Project Details Project Details

Project Name
Flyover (Kummaripalem-Rajiv Gandhi Park) Project*
Project Brief
The project involves construction of six lane flyover near Kanaka Durga temple from Kummaripalem to Rajiv Gandhi Park near the Vijayawada Municipal Corpn. office in Krishna district.
Sector
Transport
Sub-Sector
Roads and bridges
Project Capacity
2.5 KM (Kilometer)
Location The geographical location of the project
Andhra Pradesh
Project Status
Under Construction
Government/Non Government A government project pertains to project implemented either through traditional procurement mode or through PPP mode. A non-government project pertains to a project implemented solely by private sector.
Government
Any Other Information Any other relevant information for the project
Updated status for the project is not available.

Name Of Authority Name of the government agency that is the implementing authority for the project
Name Of Authority
Ministry of Road Transport and Highways
Project Contractor Name of the concessionaire executing the project along with contact details such as name of the person, address, email, phone, fax, etc.
Name Of Contractor
Soma Enterprise Limited
Project Timelines
Date Of Award Of Project The date on which the work order/notice to proceed was issued by the project authority to the developer
06-Feb-2016
Date Of Project Completion(Actual)
Not Applicable
Date Of Project Completion(as per Contract)
31-Jan-2017
Project Cost
Project Cost (as per Contract) in Rs Crore
447.00
Project Cost (Revised) in Rs Crore The project cost, if different from the cost as per original estimates
Not Available
Project Cost(Actual) in Rs Crore Actual cost of the project
Not Applicable
# - The project may have additional details that are pertinent. Kindly check the 'Any Other Information' field for further details.
* - Updated status for the project is not available.