This Report provides information on all infrastructure projects in the database across pre-defined set of parameters and following coverage criteria:
Export to Excel

Filters

Sr No. Project Name Sponsoring Authority Location Sector Total Project Cost (in Rs. Crore) PPPAC Meeting Date (Meeting Number) ApprovalStatus
1 Development of Dry Bulk Terminal at Tekra near Tuna on BOT basis Ministry of Shipping Gujarat Ports 1,140.82 15 Mar 2010 34th PPPAC Final approval
2 Two laning with paved shoulder of Tindivam Krishnagiri section of NH 66 from km 38.150 to km 214 in the state of Tamil Nadu Ministry of Road Transport and Highways Tamil Nadu Roads 828.26 15 Mar 2010 34th PPPAC Final approval
3 Four laning of Nagpur Saoner Pandhurna Betul section of NH 69 from km 3.000 to km 59.300 in the state of Maharashtra and km 137.000 to km 257.400 in the state of MP on BOT (Annuity) basis Ministry of Road Transport and Highways Maharashtra Roads 2,519.62 15 Mar 2010 34th PPPAC Final approval
4 Two laning with paved shoulder from Kozhikode - Muthanga section of NH 212 in Kerala Ministry of Road Transport and Highways Kerala Roads 365.23 22 Feb 2010 32th PPPAC Final approval
5 Six laning of NH7 from Hosur to Krishnagiri on NH93 in Tamil Nadu Ministry of Road Transport and Highways Tamil Nadu Roads 535.00 22 Feb 2010 32th PPPAC Final approval
6 Six laning of Dankuni - Baleshwar section of NH 6 in West Bengal Ministry of Road Transport and Highways West Bengal Roads 2,034.40 22 Feb 2010 32th PPPAC Final approval
7 Four laning of Chapra - Hazipur section on NH 19 in Bihar Ministry of Road Transport and Highways Bihar Roads 691.00 22 Feb 2010 32th PPPAC Final approval
8 Four laning of Bhubaneshwar - Puri section of NH 203 in Orissa Ministry of Road Transport and Highways Odisha Roads 500.29 22 Feb 2010 32th PPPAC Final approval
9 Four laning of Karnataka/Kerala border - Kannur section in Kerala Ministry of Road Transport and Highways Kerala Roads 1,157.16 22 Feb 2010 32th PPPAC Final approval
10 Four laning of Sambalpur Baragarh of Orissa/Chhatisgarh border section of NH 6 from Km 0 to Km 88 in Orissa Ministry of Road Transport and Highways Odisha Roads 909.00 22 Feb 2010 32th PPPAC Final approval
11 Two laning with paved shoulder of Dindigul - Theni and Theni - Kumili in Tamil Nadu under NHDP III Ministry of Road Transport and Highways Tamil Nadu Roads 501.00 22 Feb 2010 32th PPPAC Final approval
12 Four laning of Barhi to Hazaribagh section of NH 33 in Jharkhand Ministry of Road Transport and Highways Jharkhand Roads 414.00 22 Feb 2010 32th PPPAC Final approval
13 Four/Six lanning of Patna - Bakhtiyarpur section from Km 176.60 to Km 230 of NH 30 in the State of Bihar Ministry of Road Transport and Highways Bihar Roads 600.54 10 Feb 2010 31th PPPAC Final approval
14 Two laning with Pave shoulder from Varanasi to Gorakhpur section Km 2 to Km 208 of NH 29 in the State of UP Ministry of Road Transport and Highways Uttar Pradesh Roads 538.88 10 Feb 2010 31th PPPAC Final approval
15 Two laning with pave shoulder from Aligarh to Kanpur from Km 140.100 to Km 418.760 on NH 91 in the State of UP Ministry of Road Transport and Highways Uttar Pradesh Roads 723.25 10 Feb 2010 31th PPPAC Final approval
16 Two laning with pave shoulder from Bilaspur - Urdawal section Km 3116 to Km 312.400 of 4 on NH 200 Ministry of Road Transport and Highways Chhattisgarh Roads 494.00 10 Feb 2010 31th PPPAC Final approval
17 Two laning with pave shoulder on Raigarh - Saraipalli from 3.800 to Km 90.460 on NH 216 in the State of Chattisgarh Ministry of Road Transport and Highways Chhattisgarh Roads 189.19 10 Feb 2010 31th PPPAC Final approval
18 Two laning of Deali - Kota section of NH 12 on Kota bypass in Rajasthan Ministry of Road Transport and Highways Rajasthan Roads 593.38 10 Feb 2010 31th PPPAC Final approval
19 Development of Container Terminal at New Mangalore Port on BOT basis Ministry of Shipping Karnataka Ports 275.82 06 Jan 2010 30th PPPAC Final approval
