Project Details Project Details

Project Name
Bridge (Nakatti) Project
Project Brief
The project involves construction of major bridge on the river Fulahar at Nakatti point for connecting Mahananda Tola and Belaimari in the main land of Malda district.
Sector
Transport
Sub-Sector
Roads and bridges
Project Capacity
3.3 KM (Kilometer)
Location The geographical location of the project
West Bengal
Project Status
Completed
Government/Non Government A government project pertains to project implemented either through traditional procurement mode or through PPP mode. A non-government project pertains to a project implemented solely by private sector.
Government
Any Other Information Any other relevant information for the project
Not Available

Name Of Authority Name of the government agency that is the implementing authority for the project
Name Of Authority
Public Works Department, West Bengal
Project Contractor Name of the concessionaire executing the project along with contact details such as name of the person, address, email, phone, fax, etc.
Name Of Contractor
S.P. Singla Constructions Private Limited
Project Timelines
Date Of Award Of Project The date on which the work order/notice to proceed was issued by the project authority to the developer
21-Sep-2015
Date Of Project Completion(Actual)
Not Available
Date Of Project Completion(as per Contract)
24-Sep-2018
Project Cost
Project Cost (as per Contract) in Rs Crore
289.69
Project Cost (Revised) in Rs Crore The project cost, if different from the cost as per original estimates
Not Available
Project Cost(Actual) in Rs Crore Actual cost of the project
Not Available
# - The project may have additional details that are pertinent. Kindly check the 'Any Other Information' field for further details.
* - Updated status for the project is not available.