Project Details Project Details

Project Name
Upgradation of various roads in length of 35.4 km in Medak*
Project Brief
The project involves development of four lane ring road to Gajwel town from 0.0 km to 21.9 km in Medak district. It also includes upgradation of Gajwel-Chegunta road from 0.0 to 3.0 km, Gajwel-Doulatabad road from 0.0 km to 2.3 km, Vergal-Gajwel road from 11.0 km to 15.4 km, Gajwel bypass road and Gajwel-Venkatraopet road from 0.0 km to 1.8 km and 0.0 km to 2.0 km.
Sector
Transport
Sub-Sector
Roads and bridges
Project Capacity
35.4 KM (Kilometer)
Location The geographical location of the project
Telangana
Project Status
Under Construction
Government/Non Government A government project pertains to project implemented either through traditional procurement mode or through PPP mode. A non-government project pertains to a project implemented solely by private sector.
Government
Any Other Information Any other relevant information for the project
Updated status for the project is not available.

Name Of Authority Name of the government agency that is the implementing authority for the project
Name Of Authority
Roads and Buildings Department, Telangana
Project Contractor Name of the concessionaire executing the project along with contact details such as name of the person, address, email, phone, fax, etc.
Name Of Contractor
SLMI Infra Projects Private Limited
Project Timelines
Date Of Award Of Project The date on which the work order/notice to proceed was issued by the project authority to the developer
31-Dec-2016
Date Of Project Completion(Actual)
Not Applicable
Date Of Project Completion(as per Contract)
31-May-2018
Project Cost
Project Cost (as per Contract) in Rs Crore
223.35
Project Cost (Revised) in Rs Crore The project cost, if different from the cost as per original estimates
Not Available
Project Cost(Actual) in Rs Crore Actual cost of the project
Not Applicable
# - The project may have additional details that are pertinent. Kindly check the 'Any Other Information' field for further details.
* - Updated status for the project is not available.