Sr No. Project Name Location Sector Total Project Cost (In Rs. Crore) Total VGF Approved (In Rs. Crore) VGF Approved by DEA CAPEX (In Rs. Crore) VGF Approved by DEA OPEX (In Rs. Crore) VGF Released till date by DEA for CAPEX (In Rs. Crore) VGF Approved by State CAPEX (In Rs. Crore) VGF Approved by State OPEX (In Rs. Crore) In Principle Meeting Date In Principle Meeting Number Final Approval Meeting Date Final Approval Meeting Number Implementing Authority Latest Status
1 Development of Gwalior Jhansi up to Ghonga village via Billua Road BOT (Toll) Madhya Pradesh Transport and Logistics 67.38 19.57 12.6 Not Applicable 12.60 6.97 Not Applicable 2016-12-0606.12.2016 (75th EI) 25.02.2020 (82nd EI) Madhya Pradesh Road Development Corporation Completed
2 Setting up of 50,000 MT modern food silo complex at Ujjain District Village Manpur Madhya Pradesh Social and Commercial Infrastructure 29.6 2.41 2.41 Not Applicable 1.71 Not Applicable Not Applicable 2013-10-0303.10.2013 (49th EI) 27.01.2015 (62nd EI) Madhya Pradesh Warehousing and Logistics Corporation Completed
3 Setting up of 50,000 MT modern food silo complex at Satna District Village Mohari Madhya Pradesh Social and Commercial Infrastructure 28.95 3.11 3.11 Not Applicable 2.52 Not Applicable Not Applicable 2013-10-0303.10.2013 (49th EI) 27.01.2015 (62nd EI) Madhya Pradesh Warehousing and Logistics Corporation Completed
4 Setting up of 50,000 MT modern food silo complex at Dewas District Village Durgapura Madhya Pradesh Social and Commercial Infrastructure 29.43 2.11 2.11 Not Applicable 1.64 Not Applicable Not Applicable 2013-10-0202.10.2013 (49th EI) 27.01.2015 (62nd EI) Madhya Pradesh Warehousing and Logistics Corporation Completed
5 Setting up of 50,000 MT modern food silo complex at Hoshangabad District Village Junheta Bankhedi Madhya Pradesh Social and Commercial Infrastructure 28.82 2.41 2.41 Not Applicable 2.03 Not Applicable Not Applicable 2013-10-0303.10.2013 (49th EI) 27.01.2015 (62nd EI) Madhya Pradesh Warehousing and Logistics Corporation Completed
6 Setting up of 50,000 MT modern food silo complex at Harda District Village Bhadawad Madhya Pradesh Social and Commercial Infrastructure 28.97 2.91 2.91 Not Applicable 2.48 Not Applicable Not Applicable 2013-10-0303.10.2013 (49th EI) 27.01.2015 (62nd EI) Madhya Pradesh Warehousing and Logistics Corporation Completed
7 Setting up of 50,000 MT modern food silo complex at Vidisha District Village Patheri Haveli Madhya Pradesh Social and Commercial Infrastructure 30.96 2.21 2.21 Not Applicable 1.79 Not Applicable Not Applicable 2013-10-0303.10.2013 (49th EI) 27.01.2015 (62nd EI) Madhya Pradesh Warehousing and Logistics Corporation Completed
8 Development of Four lane of Sidhi to Singrauli section (km 83/4 to km 195/8) of NH 75E on DBFOT (Toll) basis Madhya Pradesh Transport and Logistics 871.15 339.69 174.23 Not Applicable 135.02 165.46 Not Applicable 2011-07-2020.07.2011 (33rd EI) 29.10.2014 (21st EC) Madhya Pradesh Warehousing and Logistics Corporation Under Construction
9 Development of Four lane of Satna to Bela section (km 155/0 to km 203.04) of NH 75 on PPP basis following DBFOT (Toll) basis Madhya Pradesh Transport and Logistics 320.48 31.97 31.97 Not Applicable Not Applicable Not Applicable 2011-07-2020.07.2011 (33rd EI) 19.06.2014 (55th EI) Madhya Pradesh Road Development Corporation(MPRDC) Terminated
10 Development of Four lane of Mangwan to MP/UP border section (km 98/2 to km 46/6) of NH 27 on DBFOT (Toll) basis Madhya Pradesh Transport and Logistics 381.86 46.97 46.97 Not Applicable 46.97 Not Applicable Not Applicable 2011-07-2020.07.2011 (33rd EI) 19.06.2014 (55th EI) Madhya Pradesh Road Development Corporation(MPRDC) Completed
11 Two Laning of Bhopal - Berasia - Sironj Project (SH-23) on BoT basis Madhya Pradesh Transport and Logistics 175.6 24.55 24.55 Not Applicable 0 Not Applicable Not Applicable 2010-11-1919.11.2010 (27th EI) 19.06.2014 (55th EI) Madhya Pradesh Road Development Corporation(MPRDC) Terminated
12 Two laning with PSS of Guna-Ashoknagar-Ishagarh Project (SH 20) on BOT (toll) basis Madhya Pradesh Transport and Logistics 105.10 36.75 21.02 Not Applicable 21.02 Not Applicable Not Applicable 2010-11-1919.11.2010 (27th EI) 03.03.2014 (53rd EI) Madhya Pradesh Road Development Corporation(MPRDC) Completed
