251 Six Laning of Vadakkancherry to Thrissur Section (Package No.NS-2/BOT/KL-3 Ministry of Road Transport and Highways Kerala Roads 514.05 11-05-2007
10th PPPAC (Opens New Window)
06-05-2016 Under Construction Final approval
252 Two laning with paved shoulder of Muzaffarpur Sanbarsa section of NH 77 in the State of Bihar Ministry of Road Transport and Highways Bihar Roads 511.54 28-04-2010
35th PPPAC (Opens New Window)
06-05-2016 Under Construction Final approval
253 Two laning of Chittorgarh-Neemach section of NH 79 and Nimbahera-Pratapgarh section of NH 113 under VGF Scheme, length 116.997 km Ministry of Road Transport and Highways Madhya Pradesh Roads 511.21 10-08-2011
45th PPPAC (Opens New Window)
13-04-2016 Operation and Maintenance Stage Final approval
254 Four-laning of Meerut, Bulandshahar section of NH-235 from km 7.469 to km 73.156 in the State of Uttar Pradesh under NHDP Phase IV B on DBFOT (Toll) basis: TPC ` 505.0 crore. Ministry of Road Transport and Highways Uttar Pradesh Roads 505.00 19-04-2011
42nd PPPAC (Opens New Window)
06-05-2016 Pre-construction Stage Final approval
255 Two laningof Bikaner to Suratgarh section on NH 11 under VGF Scheme, length 172.384 km Ministry of Road Transport and Highways Rajasthan Roads 501.08 10-08-2011
45th PPPAC (Opens New Window)
13-04-2016 Operation and Maintenance Stage Final approval
256 Two laning with paved shoulder of Dindigul - Theni and Theni - Kumili in Tamil Nadu under NHDP III  Ministry of Road Transport and Highways Tamil Nadu Roads 501.00 22-02-2010
32nd PPPAC (Opens New Window)
06-05-2016 Under Construction Final approval
257 Four laning of Bhubaneshwar - Puri section of NH 203 in Orissa  Ministry of Road Transport and Highways Odisha Roads 500.29 22-02-2010
32nd PPPAC (Opens New Window)
12-04-2016 Operation and Maintenance Stage Final approval
258 Two laning with pave shoulder from Bilaspur - Urdawal section Km 3116 to Km 312.400 of 4 on NH 200 Ministry of Road Transport and Highways Chhattisgarh Roads 494.00 10-02-2010
31st PPPAC (Opens New Window)
12-04-2016 - Final approval
259 Two laning with paved shoulders of Jhansi-Khajuraho section of NH 75 from km 1.900 to km 169.950 in the State of UP and MP under NHDP III on BOT (Toll) basis  Ministry of Road Transport and Highways Multiple State Roads 494.00 28-04-2010
35th PPPAC (Opens New Window)
06-05-2016 Pre-construction Stage Final approval
260 Design Construction, Finance, Operation and maintenance of Hyderabad-Vijayawada section including Design, Engineering Finance, Construction of additional Two Laning/future Six Laning of NH 9 in the State of Andhra Pradesh (km 160 to km 221.5) Ministry of Road Transport and Highways Andhra Pradesh Roads 492.00 05-11-2007
13th PPPAC (Opens New Window)
28-07-2016 Under Construction Final approval
261 Four laning of Armur-Adloor Yellareddy section of NH7 in the State of Andhra Pradesh Ministry of Road Transport and Highways Andhra Pradesh Roads 490.50 04-08-2008
16th PPPAC (Opens New Window)
06-05-2016 Operation and Maintenance Stage Final approval
262 Four laning of Haridwar-Dehradun Section of NH 58 & 72 in the state of Uttarakhand-BOT(Annuity) basis Ministry of Road Transport and Highways Uttrakhand Roads 490.00 09-07-2009
25th PPPAC (Opens New Window)
06-05-2016 Under Construction Final approval
263 Six/Four Laning of Delhi - Haryana Border to Rohtak Section of NH-10 from Km 29.70 to Km 87.00 including construction of Bahadurgarh and Rohtak Bypasses in Haryana under NHDP Phase IIIA Ministry of Road Transport and Highways Haryana Roads 486.00 11-10-2006
