Project Details Project Details

Project Name
Rural Electrification (North Tripura) Project - RGGVY-Phase I
Project Brief
The project involved implementation of power distribution in North Tripura under RGGVY scheme (1st Phase). It included construction of ST line-262.20 km, LT line 614.90 km, 440 nos. of distribution transformer-16 kV/25 KVA.
Sector
Energy
Sub-Sector
Electricity transmission
Project Capacity
262.2 KM (Kilometer)
Location The geographical location of the project
Tripura
Project Status
Completed
Government/Non Government A government project pertains to project implemented either through traditional procurement mode or through PPP mode. A non-government project pertains to a project implemented solely by private sector.
Government
Any Other Information Any other relevant information for the project
Not Available

Name Of Authority Name of the government agency that is the implementing authority for the project
Name Of Authority
Tripura State Electricity Corporation Limited
Project Contractor Name of the concessionaire executing the project along with contact details such as name of the person, address, email, phone, fax, etc.
Name Of Contractor
North Eastern Cables And Conductors Private Limited
Project Timelines
Date Of Award Of Project The date on which the work order/notice to proceed was issued by the project authority to the developer
31-Jul-2009
Date Of Project Completion(Actual)
31-Mar-2014
Date Of Project Completion(as per Contract)
31-Jul-2011
Project Cost
Project Cost (as per Contract) in Rs Crore
53.61
Project Cost (Revised) in Rs Crore The project cost, if different from the cost as per original estimates
Not Available
Project Cost(Actual) in Rs Crore Actual cost of the project
53.61
# - The project may have additional details that are pertinent. Kindly check the 'Any Other Information' field for further details.
* - Updated status for the project is not available.