-2) on (BOT) basis 31.0 KM (Kilometer) 272 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Telangana 17-Jun-2019
1405 Development of Exhibition cum Convention Centre at Sitapur Industrial Area, Jaipur 3.0 Acres 216.65 Social and Commercial Infrastructure Common infrastructure for industrial parks, SEZ Operation and Maintenance Stage Rajasthan State Industrial Development and Investment Corporation Limited Rajasthan 17-Jun-2019
1406 Lakhnadon to MP/MH Border Road Project (NS-I/BOT/MP-3) 57.0 KM (Kilometer) 408 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Madhya Pradesh 17-Jun-2019
1407 Nandigama-Vijayawada Road 35.0 KM (Kilometer) 760 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Andhra Pradesh 17-Jun-2019
1408 Operation & Maintenance of Swaroopganj-Pindwara &amp; Pindwara-Udaipur section in length of 120.0 Km 120.0 KM (Kilometer) 13 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Rajasthan 17-Jun-2019
1409 Road Upgradation (Delhi-Ramgarh-Alwar) Project 34.9 KM (Kilometer) 25.28 Transport Roads and bridges Operation and Maintenance Stage Public Works Department, Rajasthan Multi State/ Centre 17-Jun-2019
1410 Road Upgradation (Jhalawar-Indore) Project 20.2 KM (Kilometer) 7.15 Transport Roads and bridges Completed Public Works Department, Rajasthan Multi State/ Centre 17-Jun-2019
1411 Multilevel Parking (Sanjauli) Project 400.0 ECS Not Available Transport Urban public transport (except rolling stock) Operation and Maintenance Stage Shimla Municipal Corporation Himachal Pradesh 14-Jun-2019
1412 Multilevel Parking (Chotta Shimla) Project 250.0 ECS 20 Transport Urban public transport (except rolling stock) Operation and Maintenance Stage Shimla Municipal Corporation Himachal Pradesh 14-Jun-2019
1413 Useful Conversion of Solid Waste in Jaipur Not Available 20 Water Sanitation Solid waste management Operation and Maintenance Stage Jaipur Municipal Corporation Rajasthan 14-Jun-2019
1414 Construction, O and M of a new 2-lane road NH3 (Guna - bypass section) Madhya Pradesh 12.0 KM (Kilometer) 46 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Madhya Pradesh 13-Jun-2019
1415 Consulting services, O&M of 4-lane divided carriageway facility of Tuni -Ankapalli NH5 Andhra Pradesh on BOT basis 58.9 KM (Kilometer) 295 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Andhra Pradesh 07-Jun-2019
1416 Development of Datia-Dinara road in length of 8.9 km in Datia 8.93 KM (Kilometer) 16 Transport Roads and bridges Operation and Maintenance Stage Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 07-Jun-2019
1417 Development of Sausr-Mohgaon-Mordongri, Sonapipari-Umrethmonari-Umbah & Gadarwara-Tendukheda Roads 83.95 KM (Kilometer) 58.2 Transport Roads and bridges Operation and Maintenance Stage Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 07-Jun-2019
1418 Development of Ujjain - Simhastha bypass on BOT (Toll + Annuity) Basis 14.5 KM (Kilometer) 98.26 Transport Roads and bridges Operation and Maintenance Stage Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 07-Jun-2019
1419 Dewas-Ujjain-Badnagar-Badnawar Road Project 98.3 KM (Kilometer) 49.9 Transport Roads and bridges Operation and Maintenance Stage Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 07-Jun-2019
1420 Improvement, Including Strengthening and Widening of NH-3 Indore-Khalghat section, M.P. on BOT basis. 77.0 KM (Kilometer) 472 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Madhya Pradesh 07-Jun-2019
1421 Improvement,O&M and strengthening and widening of existing 2 to 4 lane NH1 Jalandhar-Amritsar section Punjab on BOT basis 49.0 KM (Kilometer) 263 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Punjab 07-Jun-2019