3rd PPPAC (Opens New Window)
06-05-2016 Under Construction Final approval
264 Four laning of Nagpur Wainganga Bridge Section of NH 6 from km 498 to km 544.200 in the State of Maharashtra under NHDP Phase III on BOT(Toll) basis  Ministry of Road Transport and Highways Maharashtra Roads 484.19 06-01-2011
40th PPPAC (Opens New Window)
06-05-2016 Operation and Maintenance Stage Final approval
265 Four laning of PSS of Sangrur - Punjab/Haryana border section of NH - 71 from km 181.805 (Sangrur) to km 238.695 (Punjab/Haryana border) in the State of Punjab on BOT (Toll) basis under NHDP - IV Ministry of Road Transport and Highways Punjab Roads 481.59 05-08-2013
59th PPPAC (Opens New Window)
30-08-2016 Operation and Maintenance Stage Final approval
266 Construction of new bridges and operation and maintenance of four-laned road of the Baleshwar-Kharagpur section of NH-60 from km 0.00 to km 119.30 on BOT (Toll) basis Ministry of Road Transport and Highways Bihar Roads 480.38 11-11-2011
47th PPPAC (Opens New Window)
06-05-2016 Operation and Maintenance Stage Final approval
267 Construction of Deep draught coal berth on BOT basis by Paradip Port Trust Ministry of Shipping Odisha Ports 479.01 23-10-2008
18th PPPAC (Opens New Window)
08-04-2016 Under Construction In-principle approval
268 Four laning of Ludhiana-Talwandi section of NH 95 from km 92 to km 170 in the State of Punjab under BOT (Toll) NHDP III on DBFOT  Ministry of Road Transport and Highways Punjab Roads 479.00 28-04-2010
35th PPPAC (Opens New Window)
06-05-2016 Under Construction Final approval
269 Development of the Assam -1 Housing Cluster on BOT (Annuity Basis)  Ministry of Home Affairs Assam Housing 476.67 21-06-2010
37th PPPAC (Opens New Window)
28-07-2016 - Final approval
270 Six laning (including Construction of additional 4 lane Bridge across River Narmada) of Vadodara-Surat Section of NH-8 from 192.000 to Km 198.000 in the State of Gujarat under NHDP Phase-V on BOT (Toll) basis. Ministry of Road Transport and Highways Gujarat Roads 473.24 09-03-2012
51st PPPAC (Opens New Window)
06-05-2016 Under Construction Final approval
271 Development of Multipurpose Berth to handle clean cargo including containers on BOT basis at Paradip Port Ministry of Shipping Odisha Ports 445.51 06-01-2010
30th PPPAC (Opens New Window)
12-04-2016 Under Construction Final approval
272 Four Laning of Nelamangala Junction on NH-4 with NH-48 to Devihalli in the state of Karnataka under NHDP phase III A on BOT basis Ministry of Road Transport and Highways Karnataka Roads 441.00 01-11-2006
4th PPPAC (Opens New Window)
06-05-2016 Operation and Maintenance Stage Final approval
273 Four Laning of Devilalli Hassan Section of NH- 48 in the state of Karnataka under NHDP phase III A on BOT basis Ministry of Road Transport and Highways Karnataka Roads 440.00 01-11-2006
4th PPPAC (Opens New Window)
06-05-2016 Operation and Maintenance Stage Final approval
274 Development of 13th to 16th Multipurpose Cargo (other than Liquid/Container) Berths at Kandla Port basis Ministry of Shipping Gujarat Ports 440.00 08-11-2006
5th PPPAC (Opens New Window)
28-07-2016 Under Construction In-principle approval
275 Two-laning with Paved Side Shoulders of Nagaur-Jodhpur section of NH-65 from km 166.26 to km 296.07 in the State of Rajasthan under NH (O) on DBFOT (Toll) basis. Ministry of Road Transport and Highways Rajasthan Roads 439.96 21-12-2012