13 Development of 400 kV DCDS Sarni (Satpura)-Ashta transmission line project under DBFOT (Toll) Madhya Pradesh Energy 282.70 60.75 56.54 Not Applicable 56.54 Not Applicable Not Applicable 2012-06-1111.06.2012 (40th EI) 03.03.2014 (53rd EI) Madhya Pradesh Power Transmission Company Limited Completed
14 Two laning with granular shoulder from km 1/5 to km 51/4 in Seoni and km 51/4 to km 24/10 in Balaghat of Seoni-Katangi section of SH 54 on DBFOT (Toll) basis Madhya Pradesh Transport and Logistics 152.55 59.5 30.5 Not Applicable 14.98 29 Not Applicable 2011-07-2020.07.2011 (33rd EI) 18.12.2013 (51st EI) Madhya Pradesh Road Development Corporation(MPRDC) Terminated
15 Manawar-Singhan-Kukshi Madhya Pradesh Transport and Logistics 94.57 27.32 18.91 Not Applicable 18.90 8.41 Not Applicable 2011-12-0101.12.2011 (36th EI) 11.01.2013 (45th EI) Madhya Pradesh Road Development Corporation(MPRDC) Completed
16 Two laning of Rau-Mhow-Jamghat-Mandleshwar section of SH 38 in MP on BOT(Toll) Madhya Pradesh Transport and Logistics 176.06 66.33 35.21 Not Applicable 35.02 31.12 Not Applicable 2011-03-1616.03.2011 (29th EI) 25.09.2012 (42nd EI) Madhya Pradesh Road Development Corporation(MPRDC) Completed
17 Two laning of Jhabua-Jobat-Zeerpanya-Bagh-Kukshi section of SH 39 in MP on BOT(Toll) Madhya Pradesh Transport and Logistics 157.44 49 31.49 Not Applicable 30.85 17.51 Not Applicable 2011-03-1616.03.2011 (29th EI) 25.09.2012 (42nd EI) Madhya Pradesh Road Development Corporation(MPRDC) Completed
18 Two laning of Sarangpur-Akodia-Shujalpur section of SH 41 in MP on BOT (Toll) Madhya Pradesh Transport and Logistics 50 10 10 Not Applicable 6.47 Not Applicable Not Applicable 2011-03-1616.03.2011 (29th EI) 25.09.2012 (42nd EI) Madhya Pradesh Road Development Corporation(MPRDC) Terminated
19 Two laning of Khandwa-Dehtala-Burhanpur section of SH 50 in MP on BOT (Toll) Madhya Pradesh Transport and Logistics 227.08 66.36 45.41 Not Applicable 45.11 20.95 Not Applicable 2011-03-1616.03.2011 (29th EI) 25.09.2012 (42nd EI) Madhya Pradesh Road Development Corporation(MPRDC) Completed
20 Development of Satna-Chitrakoot (SH 11) Madhya Pradesh Transport and Logistics 121.78 24.36 24.36 Not Applicable 17.81 Not Applicable Not Applicable 2009-12-1414.12.2009 (20th EI) 20.07.2011 (33rd EI) Madhya Pradesh Road Development Corporation(MPRDC) Terminated
21 Bina-Khimalsa-Malthon Road Project Madhya Pradesh Transport and Logistics 69.11 13.82 13.82 Not Applicable 13.82 Not Applicable Not Applicable 2009-02-0202.02.2009 (16th EI) 28.09.2010 (26th EI) Madhya Pradesh Road Development Corporation(MPRDC) Completed
22 Bhind-Mihona-Gopalpur Road project Madhya Pradesh Transport and Logistics 82.89 16.58 16.58 Not Applicable 16.58 Not Applicable Not Applicable 2009-02-0202.02.2009 (16th EI) 30.09.2010 (26th EI) Madhya Pradesh Road Development Corporation(MPRDC) Completed
23 Damoh- Jabalpur Road Project Madhya Pradesh Transport and Logistics 212.13 42.43 42.43 Not Applicable 42.43 Not Applicable Not Applicable 2009-02-0202.02.2009 (16th EI) 30.09.2010 (26th EI) Madhya Pradesh Road Development Corporation(MPRDC) Completed
24 Sagar-Damoh Road Project Madhya Pradesh Transport and Logistics 116.50 23.30 23.30 Not Applicable 23.30 Not Applicable Not Applicable 2009-02-0202.02.2009 (16th EI) 30.09.2010 (26th EI) Madhya Pradesh Road Development Corporation(MPRDC) Completed
25 Four Laning of following State Highways in Madhya Pradesh : Bhopal, Devas Madhya Pradesh Transport and Logistics 426.64 81.00 81 Not Applicable 81 Not Applicable Not Applicable 2006-11-1414.11.2006 (7th EI) 05.03.2008 (12th EI) Madhya Pradesh Road Development Corporation(MPRDC) Completed
26 Strengthening of Mandsaur-Sitamau Road (Upto Rajasthan Border) State Highway in Madhya Pradesh Madhya Pradesh Transport and Logistics 25.25 25.25 5.05 Not Applicable 5.05 Not Applicable Not Applicable 2006-09-2121.09.2006 (5th EI) 05.03.2008 (12th EI) Madhya Pradesh Road Development Corporation(MPRDC) Completed
27 Strengthening of Matkuli-Tamia-Chindwara State Highways in Madhya Pradesh Madhya Pradesh Transport and Logistics 98.43 19.69 19.69 Not Applicable 19.66 Not Applicable Not Applicable 2006-09-2121.09.2006 (5th EI) 05.03.2008 (12th EI) Madhya Pradesh Road Development Corporation(MPRDC) Completed
28 Strengthening of Chandpur-Alirajpur-Kukshi-Badwani State Highways in Madhya Pradesh Madhya Pradesh Transport and Logistics 63.02 13.2 12.6 Not Applicable 12.54 Not Applicable Not Applicable 2006-09-2121.09.2006 (5th EI) 05.03.2008 (12th EI) Madhya Pradesh Road Development Corporation(MPRDC) Completed