Project Details Project Details

Project Name
Four laning of Itanagar to Holongi section road in length of 19.3 Km of NH-52A (New NH-415)
Project Brief
The project involved four laning of Itanagar to Holongi section of NH-52A (New NH-415).
Sector
Transport
Sub-Sector
Roads and bridges
Project Capacity
19.3 KM (Kilometer)
Location The geographical location of the project
Arunachal Pradesh
Project Status
Completed
Government/Non Government A government project pertains to project implemented either through traditional procurement mode or through PPP mode. A non-government project pertains to a project implemented solely by private sector.
Government
Any Other Information Any other relevant information for the project
Not Available

Name Of Authority Name of the government agency that is the implementing authority for the project
Name Of Authority
Public Works Department, Arunachal Pradesh
Project Contractor Name of the concessionaire executing the project along with contact details such as name of the person, address, email, phone, fax, etc.
Name Of Contractor
SRK-T.K. Engineering Consortium Private Limited (JV)
Project Timelines
Date Of Award Of Project The date on which the work order/notice to proceed was issued by the project authority to the developer
15-Aug-2011
Date Of Project Completion(Actual)
31-Aug-2016
Date Of Project Completion(as per Contract)
12-Aug-2015
Project Cost
Project Cost (as per Contract) in Rs Crore
264.16
Project Cost (Revised) in Rs Crore The project cost, if different from the cost as per original estimates
475.22
Project Cost(Actual) in Rs Crore Actual cost of the project
536.70