56th PPPAC (Opens New Window)
30-08-2016 Under Construction Final approval
276 Four laning of Haryana/Punjab Border to Jind Section of NH-71 from Km 239.000 to Km 307.000 in the State of Haryana under NHDP Phase-III on BOT (Toll) basis. Ministry of Road Transport and Highways Haryana Roads 438.75 09-03-2012
51st PPPAC (Opens New Window)
06-05-2016 Completed Final approval
277 Mechanism of Coal Handling facilities and upgradation of General Cargo Berth at Outer Harbour of Visakhapatnam Port to cater 200,000 DWT vessels on DBFOT basis Ministry of Shipping Andhra Pradesh Ports 438.36 11-11-2009
29th PPPAC (Opens New Window)
31-08-2016 Operation and Maintenance Stage Final approval
278 Development of North Cargo Berth-III for handling bulk cargoes, Thermal Coal and Rock Phosphate, at V.O Chidambaranar Port on DBFOT basis Ministry of Shipping Tamil Nadu Ports 420.00 10-07-2012
52nd PPPAC (Opens New Window)
06-05-2016 Under Construction Final approval
279 Four laning of Barhi to Hazaribagh section of NH 33 in Jharkhand  Ministry of Road Transport and Highways Jharkhand Roads 414.00 22-02-2010
32nd PPPAC (Opens New Window)
06-05-2016 Operation and Maintenance Stage Final approval
280 Six laning of Indore-Dewas section of NH 3 from Km 577.55 to km 610.00 and Km 0.00 to Km 12.60 in the State of MP under NHDP V on BOT basis Ministry of Road Transport and Highways Madhya Pradesh Roads 410.00 21-11-2008
19th PPPAC (Opens New Window)
06-05-2016 Under Construction Final approval
281 Development of Eco-Tourism Resort in Lalaji Bay, Long Island, Andaman and Nicobar Islands through PPP mode Ministry of Horme Affairs Andaman and Nicobar Islands Tourism 391.00 27-08-2019
89th PPPAC (Opens New Window)
11-09-2019 - In-principle approval
282 Four laning of Goa/Karnataka border-Panaji, Goa stretch of NH 4A of Goa Ministry of Road Transport and Highways Goa Roads 382.46 04-08-2008
16th PPPAC (Opens New Window)
06-05-2016 Under Construction Final approval
283 Four laning of Mangwan to MP/UP border section of NH 27 under VGF Scheme, length 52.074 km Ministry of Road Transport and Highways Madhya Pradesh Roads 381.66 10-08-2011
45th PPPAC (Opens New Window)
13-04-2016 Under Construction Final approval
284 Construction of Access Controlled Highways from Km. 10/0 to Km. 29/5 of Bangolore section of NH-4 in the state of Karnataka on BOT basis Ministry of Road Transport and Highways Karnataka Roads 380.00 01-11-2006
4th PPPAC (Opens New Window)
06-05-2016 Operation and Maintenance Stage Final approval
285 Development of Ecor-Tourism Resort in Lalaji Bay, Long Island, Andaman and Nicobar Islands through PPP mode Ministry of Horme Affairs Andaman and Nicobar Islands Tourism 379.00 07-12-2018
84th PPPAC (Opens New Window)
19-02-2019 - In-principle approval
286 Two laning with paved shoulders of Nagaur-Bikaner section of NH-89 from km 171/00 to km 267/325 of NH 89 (including bypass at Nagaur from km 180/500 of NH-65 to km 171/00 of NH-89) in the state of Rajasthan under NH (Others) with implementation of the pro Ministry of Road Transport and Highways Rajasthan Roads 378.07 17-02-2012
50th PPPAC (Opens New Window)
06-05-2016 Under Construction Final approval
287 Two laning of Ajmer to Nagaur section on NH 89 under VGF Scheme, length 148.25 km Ministry of Road Transport and Highways Rajasthan Roads 377.15 10-08-2011
45th PPPAC (Opens New Window)