1422 Impvt,O&M,strengthening &amp;widening of existing 2 to 4 lane NH22 &amp;(ii )NH21 Ambala-Chandigarh,Haryana &amp;Punjab 35.0 KM (Kilometer) 298 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Multi State/ Centre 07-Jun-2019
1423 Paron-Goras Road (SH-23) 36.48 KM (Kilometer) 102 Transport Roads and bridges Operation and Maintenance Stage Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 07-Jun-2019
1424 Road Upgradation (AB Road-Magarkhedi-Bamari) Project 12.61 KM (Kilometer) 17.31 Transport Roads and bridges Operation and Maintenance Stage Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 07-Jun-2019
1425 Road Upgradation (Alirajpur-Jobat) Project 32.16 KM (Kilometer) 45.31 Transport Roads and bridges Operation and Maintenance Stage Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 07-Jun-2019
1426 Road Upgradation (Ankiya-Barkheda-Dongargaon-Nazirabad) Project 10.4 KM (Kilometer) 14.13 Transport Roads and bridges Operation and Maintenance Stage Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 07-Jun-2019
1427 Road Upgradation (Ashapur-Khalwa-Singhot) Project 42.0 KM (Kilometer) 56.9 Transport Roads and bridges Operation and Maintenance Stage Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 07-Jun-2019
1428 Road Upgradation (Babangaja-Pati-Bokrata) Project 33.31 KM (Kilometer) 46.87 Transport Roads and bridges Operation and Maintenance Stage Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 07-Jun-2019
1429 Road Upgradation (Chirawa-Singhana-Pacheri/Haryana Border) Project 44.8 KM (Kilometer) 44.55 Transport Roads and bridges Operation and Maintenance Stage Public Works Department, Rajasthan Rajasthan 07-Jun-2019
1430 Road Upgradation (Gwalior-Bhind up to UP Border) Project 108.0 KM (Kilometer) 314.5 Transport Roads and bridges Operation and Maintenance Stage Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 07-Jun-2019
1431 Road Upgradation (Khandela-Srimadhopur-Reengus-Khatushvaji) Project 50.93 KM (Kilometer) 43.26 Transport Roads and bridges Operation and Maintenance Stage Public Works Department, Rajasthan Rajasthan 07-Jun-2019
1432 Road Upgradation (Phoolsagar-Niwas Shalpura) Project 84.0 KM (Kilometer) 156.9 Transport Roads and bridges Operation and Maintenance Stage Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 07-Jun-2019
1433 Road Upgradation (Sheopur-Baroda-Khuwajapur) Project 32.29 KM (Kilometer) 61.8 Transport Roads and bridges Operation and Maintenance Stage Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 07-Jun-2019
1434 Road Upgradation (Tyonda-Ganjbasoda) Project 37.8 KM (Kilometer) 46.03 Transport Roads and bridges Operation and Maintenance Stage Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 07-Jun-2019
1435 Road Upgradation Project (Badwani-Palsood-Sendhawa) Project 56.9 KM (Kilometer) 103.99 Transport Roads and bridges Operation and Maintenance Stage Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 07-Jun-2019
1436 Road Upgradation Project (Gormi-Udotgarh) Project 16.77 KM (Kilometer) 37 Transport Roads and bridges Operation and Maintenance Stage Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 07-Jun-2019
1437 Road Upgradation Project (Panna-Amanganj-Semariya-Gaisabad) Project 58.2 KM (Kilometer) 97.13 Transport Roads and bridges Operation and Maintenance Stage Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 07-Jun-2019
1438 Road Upgradation Project (Semaria-Manikpur) Project 16.36 KM (Kilometer) 34.84 Transport Roads and bridges Operation and Maintenance Stage Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 07-Jun-2019
