Project Details Project Details

Project Name
Implementation of Hetawane medium irrigation project of 144.5 MLD at Pen
Project Brief
The project involves implementation of Hetawane medium irrigation project at Pen Taluka in Raigad district
Sector
Water Sanitation
Sub-Sector
Irrigation (dams, channels, embankments, etc.)
Project Capacity
144.5 MLD (Millons Liter per day)
Location The geographical location of the project
Maharashtra
Project Status
Under Construction
Government/Non Government A government project pertains to project implemented either through traditional procurement mode or through PPP mode. A non-government project pertains to a project implemented solely by private sector.
Government
Any Other Information Any other relevant information for the project
The project work has been delayed due to land acquisition & funds problem. Cost of the project was increased due to following reasons: 1) Change in DSR (District Schedule of Rate) and RSR (Regional Schedule of Rate). 2) Change in design 3) Increase in cost of land, as per Land Acquisition Act (Source :- Sectional Engineer, Konkan Irrigation Development Corporation

Name Of Authority Name of the government agency that is the implementing authority for the project
Name Of Authority
Konkan Irrigation Development Corporation
Project Contractor Name of the concessionaire executing the project along with contact details such as name of the person, address, email, phone, fax, etc.
Name Of Contractor
E. M. Brother
Project Timelines
Date Of Award Of Project The date on which the work order/notice to proceed was issued by the project authority to the developer
31-May-1985
Date Of Project Completion(Actual)
Not Applicable
Date Of Project Completion(as per Contract)
31-May-1990
Project Cost
Project Cost (as per Contract) in Rs Crore
15.36
Project Cost (Revised) in Rs Crore The project cost, if different from the cost as per original estimates
362.68
Project Cost(Actual) in Rs Crore Actual cost of the project
Not Applicable
# - The project may have additional details that are pertinent. Kindly check the 'Any Other Information' field for further details.
* - Updated status for the project is not available.