20 Development of Multipurpose Berth to handle clean cargo including containers on BOT basis at Paradip Port Ministry of Shipping Odisha Ports 445.51 06 Jan 2010 30th PPPAC Final approval
21 Development of North Cargo Berth II for handling bulk cargo at Tuticorin Port on DBFOT basis Ministry of Shipping Tamil Nadu Ports 332.16 06 Jan 2010 30th PPPAC Final approval
22 Development of Mega Container at Chennai Port Ministry of Shipping Tamil Nadu Ports 3,125.00 06 Jan 2010 30th PPPAC Final approval
23 Srinagar to banihal section of NH 1A from km 187 to km 189.350, km 270.700 to km 286.110 and 187 to 220.700 on DBFOT (Annuity) in the State of Jammu and Kashmir Ministry of Road Transport and Highways Jammu and Kashmir Roads 1,166.00 16 Nov 2009 28th PPPAC Final approval
24 Mechanism of Coal Handling facilities and upgradation of General Cargo Berth at Outer Harbour of Visakhapatnam Port to cater 200,000 DWT vessels on DBFOT basis Ministry of Shipping Andhra Pradesh Ports 438.36 11 Nov 2009 29th PPPAC Final approval
25 development of Standalone container handling facility with a quay length of 300m towards North at Jahawar Lal Nehru Port Trust Ministry of Shipping Maharashtra Ports 600.08 11 Nov 2009 29th PPPAC Final approval
26 Development of Fourth Container Terminal at Jawahar Lal Nehru Port Trust Ministry of Shipping Maharashtra Ports 6,700.00 11 Nov 2009 29th PPPAC Final approval
27 Six laning of NH 4 from Tumkur to Chitradurga in Karnataka under NHDP Phase V on BOT (Toll) on DBFO pattern Ministry of Road Transport and Highways Karnataka Roads 839.00 16 Oct 2009 28th PPPAC Final approval
28 Four laning of Qazigund to Banihal Section of NH 1A from km 189.350 to km 204.700 including 2 tunnels of 0.69 km and km 8.45 length on BOT (Annuity) basis in the State of Jammu and Kashmir Ministry of Road Transport and Highways Jammu and Kashmir Roads 1,987.00 16 Oct 2009 28th PPPAC Final approval
29 Rehabilitation , strengthening and Four laning of Ramban to Banihal section of NH 1A from km 151 to km 187 on BOT (Annuity) basis on DBFO pattern in the state of Jammu and Kashmir Ministry of Road Transport and Highways Jammu and Kashmir Roads 986.00 16 Oct 2009 28th PPPAC Final approval
30 Rehabilitation, strengthening and Four laning of Udhampur to Ramban section of NH 1A from km 67 to km 89 & km 130 to km 151 in the state of JUammu and Kashmir Ministry of Road Transport and Highways Jammu and Kashmir Roads 971.00 16 Oct 2009 28th PPPAC Final approval
31 Four laning of Chenani to Nashri section of NH 1A from km 89 to km 130 including 9 km long tunnel with parallel escape tunnel on BOT (Annuity) basis of Jammu & Kashmir Ministry of Road Transport and Highways Jammu and Kashmir Roads 2,108.00 16 Oct 2009 28th PPPAC Final approval
32 Rehabilitation strengthening and 4 laning of Jammu-Udhampur section of NH 1A from Km 15 to km 67 on BOT (Annuity) basis on DBFO pattern in the State of Jammu & Kashmir Ministry of Road Transport and Highways Jammu and Kashmir Roads 1,939.00 16 Oct 2009 28th PPPAC Final approval
33 Six laning of Chenagapjalli to Start of Coimbatore bypass section 1 and four laning from end of Coimbatore bypass to TN/Kerala Boarder of NH 47 in the State of Tamil Nadu Ministry of Road Transport and Highways Tamil Nadu Roads 852.74 27 Jul 2009 26th PPPAC Final approval
34 Design, Engineering, Upgradation, Development, Finance, Operation and Maintenance of Hyderabad-Bangalore section of NH 7 in the state of 12 under NHDP Phase VII Ministry of Road Transport and Highways Karnataka Roads 747.30 27 Jul 2009 26th PPPAC Final approval
35 Design, Engineering, Finance, Construction, Operation and Maintenance of four laning of Bijapur-Hungund section of NH 13 from km 102 to km 202 in the State of Karnataka under NHDP Phase III through DBFOT basis Ministry of Road Transport and Highways Karnataka Roads 694.60 27 Jul 2009 26th PPPAC Final approval
36 Design, Engineering, Finance, Construction, Operation and Maintenance of four laning of Bijapur-Hungund section of NH 13 from km 202 to km 299 in the State of Karnataka under NHDP Phase III through DBFOT basis Ministry of Road Transport and Highways Karnataka Roads 1,226.37 27 Jul 2009 26th PPPAC Final approval
