Construction of 6 dams in 353.1 CBM under Upper Godavari Irrigation Project in Nashik,Ahmednagar & Aurangabad*
Project Brief
The project involves construction of six dams & it's canal in Dindori, Chandwad & Yeola taluka in Nashik district and Vaijapur taluka in Aurangabad district and Kopargaon taluka in Ahmednagar district to irrigate 74210 hector. Implementation of Daraswadi feeder canal of 88 km and Punegaon left bank canal.
Sector
Water Sanitation
Sub-Sector
Irrigation (dams, channels, embankments, etc.)
Project Capacity
353.1 CBM (Million Cubic Meter)
Location The geographical location of the project
Maharashtra
Project Status
Under Construction
Government/Non Government A government project pertains to project implemented either through traditional procurement mode or through PPP mode. A non-government project pertains to a project implemented solely by private sector.
Government
Any Other Information Any other relevant information for the project
Updated status for the project is not available.

Name Of Authority Name of the government agency that is the implementing authority for the project
Name Of Authority
Godavari Marathwada Irrigation Development Corporation Limited
Project Contractor Name of the concessionaire executing the project along with contact details such as name of the person, address, email, phone, fax, etc.
Name Of Contractor
Ketan Constructions Limited-Tacon Infrastructure Private Limited (JV)
Project Timelines
Date Of Award Of Project The date on which the work order/notice to proceed was issued by the project authority to the developer
01-Apr-1997
Date Of Project Completion(Actual)
Not Applicable
Date Of Project Completion(as per Contract)
31-Mar-2002
Project Cost
Project Cost (as per Contract) in Rs Crore
439.12
Project Cost (Revised) in Rs Crore The project cost, if different from the cost as per original estimates
1,016.08
Project Cost(Actual) in Rs Crore Actual cost of the project
Not Applicable