1439 Road Upgradation Project (Thandla-Limdi-Gujarat Border) Project 31.2 KM (Kilometer) 56.16 Transport Roads and bridges Operation and Maintenance Stage Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 07-Jun-2019
1440 Satna-Maihar-Umaria Road Project 242.7 KM (Kilometer) 53.3 Transport Roads and bridges Operation and Maintenance Stage Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 07-Jun-2019
1441 Second Vivekanand Bridge Tollway Project, Kolkata 6.0 KM (Kilometer) 642 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) West Bengal 07-Jun-2019
1442 Tambaram - Tindivanam Road 93.0 KM (Kilometer) 375 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Tamil Nadu 07-Jun-2019
1443 Upgradation of Nagda-Gogapur (Mahidpur) road in length of 15 km in Ujjain and Aurangabad 15.0 KM (Kilometer) 40.58 Transport Roads and bridges Operation and Maintenance Stage Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 07-Jun-2019
1444 Upgradation of Tikamgarh-Jatara-Palera-Nowgaon road in length of 76.4 km in Tikamgarh district 76.4 KM (Kilometer) 107.34 Transport Roads and bridges Operation and Maintenance Stage Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 07-Jun-2019
1445 Widening & Improvement of Dantiwara-Pipar City-Merta City road 26.5 KM (Kilometer) 219.94 Transport Roads and bridges Operation and Maintenance Stage Public Works Department, Rajasthan Rajasthan 07-Jun-2019
1446 Development of Dakha-Raikot-Barnala Phase 2 57.9 KM (Kilometer) 78.67 Transport Roads and bridges Operation and Maintenance Stage Public Works Department, Punjab Punjab 25-Apr-2019
1447 Four laning of Ropar-Chamkaur Sahib-Neelon-Doraha Road (Sirhind canal) upto NH-1 in length of 54.74 km in Punjab 54.75 KM (Kilometer) 240 Transport Roads and bridges Operation and Maintenance Stage Public Works Department, Chandigarh Punjab 25-Apr-2019
1448 Road Upgradation of Bhawanigarh-Nabha-Gobindgarh road in length of 55.4 Km in Fatehgarh Sahib district 55.4 KM (Kilometer) 70.25 Transport Roads and bridges Operation and Maintenance Stage Public Works Department, Punjab Punjab 25-Apr-2019
1449 Road Upgradation of Patiala-Nabha-Malerkotla Road under Punjab Road Sector of 55.8 km Phase 2 project 55.8 KM (Kilometer) 63.56 Transport Roads and bridges Operation and Maintenance Stage Public Works Department, Punjab Punjab 25-Apr-2019
1450 Upgradation Operation and Maintenance of Moga-Kotkapura Road 47.7 KM (Kilometer) 62.09 Transport Roads and bridges Operation and Maintenance Stage Public Works Department, Punjab Punjab 25-Apr-2019
1451 Dhaneta - Rakhi - Shahajpur 13.5 KM (Kilometer) 22 Transport Roads and bridges Operation and Maintenance Stage Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 17-Apr-2019
1452 Inter laning of Bamkhalfata-Dogawa-Borawa-Sarvardevla in length of 23.7 km 23.67 KM (Kilometer) 33.6 Transport Roads and bridges Operation and Maintenance Stage Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 17-Apr-2019
1453 Operation & maintenance of Badwah-Dhamnod road in length of 61.9 Km in Dhar district 61.93 KM (Kilometer) 71.31 Transport Roads and bridges Operation and Maintenance Stage Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 17-Apr-2019
1454 Road Upgradation (Dariyapur-Jasaondhi-Maharashtra Border) Project 16.0 KM (Kilometer) 21.2 Transport Roads and bridges Operation and Maintenance Stage Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 17-Apr-2019