37 Four laning of Raiganj-Dalkhola section of NH 34 from km 398 to km 452.700 in the state of West Bangal on DBFOT basis under NHDP III Ministry of Road Transport and Highways West Bengal Roads 560.16 27 Jul 2009 26th PPPAC Final approval
38 Four laning of Baharampur-Farakka section of NH 34 from km 193 to km 295.700 in the state of West Bengal on DBFOT basis under NHDP III Ministry of Road Transport and Highways West Bengal Roads 1,006.53 27 Jul 2009 26th PPPAC Final approval
39 Four laning of Rohtak to Panipat section of NH 71A from km 0 to km 80.858 in the state of Haryana on BOT basis under NHDP III Ministry of Road Transport and Highways Haryana Roads 1,087.93 27 Jul 2009 26th PPPAC Final approval
40 Four/Six laning of Moradabad-Bareilly section of NH 24 from km 1+C28348 to km 262 in the state of Uttar Pradesh on DBFOT basis under NHDP III Ministry of Road Transport and Highways Uttar Pradesh Roads 1,484.93 27 Jul 2009 26th PPPAC Final approval
41 Four laning of Muzaffarnagar-Haridwar section of NH 58 from km 131 to 211 of NH 58 in the state of UP and Uttarakhand Ministry of Road Transport and Highways Multi State Roads 804.00 27 Jul 2009 26th PPPAC Final approval
42 Four laning of Farakka-Raiganj section of NH 34 from km 295 to km 398 in the State of West Bengal on DBFOT basis under NHDP III Ministry of Road Transport and Highways West Bengal Roads 1,056.56 27 Jul 2009 26th PPPAC Final approval
43 Four/Six laning of Maharashtra/Goa Border Km 475.040 to Panaji-Goa/Karnataka Border km 611 of section NH 17 in the state of Goa to be executed as BOT (Toll) on DBFO pattern under NHDP Phase III Ministry of Road Transport and Highways Goa Roads 2,078.00 09 Jul 2009 25th PPPAC Final approval
44 Six laning of Pune-Satara section of NH 4 from km 725 to km 865.35 in the State of Maharashtra under NHDP Phase V on BOT (Toll) basis on DBFO pattern Ministry of Road Transport and Highways Maharashtra Roads 1,724.55 09 Jul 2009 25th PPPAC Final approval
45 Six laning of Samakhiali-Gandhidham section of NH 8A from km 306 to km 362.16 in the State of Gujarat under NHDP Phase V on BOT (Toll) basis on DBFO pattern Ministry of Road Transport and Highways Gujarat Roads 805.39 09 Jul 2009 25th PPPAC Final approval
46 Four/Six laning of Gandhidham-Mundra Port section of NH8A in the State of Gujarat under NHDP Phase III on DBFOT pattern Ministry of Road Transport and Highways Gujarat Roads 1,031.14 09 Jul 2009 25th PPPAC Final approval
47 Four laning of Ahmedabad to Godhra section of NH 59 in the State of Gujarat under NHDP Phase III on DBFOT pattern Ministry of Road Transport and Highways Gujarat Roads 1,174.36 09 Jul 2009 25th PPPAC Final approval
48 Four laning of Godhara to Gujarat/MP border section of NH 59 in the State of Gujarat under NHDP Phase III on DBFOT pattern Ministry of Road Transport and Highways Gujarat Roads 855.55 09 Jul 2009 25th PPPAC Final approval
49 Four laning of Indore-Jhabua-Gujarat/MP border section of NH 59 in the state of Madhya Pradesh on BOT (Toll) basis under NHDP III Ministry of Road Transport and Highways Madhya Pradesh Roads 1,297.00 09 Jul 2009 25th PPPAC Final approval
50 Four laning of Rohtak to Bawal Section of NH 71 in the state of Haryana on DBFOT basis under NHDP III Ministry of Road Transport and Highways Haryana Roads 669.00 09 Jul 2009 25th PPPAC Final approval
51 Four laning of Haridwar-Dehradun Section of NH 58 & 72 in the state of Uttarakhand-BOT(Annuity) basis Ministry of Road Transport and Highways Uttarakhand Roads 490.00 09 Jul 2009 25th PPPAC Final approval
52 Four laning of Bareilly-Sitapur section of NH 24 in the State of Uttar Pradesh on BOT basis under NHDP III Ministry of Road Transport and Highways Uttar Pradesh Roads 1,046.00 09 Jul 2009 25th PPPAC Final approval
53 Four laning of Hyderabad-Yadgiri section of NH 202 in the State of Andhra Pradesh under NHDP Phase III on BOT basis Ministry of Road Transport and Highways Andhra Pradesh Roads 514.91 09 Jul 2009 25th PPPAC Final approval