Project Details Project Details

Project Name
Upgradation of Holenarasipura-K.R Nagara of SH-108,Hirisave-Chattahalli Road of SH-08 *
Project Brief
The project involves upgradation of Holenarasipura-K.R Nagara road of SH-108 from 0.0 km 17.6 km, Hirisave-Chattahalli road of SH-08 from 64.2 km to 94.2 km, Karegodu-Bidarakka MDR from 0.0 km to 12.0 km, Baragur-Doddabemmathi MDR from 0.0 km to 10.0 km, Moslehosalli-Bindaganvile MDR from 0.0 km to 18.0 km and Upparhosalli-Tyavihalli-Basthihalli MDR from 0.0 km to 12.5 km in Hassan district.
Sector
Transport
Sub-Sector
Roads and bridges
Project Capacity
100.1 KM (Kilometer)
Location The geographical location of the project
Karnataka
Project Status
Under Construction
Government/Non Government A government project pertains to project implemented either through traditional procurement mode or through PPP mode. A non-government project pertains to a project implemented solely by private sector.
Government
Any Other Information Any other relevant information for the project
Updated status for the project is not available.

Name Of Authority Name of the government agency that is the implementing authority for the project
Name Of Authority
Public Works, Ports and Inland Water Transport Department, Karnataka
Project Contractor Name of the concessionaire executing the project along with contact details such as name of the person, address, email, phone, fax, etc.
Name Of Contractor
Sri. Rayee Gowda
Project Timelines
Date Of Award Of Project The date on which the work order/notice to proceed was issued by the project authority to the developer
23-Jun-2016
Date Of Project Completion(Actual)
Not Applicable
Date Of Project Completion(as per Contract)
22-Sep-2017
Project Cost
Project Cost (as per Contract) in Rs Crore
50.00
Project Cost (Revised) in Rs Crore The project cost, if different from the cost as per original estimates
Not Available
Project Cost(Actual) in Rs Crore Actual cost of the project
Not Applicable
# - The project may have additional details that are pertinent. Kindly check the 'Any Other Information' field for further details.
* - Updated status for the project is not available.