1455 Road Upgradation (Intkhedi-Raslakhedi) Project 9.34 KM (Kilometer) 11.52 Transport Roads and bridges Operation and Maintenance Stage Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 17-Apr-2019
1456 Road Upgradation (Jaora-Piplodha-Jalandharkheda-Piploda Sailana) Project 42.27 KM (Kilometer) 60 Transport Roads and bridges Operation and Maintenance Stage Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 17-Apr-2019
1457 Road Upgradation (Kurawar-Eklera Talen) Project 39.22 KM (Kilometer) 49.89 Transport Roads and bridges Operation and Maintenance Stage Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 17-Apr-2019
1458 Road Upgradation (Lateri Anandpur-Bhagawantpur) Project 22.6 KM (Kilometer) 24.47 Transport Roads and bridges Operation and Maintenance Stage Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 17-Apr-2019
1459 Road Upgradation (Mangawan-Baikunthpur) Project 18.8 KM (Kilometer) 26.29 Transport Roads and bridges Operation and Maintenance Stage Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 17-Apr-2019
1460 Road Upgradation (Pondi-Maharajpur-Parasmaniya Road) Project 25.09 KM (Kilometer) 31.42 Transport Roads and bridges Operation and Maintenance Stage Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 17-Apr-2019
1461 Road upgradation of Waraseoni-Lalbarra Road in length of 18.30 km in Balaghat. 18.3 KM (Kilometer) 42.51 Transport Roads and bridges Operation and Maintenance Stage Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 17-Apr-2019
1462 Road Upgradation Project (Bijwad-Kusmaniya-Haran-Deepgaon) Project 75.62 KM (Kilometer) 109.01 Transport Roads and bridges Operation and Maintenance Stage Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 17-Apr-2019
1463 Road Upgradation Project (Datia-Bhander) Project 29.17 KM (Kilometer) 52.8 Transport Roads and bridges Operation and Maintenance Stage Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 17-Apr-2019
1464 Road Upgradation Project (Rehli-Gorjhamar) Project 18.08 KM (Kilometer) 28.27 Transport Roads and bridges Operation and Maintenance Stage Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 17-Apr-2019
1465 Road Upgradation Project (Salsalai-Gulana-Bolai Railway Station Road) Project 19.39 KM (Kilometer) 31.03 Transport Roads and bridges Operation and Maintenance Stage Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 17-Apr-2019
1466 Road Upgradation Project (Soyat-Pidawa) Project 6.25 KM (Kilometer) 8.8 Transport Roads and bridges Operation and Maintenance Stage Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 17-Apr-2019
1467 Upgradation of DevgulgarJod-Arandiyajod road in length of 35 km Shajapur district 35.0 KM (Kilometer) 57.83 Transport Roads and bridges Operation and Maintenance Stage Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 17-Apr-2019
1468 Upgradation of Javad-Khoh road in length of 21.0 km in Neemuch district 21.0 KM (Kilometer) 30.86 Transport Roads and bridges Operation and Maintenance Stage Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 17-Apr-2019
1469 Upgradation of Punasa - Mundi - Singhaji Road in length of 13.3 km. 13.3 KM (Kilometer) 24.5 Transport Roads and bridges Operation and Maintenance Stage Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 17-Apr-2019
1470 Development of metro link from Delhi Metro Sikanderpur to NH 8 Gurgaon 5.1 KM (Kilometer) 1088 Transport Urban public transport (except rolling stock) Operation and Maintenance Stage Haryana Urban Development Authority Haryana 11-Apr-2019
1471 Road Upgradation (Gurgaon-Faridabad-Ballabhgarh-Sohna) Project 66.2 KM (Kilometer) 779.12 Transport Roads and bridges Operation and Maintenance Stage Public Works Department, Haryana Haryana 11-Apr-2019
