Project Details Project Details

Project Name
Development of an IT park on 114 acres Ankhol & Bapod village in Vadodara
Project Brief
The project involves development of an IT park at Ankhol and Bapod village on Ajwa-Waghodia Crossing, NH 8 in Vadodara district.
Sector
Social and Commercial Infrastructure
Sub-Sector
Common infrastructure for industrial parks, SEZ
Project Capacity
114.0 Acres
Location The geographical location of the project
Gujarat
Project Status
Completed
Government/Non Government A government project pertains to project implemented either through traditional procurement mode or through PPP mode. A non-government project pertains to a project implemented solely by private sector.
Private Sector Infrastructure Projects
Any Other Information Any other relevant information for the project
As of February 2017, Phase I of the project was completed on 30-Nov-2012 and Phase II was underway. Revised projection completion date was 31-Aug-2018 (Source:- General Manager, Larsen & Toubro Limited).

Project Developer Name of the private player implementing the project
Name of Developer
Larsen & Toubro Limited
Project Timelines
Date Of Start Of Project The date on which the work order/notice to proceed was issued by the project authority to the developer
31-Oct-2010
Date Of Project Completion(Actual)
Not Available
Date Of Project Completion(as per Contract)
30-Jun-2011
Project Cost
Project Cost (as per Contract) in Rs Crore
600.00
Project Cost (Revised) in Rs Crore The project cost, if different from the cost as per original estimates
700.00
Project Cost(Actual) in Rs Crore Actual cost of the project
Not Available
# - The project may have additional details that are pertinent. Kindly check the 'Any Other Information' field for further details.
* - Updated status for the project is not available.