Viability Gap Funding (VGF) Scheme

Viability Gap Funding (VGF) Scheme

This section contains list of PPP projects granted final approval by the Empowered Institution (EI)/Empowered Committee (EC)under the Scheme for Financial Support to PPPs in Infrastructure (VGF Scheme).
Export to Excel
Sr No. Project Name Location Sector Total Project Cost (In Rs. Crore) VGF Approved (in Rs. Crore) In Principle Approval Final Approval Implementing Authority
1 Improvement of Nagaur-Bikaner section of NH-89 Rajasthan Roads 378.0700 69.0000 06 Jan 2012 (37th EI) 07 Apr 2015 (64th EI) Public Works Department, Government of Rajasthan
2 Bulk Water Supply Project for IIT Bhubaneshwar, NISAR, INFO City and adjoining areas, Bhubaneshwar Odisha Water Supply & Sanitation 187.7100 37.5400 23 Jul 2013 (47th EI) 31 Jul 2015 (66th EI) Public Health Engineering Department, Odisha
Total 565.78 106.54