1472 Hospital (Fatehgarh Sahib) Project 60.0 Beds 5.25 Social and Commercial Infrastructure Health Care Operation and Maintenance Stage Punjab Health Systems Corporation Punjab 04-Apr-2019
1473 Implementation of 70 MLD sewage treatment plant in Jamnagar district 70.0 MLD (Millons Liter per day) 78 Water Sanitation Sewage collection, treatment and disposal system Operation and Maintenance Stage Jamnagar Municipal Corporation Gujarat 27-Mar-2019
1474 Bailkhedu - Saraoud 12.69 KM (Kilometer) 24 Transport Roads and bridges Operation and Maintenance Stage Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 19-Mar-2019
1475 Road Upgradation Project (Guna-Aron-Sironaj) Project 86.76 KM (Kilometer) 190.62 Transport Roads and bridges Operation and Maintenance Stage Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 19-Mar-2019
1476 Silwali-Sultanganj-Jaisingh Nagar Sagar 76.8 KM (Kilometer) 121 Transport Roads and bridges Operation and Maintenance Stage Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 19-Mar-2019
1477 Suraiya - Padariya - Dhamni - Singori 13.22 KM (Kilometer) 25 Transport Roads and bridges Operation and Maintenance Stage Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 19-Mar-2019
1478 Two laning of Satna-Majhgawan 74.132 KM (Kilometer) 121.78 Transport Roads and bridges Operation and Maintenance Stage Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 19-Mar-2019
1479 Kishangarh Gulabpura NH 79 Project ROB Not Available 16.66 Transport Roads and bridges Completed National Highways Authority of India (NHAI) Maharashtra 28-Jan-2019
1480 Ulundurpet - Padalur (Pkg - VI-B) 93.89 KM (Kilometer) 748 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Tamil Nadu 28-Jan-2019
1481 Karcham Wangtoo- Abdullapur Transmission Line 223.0 CKM (Circuit Kilo Meter) 1003 Energy Electricity transmission Operation and Maintenance Stage Power Grid Corpn. of India Ltd. Himachal Pradesh 20-Dec-2018
1482 225 MW combined cylce gas turbine power project in Uttarakhand 225.0 MW (Mega Watt) 1380 Energy Electricity generation (grid) Operation and Maintenance Stage Not Available Uttarakhand 17-Dec-2018
1483 Development of Polytechnic at Rahon Not Available 10 Social and Commercial Infrastructure Education Operation and Maintenance Stage Department of Technical Education and Industrial Training, Punjab Punjab 17-Dec-2018
1484 Implementation of 237 TPD solid waste management system at Haridwar 237.0 TPD (Tonne per day) 18.56 Water Sanitation Solid waste management Operation and Maintenance Stage Nagar Nigam Haridwar Uttarakhand 17-Dec-2018
1485 Road Upgradation (Jhansi-Lalitpur NS-1/UP-3) Project 49.7 KM (Kilometer) 355 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Uttar Pradesh 17-Dec-2018
1486 Two laning of Alwar-Sikandra section in length of 81.0 Km 81.0 KM (Kilometer) 128.1 Transport Roads and bridges Operation and Maintenance Stage Public Works Department, Rajasthan Rajasthan 17-Dec-2018
1487 Two laning of Jhalawar to Jhalawar road in length of 31 Km 31.0 KM (Kilometer) 79.73 Transport Roads and bridges Operation and Maintenance Stage Public Works Department, Rajasthan Rajasthan 17-Dec-2018
1488 Two laning of Lalsot-Kota section in length of 195.0 Km 195.0 KM (Kilometer) 303.7 Transport Roads and bridges Operation and Maintenance Stage Public Works Department, Rajasthan Rajasthan 17-Dec-2018
1489 Two laning of Phalodi-Ramji Ki Gol section in length of 292.0 Km 292.0 KM (Kilometer) 386.3 Transport Roads and bridges Operation and Maintenance Stage Public Works Department, Rajasthan Rajasthan 17-Dec-2018
