Project Details Project Details

Project Name
Dhamani Medium Irrigation Project
Project Brief
The project involves implementation of Dhamani irrigation scheme at Radhanagari in Kolhapur district. The project will irrigate 1400 ha. of land of 25 villages from Panhala, Gaganbavada, Radhanagari taluka, construction of 74.64m long earthen dam.
Sector
Water Sanitation
Sub-Sector
Irrigation (dams, channels, embankments, etc.)
Project Capacity
109.0 CBM (Million Cubic Meter)
Location The geographical location of the project
Maharashtra
Project Status
Under Construction
Government/Non Government A government project pertains to project implemented either through traditional procurement mode or through PPP mode. A non-government project pertains to a project implemented solely by private sector.
Government
Any Other Information Any other relevant information for the project
Not Available

Name Of Authority Name of the government agency that is the implementing authority for the project
Name Of Authority
Maharashtra Krishna Valley Development Corporation
Project Contractor Name of the concessionaire executing the project along with contact details such as name of the person, address, email, phone, fax, etc.
Name Of Contractor
D. Y. Uppar & S. M. Anand
Project Timelines
Date Of Award Of Project The date on which the work order/notice to proceed was issued by the project authority to the developer
29-Aug-2000
Date Of Project Completion(Actual)
Not Applicable
Date Of Project Completion(as per Contract)
28-Aug-2003
Project Cost
Project Cost (as per Contract) in Rs Crore
120.30
Project Cost (Revised) in Rs Crore The project cost, if different from the cost as per original estimates
320.71
Project Cost(Actual) in Rs Crore Actual cost of the project
Not Applicable
# - The project may have additional details that are pertinent. Kindly check the 'Any Other Information' field for further details.