Project Details Project Details

Project Name
Sewage Treatment Plant (Kadugodi & Chikkabanavara) *
Project Brief
The project involves implementation of sewage treatment plant at Kadugodi and Chikkabanavara in Bangalore district.
Sector
Water Sanitation
Sub-Sector
Sewage collection, treatment and disposal system
Project Capacity
11.0 MMSCMD (Million Metric Standard Cubic Meter Per Day)
Location The geographical location of the project
Karnataka
Project Status
Under Construction
Government/Non Government A government project pertains to project implemented either through traditional procurement mode or through PPP mode. A non-government project pertains to a project implemented solely by private sector.
Government
Any Other Information Any other relevant information for the project
Updated status for the project is not available.

Name Of Authority Name of the government agency that is the implementing authority for the project
Name Of Authority
Bangalore Water Supply and Sewerage Board
Project Contractor Name of the concessionaire executing the project along with contact details such as name of the person, address, email, phone, fax, etc.
Name Of Contractor
Degremont S.A. France-Degremont India Limited (JV)
Project Timelines
Date Of Award Of Project The date on which the work order/notice to proceed was issued by the project authority to the developer
10-Mar-2014
Date Of Project Completion(Actual)
Not Applicable
Date Of Project Completion(as per Contract)
09-Mar-2016
Project Cost
Project Cost (as per Contract) in Rs Crore
95.58
Project Cost (Revised) in Rs Crore The project cost, if different from the cost as per original estimates
98.00
Project Cost(Actual) in Rs Crore Actual cost of the project
Not Applicable
# - The project may have additional details that are pertinent. Kindly check the 'Any Other Information' field for further details.
* - Updated status for the project is not available.