1490 Widening of 2- 6 lanes divided carriageway including rehabilitation of 2 lanes Jaipur-Kishangarh section of NH8,Rajasthan 90.38 KM (Kilometer) 615 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Rajasthan 17-Dec-2018
1491 Women Polytechnic College (Dausa) Project 5.0 Acres 5.49 Social and Commercial Infrastructure Education Operation and Maintenance Stage Directorate of Technical Education, Rajasthan Rajasthan 17-Dec-2018
1492 Engineering College (Abu Road) Project 10.0 Acres 16.4 Social and Commercial Infrastructure Education Operation and Maintenance Stage Directorate of Technical Education, Rajasthan Rajasthan 13-Dec-2018
1493 Five Star Hotel at Guwahati 125.0 Rooms 31.08 Social and Commercial Infrastructure Tourism Operation and Maintenance Stage Government of Assam Assam 13-Dec-2018
1494 Gandhidham-Palanpur Railway Project 301.0 KM (Kilometer) 500 Transport Railway track, tunnel, viaducts, bridges Operation and Maintenance Stage Ministry of Railways Gujarat 13-Dec-2018
1495 Mega Food Park (Murshidabad) Project 82.0 Acres 132.71 Social and Commercial Infrastructure Common infrastructure for industrial parks, SEZ Operation and Maintenance Stage Ministry of Food Processing Industries West Bengal 13-Dec-2018
1496 Setting up of 110 MW Chuzachen hydel power unit in East Sikkim 110.0 MW (Mega Watt) 1188.57 Energy Renewable energy (grid) Operation and Maintenance Stage Sikkim Power Development Corporation Limited Sikkim 13-Dec-2018
1497 Technical & Engineering College (Kota Road) Project 10.0 Acres 16.4 Social and Commercial Infrastructure Education Operation and Maintenance Stage Directorate of Technical Education, Rajasthan Rajasthan 13-Dec-2018
1498 Women Polytechnic College (Jalore) Project 5.0 Acres 5.49 Social and Commercial Infrastructure Education Operation and Maintenance Stage Directorate of Technical Education, Rajasthan Rajasthan 13-Dec-2018
1499 Road Upgradation (Badwah-Katkut ) Project 24.0 KM (Kilometer) 35 Transport Roads and bridges Operation and Maintenance Stage Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 12-Dec-2018
1500 Sikka Jetty Not Available 87 Transport Ports (excluding captive) Operation and Maintenance Stage Gujarat Maritime Board (GMB) Gujarat 12-Dec-2018
1501 Two laning of Baran-Jhalawar section in length of 78.0 Km 78.0 KM (Kilometer) 111.7 Transport Roads and bridges Operation and Maintenance Stage Public Works Department, Rajasthan Rajasthan 12-Dec-2018
1502 Women Polytechnic College (Dholpur) Project 5.0 Acres 5.49 Social and Commercial Infrastructure Education Operation and Maintenance Stage Directorate of Technical Education, Rajasthan Rajasthan 12-Dec-2018
1503 Design Construction for improvement upgrading to four lanes finance operation and maintenance of Kadapa Pulivendula Road KP01 13.3 KM (Kilometer) 51.95 Transport Roads and bridges Operation and Maintenance Stage Andhra Pradesh Road Development Corporation Andhra Pradesh 10-Dec-2018
1504 Operation & Maintenance of Lalitpur-Sagar-Lakhnadon in length of 316.1 Km 316.1 KM (Kilometer) 30.46 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Madhya Pradesh 10-Dec-2018
1505 Road Upgradation (Kataphod-Nachalbor) Project 60.38 KM (Kilometer) 91 Transport Roads and bridges Operation and Maintenance Stage Madhya Pradesh Road Development Corporation Limited (MPRDC) Madhya Pradesh 10-Dec-2018
1506 Road Upgradation (Nasirabad-Mangliawas) Project 24.0 KM (Kilometer) 21.52 Transport Roads and bridges Operation and Maintenance Stage Public Works Department, Rajasthan Rajasthan 10-Dec-2018
