Sr No. Project Name Sponsoring Authority Location Sector Sub Sector Total Project Cost (In Rs. Crore) PPPAC Meeting Date Meeting Number Recommended For
1 Six-lane Access Control Greenfield Capital Region Ring Road (Bhubaneswar Bypass) from Rameshwar to Tangi in the State of Odisha on HAM Ministry of Road Transport and Highways (MoRTH) Odisha Transport and Logistics Roads 0.00 04.02.2025 PDF icon120th PPPAC Final approval
2 4-laning of NH-167 from Gudebellur at Design Km.182+930 to Mahabubnagar at Design Km 262+940 of Hyderabad-Panaji section (length 80.01km) under NH(O) on HAM in the state of Telangana Ministry of Road Transport and Highways (MoRTH) Telangana Transport and Logistics Roads 2,394.68 30.09.2025 PDF icon134th PPPAC Final approval
3 4-laning of Jagtial (Km 0.000) to Karimnagar (Km 58.866) section of NH- 563, Armoor (Km 29.100) to Jagtial (Km 92.700) section of NH-63, and Jagtial (Km 92.700) to Mancherial (Km 160.995) section of NH-63 under NH (O) on HAM in the State of Telangana. Ministry of Road Transport and Highways (MoRTH) Telangana Transport and Logistics Roads 4,459.48 30.09.2025 PDF icon134th PPPAC Final approval
4 4-laning from Dhamasiya (Km132+32) to Bitada/Movi (Km 179+78) section of NH-56 (Pkg-IV) and 4-laning from Nasarpore (Km 208+90) to Malotha (Km 269+11) section of NH-56 (Pkg-VI) on HAM under NH(O) in the State of Gujarat. Ministry of Road Transport and Highways (MoRTH) Gujarat Transport and Logistics Roads 2,822.69 30.09.2025 PDF icon134th PPPAC Final approval
5 Construction of Access Controlled Highway of 4-Lane with Paved Shoulders from Ranganathpura (Hassan) to Keresooragondanahalli in Hassan Hiriyur section (EC-20) in Karnataka on HAM under NH (O). Ministry of Road Transport and Highways (MoRTH) Karnataka Transport and Logistics Roads 1,791.01 08.08.2025 PDF icon132nd PPPAC Final approval
6 4 laning of NH-167 from Gudebellur to Mahabubnagar of Hyderabad- Panaji section under NH(O) on HAM in the State of Telangana Ministry of Road Transport and Highways (MoRTH) Telangana Transport and Logistics Roads 2,574.34 08.08.2025 PDF icon132nd PPPAC Final approval
7 4 Laning of Rajapalayam to Shenkottai Section of NH-744 from Km 71+600 to Km 139+900 (Design Chainage) in Tamil Nadu on Hybrid Annuity Mode (Project Length-68.3Km) Ministry of Road Transport and Highways (MoRTH) Tamil Nadu Transport and Logistics Roads 0.00 29.04.2025 PDF icon122nd PPPAC Final approval
8 Development of 4-lane Access Controlled Marakkanam to Puducherry of NH332A in the State of Tamil Nadu under NH(O) on Hybrid Annuity Mode (Package - III). Ministry of Road Transport and Highways (MoRTH) Tamil Nadu Transport and Logistics Roads 2,157.09 10.05.2025 PDF icon126th PPPAC Final approval
9 Development of 4-lane Access Controlled Sirhind – Sehna section of NH205AG in the State of Punjab under NH(O) on Hybrid Annuity Mode (Package I & II) Ministry of Road Transport and Highways (MoRTH) Punjab Transport and Logistics Roads 5,082.10 10.05.2025 PDF icon126th PPPAC Final approval
10 Revalidation of the proposal, Development of 4-lane from Badvel to Nellore (Guruvindapudi Vilage on NH-16) in the State of Andhra Pradesh on Built Operate Transfer (BOT) Toll mode. Ministry of Road Transport and Highways (MoRTH) Andhra Pradesh Transport and Logistics Roads 2,841.38 17.05.2025 PDF icon127th PPPAC Final approval
11 Development of Multi Modal Logistics Parks MMLP at Pune Maharashtra Ministry of Road Transport and Highways (MoRTH) Maharashtra Transport and Logistics Roads 1,362.02 02.05.2025 PDF icon123rd PPPAC Final approval
12 Four-lane, Parmakudi to Ramanathapuram Section of NH-87 in the state of Tamil Nadu on HAM Ministry of Road Transport and Highways (MoRTH) Tamil Nadu Transport and Logistics Roads 1,853.16 29.04.2025 PDF icon122nd PPPAC Final approval
13 Six lane Acess Control Greenfield Capital Region Ring Road Bhubaneshwar Bypass from Rameshwar to Tangi in the state of Odisha on HAM Ministry of Road Transport and Highways (MoRTH) Odisha Transport and Logistics Roads 4,945.28 29.04.2025 PDF icon122nd PPPAC Final approval
14 Considering the revalidation of the revised cost of the Development, Maintenance and Management of the New NH-06 from Existing 61.8KM, Mawlyngkhung (Barapani Near Shillong in Meghalaya) to existing Km.197.40 New NH-06 (Panchgram in Assam) in the State of Meghalaya and Assam by 4-Laning with paved Shoulder on Hybrid Annuity Mode (HAM) Basis under Public-Private Partnership (PPP) Mode reg: - Ministry of Road Transport and Highways (MoRTH) Meghalaya Transport and Logistics Roads 22,863.93 21.02.2025 PDF icon121st PPPAC Final approval
15 Four-lane, Parmakudi to Ramanathapuram Section of NH-87 in the state of Tamil Nadu on HAM Ministry of Road Transport and Highways (MoRTH) Tamil Nadu Transport and Logistics Roads 32.09 04.02.2025 PDF icon120th PPPAC Final approval
