Project Details Project Details

Project Name
Water Supply Scheme (Tumkuru)*
Project Brief
The project envisages implementation of continuous pressurized water supply scheme. It includes implementation of 50 MLD water treatment plant and laying of pipeline to Tumkuru city under Urban infrastructure Development Scheme for Small & Medium Towns (UIDSSMT).
Sector
Water Sanitation
Sub-Sector
Water supply pipeline
Project Capacity
560.0 KM (Kilometer)
Location The geographical location of the project
Karnataka
Project Status
Pre-construction Stage
Government/Non Government A government project pertains to project implemented either through traditional procurement mode or through PPP mode. A non-government project pertains to a project implemented solely by private sector.
Government
Any Other Information Any other relevant information for the project
Updated status for the project is not available.

Name Of Authority Name of the government agency that is the implementing authority for the project
Name Of Authority
Karnataka Urban Water Supply and Drainage Board
Project Contractor Name of the concessionaire executing the project along with contact details such as name of the person, address, email, phone, fax, etc.
Name Of Contractor
Larsen & Toubro Limited
Project Timelines
Date Of Award Of Project The date on which the work order/notice to proceed was issued by the project authority to the developer
01-Aug-2016
Date Of Project Completion(Actual)
Not Applicable
Date Of Project Completion(as per Contract)
Not Available
Project Cost
Project Cost (as per Contract) in Rs Crore
127.51
Project Cost (Revised) in Rs Crore The project cost, if different from the cost as per original estimates
Not Available
Project Cost(Actual) in Rs Crore Actual cost of the project
Not Applicable