Projects granted final approval under the Scheme for Financial Support to PPPs in Infrastructure (VGF Scheme) Projects granted final approval under the Scheme for Financial Support to PPPs in Infrastructure (VGF Scheme)

This section contains list of PPP projects granted final approval by the Empowered Institution (EI)/ Empowered Committee (EC) under the Scheme for Financial Support to PPPs in Infrastructure (VGF Scheme).

Search
S.No
1 Hyderabad Metro Rail Project Telangana Metro 12,132.00 1,458.00
(16% of TPC)
29-07-2010
(12th EC) (Opens New Window)
06-05-2013
(17th EC) (Opens New Window)
18-05-2016 Under Construction Hyderabad Metro Rail Limited
2 Hinjewadi to Shivajinagar Pune Metro Line-III Project Maharashtra Metro 7,420.31 1,224.80
16.5
07-03-2018
30 (Opens New Window)
08-11-2021
38 (Opens New Window)
01-04-2022 Under Construction PMRDA
3 Four laning with paved shoulder Delhi-Saharanpur-Yamunotri Road upto Uttrakhand Boarder (SH 57) on DBFOT basis Uttar Pradesh Roads 1,718.35 343.53
(20%of TPC)
27-08-2012
(15th EC) (Opens New Window)
17-01-2014
(19th EC) (Opens New Window)
18-05-2016 Terminated Uttar Pradesh State Highways Authority
4 Construction of green field bridge across river Ganga connecting Bakhtiyarpur Bihar Bridge 1,502.74 277.50
(18%of TPC)
23-02-2010
(9th EC) (Opens New Window)
27-08-2012
(15th EC) (Opens New Window)
18-05-2016 Operation and Maintenance Stage Bihar State Road Development Corporation Limited
5 Four laning of Hyderabad-Karimnagar-Ramagundam Road Project Andhra Pradesh Roads 1,358.19 271.64
(20%of TPC)
23-02-2010
(9th EC) (Opens New Window)
27-08-2012
(15th EC) (Opens New Window)
17-05-2016 Operation and Maintenance Stage Andhra Pradesh Road Development Corporation Limited
6 Four laning of Sambalpur - Rourkela section of SH-10 from km 4.900 to to km 167.900 (Rourkela) under DBFOT Odisha Roads 1,292.56 258.51
(20%of TPC)
12-12-2012
(16th EC) (Opens New Window)
29-10-2014
(21st EC) (Opens New Window)
18-05-2016 Under Construction Public Works Department, Government of Odisha
7 Four-laning of Varanasi-Shaktinagar road of SH-5A in UP under DBFOT basis Uttar Pradesh Roads 1,211.96 241.92
(20%of TPC)
27-08-2012
(15th EC) (Opens New Window)
17-01-2014
(19th EC) (Opens New Window)
18-05-2016 Operation and Maintenance Stage Uttar Pradesh State Highways Authority
8 Four laning of Narketpally-Addanki-Medarametla Road Project Andhra Pradesh Roads 1,196.84 239.36
(20%of TPC)
18-02-2009
(16th EI) (Opens New Window)
27-08-2012
(15th EC) (Opens New Window)
06-05-2016 Operation and Maintenance Stage Andhra Pradesh Road Development Corporation Limited
9 Four laning of Ara-Mohania Road Bihar Roads 917.12 183.40
(20%of TPC)
18-02-2009
(7th EC) (Opens New Window)
14-03-2014
(20th EC) (Opens New Window)
18-05-2016 Terminated Bihar State Road Development Corporation Limited
10 Development of Four lane of Sidhi to Singrauli section (km 83/4 to km 195/8) of NH 75E on DBFOT (Toll) basis Madhya Pradesh Roads 871.15 174.23
(20%of TPC)
20-07-2011
(33rd EI) (Opens New Window)
29-10-2014
(21st EC) (Opens New Window)