13-04-2016 Under Construction Final approval
288 Two laning with paved shoulder from Kozhikode - Muthanga section of NH 212 in Kerala  Ministry of Road Transport and Highways Kerala Roads 365.23 22-02-2010
32th PPPAC (Opens New Window)
28-07-2016 Final approval
289 Development of North Cargo Berth-IV for handling bulk cargoes, Thermal Coal and Copper Concentrate, at V.O Chidambaranar Port on DBFOT basis Ministry of Shipping Tamil Nadu Ports 355.00 10-07-2012
52nd PPPAC (Opens New Window)
06-05-2016 Under Construction Final approval
290 Six Laning of Chennai-Tada Section of NH-5 (43 Km) in Tamil Nadu Ministry of Road Transport and Highways Tamil Nadu Roads 353.37 11-05-2007
10th PPPAC (Opens New Window)
06-05-2016 Operation and Maintenance Stage Final approval
291 Design, Engineering, Construction, Finance and Maintenance of Jaipur Reengus section of NH 11 Ministry of Road Transport and Highways Rajasthan Roads 343.00 05-11-2007
13th PPPAC (Opens New Window)
31-08-2016 Operation and Maintenance Stage Final approval
292 Opeartion, Management and Development (OMD) of Multimodal Terminal (MMT) at Varanasi under PPP mode Ministry of Shipping Uttar Pradesh Housing 334.38 28-02-2019
86th PPPAC (Opens New Window)
28-02-2019 Final approval
293 Development of a Coal Terminal at Port of Mormugao, Goa on Design, Build, Finance, Operate and Transfer (DBFOT) Basis Ministry of Shipping Goa Ports 334.00 13-01-2009
22nd PPPAC (Opens New Window)
06-05-2016 Operation and Maintenance Stage Final approval
294 Four-laning with PSS of Jodhpur-Pali section of NH-65 (from km 308.0 to km 366.0) and Pali bypass starting from km 366.0of NH-65 to km 114 of NH-14 in the State of Rajasthan under NH (O) on DBFOT (Toll) basis Ministry of Road Transport and Highways Rajasthan Roads 332.70 16-07-2012
53rd PPPAC (Opens New Window)
06-05-2016 Operation and Maintenance Stage Final approval
295 Development of North Cargo Berth II for handling bulk cargo at Tuticorin Port on DBFOT basis Ministry of Shipping Tamil Nadu Ports 332.16 06-01-2010
30th PPPAC (Opens New Window)
12-04-2016 Under Construction Final approval
296 Development of the Assam -2 Housing Cluster on BOT (Annuity Basis)  Ministry of Home Affairs Assam Housing 329.19 21-06-2010
37th PPPAC (Opens New Window)
28-07-2016 - Final approval
297 Development of EQ 1 berth by replacement of the existing EQ1 and part of EQ2 berths in the north of the Inner Harbour of Vishakhapatnam Port Ministry of Shipping Andhra Pradesh Ports 323.18 17-08-2010
38th PPPAC (Opens New Window)
13-04-2016 Operation and Maintenance Stage Final approval
298 Four laning of Mangwan to  Satna to Bela section of NH 75 under VGF Scheme, length 48.04 km Ministry of Road Transport and Highways Madhya Pradesh Roads 320.48 10-08-2011
45th PPPAC (Opens New Window)
13-04-2016 Under Construction Final approval
299 Development of EQ 1A berth on south of EQ 1 berth for handling Thermal Coal and Steam Coal in the Inner Harbour of Vishakhapatnam Port Ministry of Shipping Andhra Pradesh Ports 313.39 17-08-2010
38th PPPAC (Opens New Window)
06-05-2016 Operation and Maintenance Stage Final approval
300 Four laning with paved shoulders of Sinnnar - Nashik Section of NH-50 (km 177 to 201.35 in the state of Maharashtra under National Highways (Others)  on BOT (Toll) Basis  Ministry of Road Transport and Highways Maharashtra Roads 312.96 13-12-2011
48th PPPAC (Opens New Window)
06-05-2016 Under Construction Final approval