Project Details Project Details

Project Name
Implementation of 15 MLD sewage system for Taleigao, Dona Paula & Caranzalem*
Project Brief
The project involves implementation of sewage system for Taleigao, Dona Paula and Caranzalem areas on the outskirts of Panaji city -Phase I.
Sector
Water Sanitation
Sub-Sector
Sewage collection, treatment and disposal system
Project Capacity
15.0 MLD (Millons Liter per day)
Location The geographical location of the project
Goa
Project Status
Completed
Government/Non Government A government project pertains to project implemented either through traditional procurement mode or through PPP mode. A non-government project pertains to a project implemented solely by private sector.
Government
Any Other Information Any other relevant information for the project
Project was delayed due to lack of funds issues and revised date under approval stage (Source :- Assistant Engineer, Public Works Department, Goa)

Name Of Authority Name of the government agency that is the implementing authority for the project
Name Of Authority
Public Works Department, Goa
Project Contractor Name of the concessionaire executing the project along with contact details such as name of the person, address, email, phone, fax, etc.
Name Of Contractor
Ayyappa Infra Projects Private Limited
Project Timelines
Date Of Award Of Project The date on which the work order/notice to proceed was issued by the project authority to the developer
28-Apr-2012
Date Of Project Completion(Actual)
29-Nov-2019
Date Of Project Completion(as per Contract)
31-Mar-2017
Project Cost
Project Cost (as per Contract) in Rs Crore
101.00
Project Cost (Revised) in Rs Crore The project cost, if different from the cost as per original estimates
144.25
Project Cost(Actual) in Rs Crore Actual cost of the project
Not Available
# - The project may have additional details that are pertinent. Kindly check the 'Any Other Information' field for further details.