Project Details Project Details

Project Name
Bridge (Athwa-Adajan) Project
Project Brief
The project involves construction of cable stay bridge across river Tapi joining Athwa and Adajan in Surat district.
Sector
Transport
Sub-Sector
Roads and bridges
Project Capacity
0.6 KM (Kilometer)
Location The geographical location of the project
Gujarat
Project Status
Completed
Government/Non Government A government project pertains to project implemented either through traditional procurement mode or through PPP mode. A non-government project pertains to a project implemented solely by private sector.
Government
Any Other Information Any other relevant information for the project
Not Available

Name Of Authority Name of the government agency that is the implementing authority for the project
Name Of Authority
Surat Municipal Corporation
Project Contractor Name of the concessionaire executing the project along with contact details such as name of the person, address, email, phone, fax, etc.
Name Of Contractor
Unique Construction
Project Timelines
Date Of Award Of Project The date on which the work order/notice to proceed was issued by the project authority to the developer
30-Jul-2015
Date Of Project Completion(Actual)
02-Dec-2019
Date Of Project Completion(as per Contract)
28-Feb-2017
Project Cost
Project Cost (as per Contract) in Rs Crore
143.64
Project Cost (Revised) in Rs Crore The project cost, if different from the cost as per original estimates
Not Available
Project Cost(Actual) in Rs Crore Actual cost of the project
Not Available
# - The project may have additional details that are pertinent. Kindly check the 'Any Other Information' field for further details.
* - Updated status for the project is not available.