Sr No. | Project Name | Sponsoring Authority | Location | Sector | Total Project Cost (in Rs. Crore) | PPPAC Meeting Date (Meeting Number) | ApprovalStatus |
---|---|---|---|---|---|---|---|
1 | Four Laning of Rimuli Roxy Rajamunda Section of NH 215 from Km 163 to Km 269 in the State of Orissa under NHDP Phase IIIA on BOT Basis. | Ministry of Road Transport and Highways | Odisha | Roads | 654.00 | 05 Nov 2007 13th PPPAC | Final approval |
2 | Design Construction, Finance, Operation and maintenance of Hyderabad-Vijayawada section including Design, Engineering Finance, Consttruction of additional Two Laning/future Six Laning of NH 9 in the State of Andhra Pradesh (km 40 to km 160) | Ministry of Road Transport and Highways | Andhra Pradesh | Roads | 968.00 | 05 Nov 2007 13th PPPAC | Final approval |
3 | Design Construction, Finance, Operation and maintenance of Hyderabad-Vijayawada section including Design, Engineering Finance, Construction of additional Two Laning/future Six Laning of NH 9 in the State of Andhra Pradesh (km 160 to km 221.5) | Ministry of Road Transport and Highways | Andhra Pradesh | Roads | 492.00 | 05 Nov 2007 13th PPPAC | Final approval |
4 | Four Laning of Jorabat-Barapani section from km. 0 to 61.800 of NH 40 in the state of Meghalaya under SARDP NE Phase A on BOT Annuity basis. | Ministry of Road Transport and Highways | Meghalaya | Roads | 536.00 | 05 Nov 2007 13th PPPAC | Final approval |
5 | Six Laning of Pimpalgaon-Nashik-Gonde section of NH-3 in the State of Maharashtra under NHDP Phase IIIA on BOT basis. | Ministry of Road Transport and Highways | Maharashtra | Roads | 752.47 | 05 Nov 2007 13th PPPAC | Final approval |
6 | Design Engineering, Construction, Development, Finance and Operation and maintenance of MP/Maharashtra Border Dhule section of NH 3 | Ministry of Road Transport and Highways | Maharashtra | Roads | 675.00 | 05 Nov 2007 13th PPPAC | Final approval |
7 | Design, Engineering, Construction, Finance and Maintenance of Jaipur Reengus section of NH 11 | Ministry of Road Transport and Highways | Rajasthan | Roads | 343.00 | 05 Nov 2007 13th PPPAC | Final approval |
8 | Six Laning of Surat-Dahisar Section of NH-8 (239 Km) in Gujarat and Maharashtra | Ministry of Road Transport and Highways | Maharashtra | Roads | 1,405.57 | 11 May 2007 10th PPPAC | Final approval |
9 | Six Laning of Panipat - Jalandhar Section of NH-1 (291 Km) in Haryana and Punjab. | Ministry of Road Transport and Highways | Punjab | Roads | 2,288.00 | 11 May 2007 10th PPPAC | Final approval |
10 | Six Laning of Chilkaluripet-Vijayawada, including Guntur bypass and Mangalagiri bypass of Chennai-Vijayawada Section of NH-5 in Andhra Pradesh. | Ministry of Road Transport and Highways | Andhra Pradesh | Roads | 572.30 | 11 May 2007 10th PPPAC | Final approval |
11 | Six Laning of Chennai-Tada Section of NH-5 (43 Km) in Tamil Nadu | Ministry of Road Transport and Highways | Tamil Nadu | Roads | 353.37 | 11 May 2007 10th PPPAC | Final approval |
12 | Six Laning of Gurgaon-Kotputli-Jaipur Section of NH-8 in Haryana/Rajasthan on BOT (Toll) basis following by DBFO pattern. | Ministry of Road Transport and Highways | Haryana | Roads | 1,673.70 | 11 May 2007 10th PPPAC | Final approval |
13 | Six Laning of Vadakkancherry to Thrissur Section (Package No.NS-2/BOT/KL-3 | Ministry of Road Transport and Highways | Kerala | Roads | 514.05 | 11 May 2007 10th PPPAC | Final approval |