Project Details Project Details

Project Name
R-O-B (Bhedwad & Dindoli) Project
Project Brief
The project involves construction of R.O.B. on W.R. main line and lieu Bhestan railway line on 45.0 M. wide road nr. Pramukh Park society joining Bhedwad and Dindoli area.
Sector
Transport
Sub-Sector
Roads and bridges
Project Capacity
1.207 KM (Kilometer)
Location The geographical location of the project
Gujarat
Project Status
Completed
Government/Non Government A government project pertains to project implemented either through traditional procurement mode or through PPP mode. A non-government project pertains to a project implemented solely by private sector.
Government
Any Other Information Any other relevant information for the project
Not Available

Name Of Authority Name of the government agency that is the implementing authority for the project
Name Of Authority
Surat Municipal Corporation
Project Contractor Name of the concessionaire executing the project along with contact details such as name of the person, address, email, phone, fax, etc.
Name Of Contractor
Valecha Engineering Limited
Project Timelines
Date Of Award Of Project The date on which the work order/notice to proceed was issued by the project authority to the developer
20-Sep-2012
Date Of Project Completion(Actual)
18-Jan-2018
Date Of Project Completion(as per Contract)
19-Sep-2014
Project Cost
Project Cost (as per Contract) in Rs Crore
60.49
Project Cost (Revised) in Rs Crore The project cost, if different from the cost as per original estimates
Not Available
Project Cost(Actual) in Rs Crore Actual cost of the project
82.57
# - The project may have additional details that are pertinent. Kindly check the 'Any Other Information' field for further details.
* - Updated status for the project is not available.