Project Details Project Details

Project Name
Implementation of rural electrification works in Nuapada under RGGVY-12th Plan*
Project Brief
The project involves augmentation of the existing 33/11 kV substation, construction of 11 kV outgoing bay, construction of new 11 kV line, LT lines and installation of distribution transformers in Nuapada district under Rajiv Gandhi Gramin Vidyutikaran Yojna (RGGVY) - 12th Plan.
Sector
Energy
Sub-Sector
Electricity transmission
Project Capacity
11.0 KV (Kilo Volt)
Location The geographical location of the project
Odisha
Project Status
Under Construction
Government/Non Government A government project pertains to project implemented either through traditional procurement mode or through PPP mode. A non-government project pertains to a project implemented solely by private sector.
Government
Any Other Information Any other relevant information for the project
Updated status for the project is not available.

Name Of Authority Name of the government agency that is the implementing authority for the project
Name Of Authority
NTPC Electric Supply Company Limited
Project Contractor Name of the concessionaire executing the project along with contact details such as name of the person, address, email, phone, fax, etc.
Name Of Contractor
Not Available
Project Timelines
Date Of Award Of Project The date on which the work order/notice to proceed was issued by the project authority to the developer
14-Nov-2015
Date Of Project Completion(Actual)
Not Applicable
Date Of Project Completion(as per Contract)
13-Nov-2017
Project Cost
Project Cost (as per Contract) in Rs Crore
107.86
Project Cost (Revised) in Rs Crore The project cost, if different from the cost as per original estimates
Not Available
Project Cost(Actual) in Rs Crore Actual cost of the project
Not Applicable