16 Two-lane with Paved shoulder from Basnaghat (Morigaon) to Bhuragaon (in Darrang district) including new 2 lane Major Bridge over river Brahmaputra in the State of Assam on HAM Ministry of Road Transport and Highways (MoRTH) Assam Transport and Logistics Roads 0.00 04.02.2025 PDF icon120th PPPAC Final approval
17 Four-lane, Badvel to Nellore section of NH-67 in the state of Andhra Pradesh on HAM Ministry of Road Transport and Highways (MoRTH) Andhra Pradesh Transport and Logistics Roads 4,377.38 04.02.2025 PDF icon120th PPPAC Final approval
18 Four-lane STRR, NH948A - Obalapura to S.Mudugadapalli in Karnataka & Tamil Nadu on HAM. Ministry of Road Transport and Highways (MoRTH) Karnataka Transport and Logistics Roads 8,834.08 01.01.2025 PDF icon119th PPPAC Final approval
19 Six-lane Zirakpur Bypass in the state of Punjab & Haryana on Hybrid Annuity Mode Ministry of Road Transport and Highways (MoRTH) Punjab Transport and Logistics Roads 1,878.31 01.01.2025 PDF icon119th PPPAC Final approval
20 Ropeway project between Govindghat and Hemkund Sahib in the State of Uttarakhand on DBFOT model. Ministry of Road Transport and Highways (MoRTH) Uttarakhand Transport and Logistics Roads 2,589.04 01.01.2025 PDF icon119th PPPAC Final approval
21 Ropeway Project between Sonprayag and Kedarnath on Design, Build, Finance, Operate and Transfer (DBFOT) model Ministry of Road Transport and Highways (MoRTH) Uttarakhand Transport and Logistics Roads 0.00 03.12.2024 PDF icon118th PPPAC Final approval
22 Four-Lane Patna – Arrah - Sasaram Access Controlled Greenfield Corridor’ as a new National Highway NH-119A on Hybrid Annuity Model (HAM) Ministry of Road Transport and Highways (MoRTH) Bihar Transport and Logistics Roads 0.00 03.12.2024 PDF icon118th PPPAC Final approval
23 Six-Lane Greenfield Highway from Pagote to Chowk of NH 348B in Maharashtra on Built Operate Transfer (BOT) mode. Ministry of Road Transport and Highways (MoRTH) Maharashtra Transport and Logistics Roads 3,653.09 03.12.2024 PDF icon118th PPPAC Final approval
24 Greenfield Development, Maintenance and Management of a new alignment of National Highway-06 from Mawlyngkhung in Meghalaya (from 61.8 km on existing NH06) to Panchgram in Assam (to 197.4 km on the existing NH06) by 4 laning with paved shoulders. Ministry of Road Transport and Highways (MoRTH) Meghalaya Transport and Logistics Roads 24,804.82 09.11.2024 PDF icon117th PPPAC Final approval
25 Construction of Six lane access-controlled Greenfield Expressway from Km 0.000 to Km 213.803 (Tharad to Ahmedabad-Design length 213.803 km) in 6 packages under Bharatmala Pariyojana in the State of Gujarat on Hybrid Annuity Mode. Ministry of Road Transport and Highways (MoRTH) Gujarat Transport and Logistics Roads 10,578.97 02.03.2024 PDF icon115th PPPAC Final approval
26 Development of 8- Lane Elevated Flyover at Tier 1 on Single Pier including upgradation of Existing Road to 4/6 Lane with 2 Lane Service Road on both sides of Nashik Phata to Khed section of NH-60 in the state of Maharashtra under NH(O) Projects on Build, Operate and Transfer (BOT) Mode. Ministry of Road Transport and Highways (MoRTH) Maharashtra Transport and Logistics Roads 7,807.76 02.03.2024 PDF icon115th PPPAC Final approval
27 Development of 4-lane access-controlled Pathalgaon-Kunkuri-CG/JH border-Gumla-Bharda section as part of Raipur-Dhanbad Economic Corridor under Bharatmala Pariyojana in the state of Chhattisgarh and Jharkhand on HAM model Ministry of Road Transport and Highways (MoRTH) Jharkhand Transport and Logistics Roads 4,472.78 21.02.2024 PDF icon114th PPPAC Final approval
28 Development of 4 lane access-controlled Economic Corridor from Kharagpur to Moregram Section Km 0.000 to Km 230.957 of NH 116A divided into 5 packages in the state of West Bengal under Bharatmala Pariyojana on HAM model Ministry of Road Transport and Highways (MoRTH) West Bengal Transport and Logistics Roads 1,024.70 21.02.2024 PDF icon114th PPPAC Final approval
29 Development of 6 lane access-controlled Agra-Gwalior greenfield highway in the state of Uttar Pradesh, Rajasthan and Madhya Pradesh on BOT(Toll) Mode Ministry of Road Transport and Highways (MoRTH) Uttar Pradesh Transport and Logistics Roads 4,262.78 21.02.2024 PDF icon114th PPPAC Final approval
30 Construction of Guwahati Ring Road in the state of Assam on DBFOT (Toll) Ministry of Road Transport and Highways (MoRTH) Assam Transport and Logistics Roads 5,729.47 20.02.2024 PDF icon113th PPPAC Final approval
Logo of www.digitalindia.gov.in
Logo of www.digitalindia.gov.in
Logo of www.india.gov.in
Logo of www.meity.gov.in
Logo of www.pmindia.gov.in
Logo of amritmahotsav.nic.in
Logo of www.mygov.in
Logo of www.makeinindia.com