Project Details Project Details

Project Name
Implementation of 132/33 kV gas insulated substation at Chandabali in Bhadrak*
Project Brief
The project envisages implementation of 2x40 MVA, 132/33 kV gas insulated substation at Chandabali in Bhadrak district.
Sector
Energy
Sub-Sector
Electricity transmission
Project Capacity
132.0 KV (Kilo Volt)
Location The geographical location of the project
Odisha
Project Status
Pre-construction Stage
Government/Non Government A government project pertains to project implemented either through traditional procurement mode or through PPP mode. A non-government project pertains to a project implemented solely by private sector.
Government
Any Other Information Any other relevant information for the project
Updated status for the project is not available.

Name Of Authority Name of the government agency that is the implementing authority for the project
Name Of Authority
Odisha Power Transmission Corporation Limited
Project Contractor Name of the concessionaire executing the project along with contact details such as name of the person, address, email, phone, fax, etc.
Name Of Contractor
GE T&D India Limited
Project Timelines
Date Of Award Of Project The date on which the work order/notice to proceed was issued by the project authority to the developer
23-Jun-2016
Date Of Project Completion(Actual)
Not Applicable
Date Of Project Completion(as per Contract)
Not Available
Project Cost
Project Cost (as per Contract) in Rs Crore
52.65
Project Cost (Revised) in Rs Crore The project cost, if different from the cost as per original estimates
Not Available
Project Cost(Actual) in Rs Crore Actual cost of the project
Not Applicable
# - The project may have additional details that are pertinent. Kindly check the 'Any Other Information' field for further details.
* - Updated status for the project is not available.