18-05-2016 Under Construction Madhya Pradesh Road Development Corporation(MPRDC)
11 4-laning of Muzaffarnagar - Saharanpur Road (SH-59) from Km.0.000 to Km.52.950 on Design, Build, Finance, Operate and Transfer (DBFOT) toll basis Uttar Pradesh Roads 752.88 150.58
(20%of TPC)
23-12-2014
(22nd EC) (Opens New Window)
03-01-2017
(28th EC) (Opens New Window)
13-06-2019 Operation and Maintenance Stage Uttar Pradesh State Highways Authority
12 Two lane with paved shoulders from Sikar to Bikaner and Bikaner Bypass of NH-11 under DBFOT basis Rajasthan Roads 650.84 130.17
(20%of TPC)
02-11-2011
(35th EI) (Opens New Window)
27-03-2014
(20th EC) (Opens New Window)
18-05-2016 Operation and Maintenance Stage Public Works Department, Government of Rajasthan
13 Construction of Bridge across river Godavari Andhra Pradesh Bridge 593.00 118.60
(20%of TPC)
05-03-2008
(12th EI) (Opens New Window)
02-07-2009
(18th EI) (Opens New Window)
06-05-2016 Operation and Maintenance Stage Andhra Pradesh Road Development Corporation Limited
14 Improvement of Karanji-Chandrapur Road section of MSH - 6 & 7 on DBFOT basis Maharashtra Roads 498.77 99.75
(20%of TPC)
14-12-2009
(20th EI) (Opens New Window)
11-06-2012
(40th EI) (Opens New Window)
18-05-2016 Under Construction Public Works Department, Government of Maharashtra
15 Jam Warora-Chandrapur-Ballarpur-Bamni Road project Maharashtra Roads 449.25 89.85
(20%of TPC)
02-02-2009
(16th EI) (Opens New Window)
06-03-2012
(38th EI) (Opens New Window)
06-05-2016 Operation and Maintenance Stage Public Works Department, Government of Maharashtra
16 Four Laning of following State Highways in Madhya Pradesh : Bhopal, Devas Madhya Pradesh Roads 426.64 81.00
(19%of TPC)
14-11-2006
(7th EI) (Opens New Window)
05-03-2008
(12th EI) (Opens New Window)
06-05-2016 Operation and Maintenance Stage Madhya Pradesh Road Development Corporation(MPRDC)
17 HVPNL 400 KV Jhajjar Power Transmission Project in Haryana on DBFOT basis Haryana Power 382.00 76.40
(20%of TPC)
04-03-2010
(22nd EI) (Opens New Window)
16-03-2011
(29th EI) (Opens New Window)
18-05-2016 Operation and Maintenance Stage Haryana Vidyut Prasaran Nigam Limited
18 Development of Four lane of Mangwan to MP/UP border section (km 98/2 to km 46/6) of NH 27 on DBFOT (Toll) basis Madhya Pradesh Roads 381.86 46.97
(12%of TPC)
20-07-2011
(33rd EI) (Opens New Window)
19-06-2014
(55th EI) (Opens New Window)
18-05-2016 Under Construction Madhya Pradesh Road Development Corporation(MPRDC)
19 Improvements of Road from Yelahanka to Karnataka/AP border Section of SH9 on DBFOT (Toll) basis Karnataka Roads 380.85 76.17
(20%of TPC)
09-04-2013
(46th EI) (Opens New Window)
16-05-2017
(77th EI) (Opens New Window)
Not Available Under Construction Karnataka Road Development Corporation Limited (KRDCL)
20 Improvement of Nagaur-Bikaner section of NH-89 Rajasthan Roads 378.07 69.00
(18%of TPC)
06-01-2012
(37th EI) (Opens New Window)
07-04-2015
(64th EI) (Opens New Window)
18-05-2016 Under Construction Public Works Department, Government of Rajasthan

Disclaimer : Status is being updated on receipt of information from project authorities