1 |
Construction of Sonnagar -Gomoh Section (263.705 Km) of Eastern Dedicated Freight Corridor on PPP basis |
Ministry of Railways |
Jharkhand |
Transport and Logistics |
Railway track including electrical & signalling system, tunnels, viaducts, bridges |
2,269.70 |
18.03.2021
|
101st PPPAC
|
Final approval |
2 |
Passenger Train Operations Project on PPP mode |
Ministry of Railways |
Multi State |
Transport and Logistics |
Railway track including electrical & signalling system, tunnels, viaducts, bridges |
30,099.00 |
29.10.2020
|
97th PPPAC
|
Final approval |
3 |
Development of Sonnagar-Gomoh Section (261.35 Km) of EDFC(Eastern Dedicated Freight Corridor) on Hybrid-DBFOT) model on PPP mode |
Ministry of Railways |
Multi State |
Transport and Logistics |
Railway track including electrical & signalling system, tunnels, viaducts, bridges |
9,751.00 |
13.12.2021
|
106th PPPAC
|
Final approval |
4 |
Redevelopment of New Delhi Railway Station & Development of Commercial Facilities on DBFOT basis under PPP mode to be undertaken by RLDA |
Ministry of Railways |
Delhi |
Transport and Logistics |
Railway track including electrical & signalling system, tunnels, viaducts, bridges |
4,425.00 |
03.07.2020
|
95th PPPAC
|
In-principle approval |
5 |
Redevelopment of Chhatrapati Shivaji Maharaj Terminus Railway Station on DBFOT basis on PPP mode to be undertaken by IRSDC |
Ministry of Railways |
Maharashtra |
Transport and Logistics |
Railway track including electrical & signalling system, tunnels, viaducts, bridges |
1,796.00 |
03.07.2020
|
95th PPPAC
|
In-principle approval |
6 |
Redevelopment and operation of Surat MMTH and Udhana railway station on PPP mode |
Ministry of Railways |
Gujarat |
Transport and Logistics |
Railway track including electrical & signalling system, tunnels, viaducts, bridges |
1,284.98 |
24.05.2021
|
103rd PPPAC
|
In-principle approval |
7 |
Passenger Train Operations Project on PPP mode |
Ministry of Railways |
Multi State |
Transport and Logistics |
Railway track including electrical & signalling system, tunnels, viaducts, bridges |
22,500.00 |
01.06.2020
|
92nd PPPAC
|
Final approval |
8 |
Redevelopment of Gwalior, Nagpur, Amritsar and Sabarmati Railway stations on PPP mode |
Ministry of Railways |
Madhya Pradesh |
Transport and Logistics |
Railway track including electrical & signalling system, tunnels, viaducts, bridges |
300.00 |
17.12.2019
|
91st PPPAC
|
In-principle approval |
9 |
Redevelopment of Nagpur Railway stations on PPP mode |
Ministry of Railways |
Maharashtra |
Transport and Logistics |
Railway track including electrical & signalling system, tunnels, viaducts, bridges |
465.00 |
17.12.2019
|
91st PPPAC
|
In-principle approval |
10 |
Redevelopment of Amritsar Railway stations on PPP mode |
Ministry of Railways |
Punjab |
Transport and Logistics |
Railway track including electrical & signalling system, tunnels, viaducts, bridges |
375.00 |
17.12.2019
|
91st PPPAC
|
In-principle approval |
11 |
Redevelopment of Sabarmati Railway stations on PPP mode |
Ministry of Railways |
Gujarat |
Transport and Logistics |
Railway track including electrical & signalling system, tunnels, viaducts, bridges |
156.00 |
17.12.2019
|
91st PPPAC
|
In-principle approval |
12 |
Redevelopment of New delhi Railway station |
Ministry of Railways |
Delhi |
Transport and Logistics |
Railway track including electrical & signalling system, tunnels, viaducts, bridges |
8,500.00 |
06.10.2008
|
17th PPPAC
|
In-principle approval |
13 |
Passenger Train Operations Project on PPP mode |
Ministry of Railways |
Across India |
Transport and Logistics |
Railway track including electrical & signalling system, tunnels, viaducts, bridges |
22,500.00 |
17.03.2020
|
93rd PPPAC
|
Final approval |
14 |
Passenger Train Operations Project on PPP mode |
Ministry of Railways |
Across India |
Transport and Logistics |
Railway track including electrical & signalling system, tunnels, viaducts, bridges |
30,099.00 |
14.06.2021
|
104th PPPAC
|
Final approval |