1507 Road Upgradation (Pulivendula-Ambakapalli-Murarichintala) Project 1.0 KM (Kilometer) 26.5 Transport Roads and bridges Operation and Maintenance Stage Andhra Pradesh Road Development Corporation Andhra Pradesh 10-Dec-2018
1508 Road Upgradation (Pulivendula-Ramireddypalli-Palagiri) Project 1.0 KM (Kilometer) 36.6 Transport Roads and bridges Operation and Maintenance Stage Andhra Pradesh Road Development Corporation Andhra Pradesh 10-Dec-2018
1509 Upgradation of Deesa-Panthawada-Gudari road of 44.1 km 44.32 KM (Kilometer) 89 Transport Roads and bridges Operation and Maintenance Stage Gujarat State Road Development Corporation Limited (GSRDC) Gujarat 10-Dec-2018
1510 Design, Construction, Development, Finance, O&M NH-7 (Salem,Kumarpalyam) NH-47,Tamilnadu (BOT) basis 54.0 KM (Kilometer) 502 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Tamil Nadu 07-Dec-2018
1511 Design. Construction, Development, Finance,O&M,End of proposed Kotakatta bypass,NH-7 Andhra Pradesh,NHDP PH-2 ON BOT basis 75.5 KM (Kilometer) 745 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Multi State/ Centre 07-Dec-2018
1512 Kadloor Yellareddy - Kalkallu - Gundla Pochanpalli on NH - 7 103.0 KM (Kilometer) 546 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Andhra Pradesh 07-Dec-2018
1513 Operation & maintenance of Madurai-Kanyakumari road in length of 243.17 km on NH-7 243.1 KM (Kilometer) 2309 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Tamil Nadu 07-Dec-2018
1514 Tuni - Dharmavaram Road 47.0 KM (Kilometer) 231.9 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Andhra Pradesh 07-Dec-2018
1515 Upgradation of four lane Bhandara Road-Maharashtra-Chhattisgarh Border in length of 80 Km 80.0 KM (Kilometer) 528 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Maharashtra 07-Dec-2018
1516 Bay Park Project, Rushikonda, Visakhapatnam Not Available 38 Social and Commercial Infrastructure Tourism Operation and Maintenance Stage Not Available Andhra Pradesh 03-Dec-2018
1517 MSW Processing Plant at Khajod Not Available 50 Water Sanitation Solid waste management Operation and Maintenance Stage Surat Municipal Corporation Gujarat 03-Dec-2018
1518 4-Laning of Hungund - Hospet Section of NH-13 Karnataka on("DBFOT") basis under NHDP III 99.0 KM (Kilometer) 946 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Karnataka 30-Nov-2018
1519 6/8 Laning of Road port connectivity JNPT phase II 18.0 KM (Kilometer) 872 Transport Roads and bridges Under Construction National Highways Authority of India (NHAI) Maharashtra 30-Nov-2018
1520 Design, Engineering, Construction, Development, Finance, O & M, near Padailjr NH-45 Tamil Nadu on (BOT) Basis 93.8 KM (Kilometer) 747.56 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Tamil Nadu 30-Nov-2018
1521 Development of Punjab Institute of Medical Sciences, Jalandhar Not Available 250 Social and Commercial Infrastructure Health Care Operation and Maintenance Stage Directorate of Research and Medical Education, Punjab Punjab 30-Nov-2018
1522 Nellore bypass project, National Highway No. 5 17.1 KM (Kilometer) 389 Transport Roads and bridges Operation and Maintenance Stage National Highways Authority of India (NHAI) Andhra Pradesh 30-Nov-2018
1523 Raja Canal wastewater treatment plant 40.0 MLD (Millons Liter per day) 44.8 Water Sanitation Sewage collection, treatment and disposal system Operation and Maintenance Stage Not Available Karnataka 30-Nov-2018
1524 Savitri Mata Mandir Ropeway Project, Pushkar Not Available 9 Social and Commercial Infrastructure