20 Development of Four lane of Satna to Bela section (km 155/0 to km 203.04) of NH 75 on PPP basis following DBFOT (Toll) basis in the State of MP Madhya Pradesh Roads 320.48 31.97
(10%of TPC)
20-07-2011
(33rd EI) (Opens New Window)
19-06-2014
(55th EI) (Opens New Window)
18-05-2016 Terminated Madhya Pradesh Road Development Corporation(MPRDC)
21 Development of Four lane of Mangwan to MP/UP border section (km 98/2 to km 46/6) of NH 27 on DBFOT (Toll) basis Madhya Pradesh Roads 381.86 46.97
(12%of TPC)
20-07-2011
(33rd EI) (Opens New Window)
19-06-2014
(55th EI) (Opens New Window)
18-05-2016 Under Construction Madhya Pradesh Road Development Corporation(MPRDC)
22 Two lane with paved shoulders from Sikar to Bikaner and Bikaner Bypass of NH-11 under DBFOT basis Rajasthan Roads 650.84 130.17
(20%of TPC)
02-11-2011
(35th EI) (Opens New Window)
27-03-2014
(20th EC) (Opens New Window)
18-05-2016 Operation and Maintenance Stage Public Works Department, Government of Rajasthan
23 Four laning of Ara-Mohania Road Bihar Roads 917.12 183.40
(20%of TPC)
18-02-2009
(7th EC) (Opens New Window)
14-03-2014
(20th EC) (Opens New Window)
18-05-2016 Terminated Bihar State Road Development Corporation Limited
24 Two laning of Guna-Ashoknagar-Ishagarh Project (SH 20) on BOT basis Madhya Pradesh Roads 105.10 21.02
(20%of TPC)
19-11-2010
(27th EI) (Opens New Window)
03-03-2014
(53rd EI) (Opens New Window)
18-05-2016 Under Construction Madhya Pradesh Road Development Corporation(MPRDC)
25 Development of 400 kV DCDS Sarni (Satpura)-Ashta transmission line project under DBFOT (Toll) Madhya Pradesh Power 282.70 56.50
(20%of TPC)
11-06-2012
(40th EI) (Opens New Window)
03-03-2014
(53rd EI) (Opens New Window)
18-05-2016 Operation and Maintenance Stage Madhya Pradesh Power Transmission Company Limited
26 Four laning with paved shoulder Delhi-Saharanpur-Yamunotri Road upto Uttrakhand Boarder (SH 57) on DBFOT basis Uttar Pradesh Roads 1,718.35 343.53
(20%of TPC)
27-08-2012
(15th EC) (Opens New Window)
17-01-2014
(19th EC) (Opens New Window)
18-05-2016 Terminated Uttar Pradesh State Highways Authority
27 Four-laning of Varanasi-Shaktinagar road of SH-5A in UP under DBFOT basis Uttar Pradesh Roads 1,211.96 241.92
(20%of TPC)
27-08-2012
(15th EC) (Opens New Window)
17-01-2014
(19th EC) (Opens New Window)
18-05-2016 Operation and Maintenance Stage Uttar Pradesh State Highways Authority
28 Four laning with paved shoulder in Bareilly-Almora section of SH 37 in the State of Uttar Pradesh on DBFOT basis Uttar Pradesh Roads 355.00 69.95
(20%of TPC)
31-01-2011
(28th EI) (Opens New Window)
18-12-2013
(51st EI) (Opens New Window)
18-05-2016 Operation and Maintenance Stage Uttar Pradesh State Highways Authority
29 Two laning with granular shoulder from km 1/5 to km 51/4 in Seoni and km 51/4 to km 24/10 in Balaghat of Seoni-Katangi section of SH 54 on DBFOT (Toll) basis Madhya Pradesh Roads 152.55 30.50
(20%of TPC)
20-07-2011
(33rd EI) (Opens New Window)
18-12-2013
(51st EI) (Opens New Window)
18-05-2016 Terminated Madhya Pradesh Road Development Corporation(MPRDC)
30 Hyderabad Metro Rail Project Telangana Metro 12,132.00 1,458.00
(16% of TPC)
29-07-2010
(12th EC) (Opens New Window)
06-05-2013
(17th EC) (Opens New Window)
18-05-2016 Under Construction Hyderabad Metro Rail Limited
31 Manawar-Singhan-Kukshi Madhya Pradesh Roads 94.57 18.91
(20%of TPC)
01-12-2011
(36th EI) (Opens New Window)
11-01-2013
(45th EI) (Opens New Window)
18-05-2016 Operation and Maintenance Stage Madhya Pradesh Road Development Corporation(MPRDC)
32 Upgradation of Jaipur to Bhilwara State Highway, Rajasthan Rajasthan Roads 220.00 44.00
(20%of TPC)
02-07-2009
(18th EI) (Opens New Window)
13-12-2012
(44th EI) (Opens New Window)
06-05-2016 Operation and Maintenance Stage Rajasthan State Road Development and Construction Corporation Limited
33 Two laning of Rau-Mhow-Jamghat-Mandleshwar section of SH 38 in MP on BOT(Toll) Madhya Pradesh Roads 176.06 35.21
(20%of TPC)
16-03-2011
(29th EI) (Opens New Window)
25-09-2012
(42nd EI) (Opens New Window)
18-05-2016 Under Construction Madhya Pradesh Road Development Corporation(MPRDC)
34 Two laning of Jhabua-Jobat-Zeerpanya-Bagh-Kukshi section of SH 39 in MP on BOT(Toll) Madhya Pradesh Roads 157.44 31.49
(20%of TPC)
16-03-2011
(29th EI) (Opens New Window)
25-09-2012
(42nd EI) (Opens New Window)
18-05-2016 Operation and Maintenance Stage Madhya Pradesh Road Development Corporation(MPRDC)
35 Two laning of Sarangpur-Akodia-Shujalpur section of SH 41 in MP on BOT (Toll) Madhya Pradesh Roads 50.00 10.00
(20%of TPC)
16-03-2011
(29th EI) (Opens New Window)
25-09-2012
(42nd EI) (Opens New Window)
18-05-2016 Terminated Madhya Pradesh Road Development Corporation(MPRDC)
36 Two laning of Khandwa-Dehtala-Burhanpur section of SH 50 in MP on BOT (Toll) Madhya Pradesh Roads 227.08 45.41
(20%of TPC)
16-03-2011
(29th EI) (Opens New Window)
25-09-2012
(42nd EI) (Opens New Window)
18-05-2016 Operation and Maintenance Stage Madhya Pradesh Road Development Corporation(MPRDC)
37 Four laning of Hyderabad-Karimnagar-Ramagundam Road Project Andhra Pradesh Roads 1,358.19 271.64
(20%of TPC)
23-02-2010
(9th EC) (Opens New Window)
27-08-2012
(15th EC) (Opens New Window)
17-05-2016 Operation and Maintenance Stage Andhra Pradesh Road Development Corporation Limited
38 Four laning of Narketpally-Addanki-Medarametla Road Project Andhra Pradesh Roads 1,196.84 239.36
(20%of TPC)
18-02-2009
(16th EI) (Opens New Window)
27-08-2012
(15th EC) (Opens New Window)
06-05-2016 Operation and Maintenance Stage Andhra Pradesh Road Development Corporation Limited