This Report provides information on all infrastructure projects in the database across pre-defined set of parameters and following coverage criteria:
Export to Excel

Filters

Sr No. Project Name Sponsoring Authority Location Sector Total Project Cost (in Rs. Crore) PPPAC Meeting Date (Meeting Number) ApprovalStatus
1 Redevelopment of Gwalior, Nagpur, Amritsar and Sabarmati Railway stations on PPP mode Ministry of Railways Madhya Pradesh Railways 300.00 17 Dec 2019 91st PPPAC In-principle approval
2 Four laning of Guna to Biaora section of NH 3 from Km 332.100 to Km 426.100 in the state of Madhya Pradesh under NHDP phase IV Ministry of Road Transport and Highways Madhya Pradesh Roads 1,012.90 20 Mar 2015 71st PPPAC Final approval
3 Six laning of Indore-Dewas section of NH 3 from Km 577.55 to km 610.00 and Km 0.00 to Km 12.60 in the State of MP under NHDP V on BOT basis Ministry of Road Transport and Highways Madhya Pradesh Roads 410.00 21 Nov 2008 19th PPPAC Final approval
4 Four laning of Biora - Dewas section of NH-3 from Km 426.100 to Km 566.450 in the state of Madhya Pradesh under NHDP phase IV Ministry of Road Transport and Highways Madhya Pradesh Roads 1,583.79 20 Mar 2015 71st PPPAC Final approval
5 Two laning with paved shoulder of Jabalpur - Mandala - Chilpi section from km 3/4 to km 192.400 of NH-12A in the State of Madhya Pradesh on DBFOT basis under NHDP - IV Ministry of Road Transport and Highways Madhya Pradesh Roads 811.74 17 Jan 2014 62nd PPPAC Final approval
6 Two laning with paved shoulder from km 0.000 to km7.950 ( Katni Bypass) & km 4.600 to km 245.000 of Katni - Shahdol - Anooppur to MP/CG Border section on NH-78 in the State of Madhya Pradesh on DBFOT Ministry of Road Transport and Highways Madhya Pradesh Roads 811.47 26 Dec 2013 61st PPPAC Final approval
7 Four-laning of Rewa-Sidhi section of NH-75 E from km. 2.8 to km 83.4 in the State of Madhya Pradesh under NH (O) on DBFOT (Toll) basis Ministry of Road Transport and Highways Madhya Pradesh Roads 627.87 21 Dec 2012 56th PPPAC Final approval
8 Four-laning with PSS of Jabalpur-Bhopal section of NH-12 from km 10.400 to km 301.800 under NHDP Phase III on BOT (Toll) basis Ministry of Road Transport and Highways Madhya Pradesh Roads 2,485.96 28 Sep 2012 54th PPPAC Final approval
9 Two/ four laning of Obedullaganj -Shahganj Junction, Budhni- Betul Section of NH 69 under NHDP-IV, length 121.36 km Ministry of Road Transport and Highways Madhya Pradesh Roads 1,152.00 10 Aug 2011 45th PPPAC Final approval
10 Two laning of Chittorgarh-Neemach section of NH 79 and Nimbahera-Pratapgarh section of NH 113 under VGF Scheme, length 116.997 km Ministry of Road Transport and Highways Madhya Pradesh Roads 511.21 10 Aug 2011 45th PPPAC Final approval
11 Four laning of Mangwan to MP/UP border section of NH 27 under VGF Scheme, length 52.074 km Ministry of Road Transport and Highways Madhya Pradesh Roads 381.66 10 Aug 2011 45th PPPAC Final approval
12 Four laning of Sidhi to Singrauli section of NH 75E under VGF Scheme, length 102.60 km Ministry of Road Transport and Highways Madhya Pradesh Roads 871.15 10 Aug 2011 45th PPPAC Final approval
13 Four laning of Mangwan to Satna to Bela section of NH 75 under VGF Scheme, length 48.04 km Ministry of Road Transport and Highways Madhya Pradesh Roads 320.48 10 Aug 2011 45th PPPAC Final approval
14 Four laning of Bhopal to Biaora section of NH 12 under VGF scheme, length 105.60 km Ministry of Road Transport and Highways Madhya Pradesh Roads 704.26 20 Jun 2011 44th PPPAC Final approval
15 Four laning of Rewa to MP/UP Border of NH 7 under VGF scheme, length 89.30 km Ministry of Road Transport and Highways Madhya Pradesh Roads 670.82 20 Jun 2011 44th PPPAC Final approval
16 Four-laning of Jabalpur- Kanti- Rewa Section of NH-7 from km 242.30 to km 465.50 in the State of Madhya Pradesh under NHDP Phase IV on BOT (Toll) Ministry of Road Transport and Highways Madhya Pradesh Roads 1,906.83 19 Apr 2011 42nd PPPAC Final approval
17 Four laning of Jabalpur - Lakhandone section of NH7 from km 465.600 to km 546.425 in the State fo Madhaya Pradesh under NHDP Phase IVB on BOT (Too) basis Ministry of Road Transport and Highways Madhya Pradesh Roads 776.76 25 Jan 2011 41st PPPAC Final approval
18 Four laning of Gwalior - Shivpuri section of NH 3 from km 15.600 to NH 75 to km 236.000 in the State of Madhya Pradesh under NHDP Phase IV on BOT (Toll) basis. Ministry of Road Transport and Highways Madhya Pradesh Roads 1,059.00 25 Jan 2011 41st PPPAC Final approval
19 Four laning of Shivpuri - Dewas section of NH3 from km 15.623 to km 566.45 in the State of Madhya Pradesh under NHDP Phase IV on BOT (Toll) basis. Ministry of Road Transport and Highways Madhya Pradesh Roads 2,815.00 25 Jan 2011 41st PPPAC Final approval
20 Four laning of Indore-Jhabua-Gujarat/MP border section of NH 59 in the state of Madhya Pradesh on BOT (Toll) basis under NHDP III Ministry of Road Transport and Highways Madhya Pradesh Roads 1,297.00 09 Jul 2009 25th PPPAC Final approval
21 Four Laning of Khalghat-MP/ Maharashtra Border section of NH-3 from Km. 84.700 to Km.167.500 in the state of M.P. on BOT basis. Ministry of Road Transport and Highways Madhya Pradesh Roads 549.00 16 Jan 2007 8th PPPAC Final approval