Project Details Project Details

Project Name
Implementation of 1500 km rural water supply scheme Bisalpur-Dudu-Phagi in Jaipur *
Project Brief
The project involves implementation of rural water supply scheme of 161 villages and their dhanies of Phagi tehsil under Bisalpur Dudu Phagi water supply project in Jaipur district.
Sector
Water Sanitation
Sub-Sector
Water supply pipeline
Project Capacity
1500.0 KM (Kilometer)
Location The geographical location of the project
Rajasthan
Project Status
Under Construction
Government/Non Government A government project pertains to project implemented either through traditional procurement mode or through PPP mode. A non-government project pertains to a project implemented solely by private sector.
Government
Any Other Information Any other relevant information for the project
Updated status for the project is not available.

Name Of Authority Name of the government agency that is the implementing authority for the project
Name Of Authority
Public Health Engineering Department, Rajasthan
Project Contractor Name of the concessionaire executing the project along with contact details such as name of the person, address, email, phone, fax, etc.
Name Of Contractor
Pratibha Industries Limited
Project Timelines
Date Of Award Of Project The date on which the work order/notice to proceed was issued by the project authority to the developer
03-Aug-2013
Date Of Project Completion(Actual)
Not Applicable
Date Of Project Completion(as per Contract)
02-Feb-2016
Project Cost
Project Cost (as per Contract) in Rs Crore
205.12
Project Cost (Revised) in Rs Crore The project cost, if different from the cost as per original estimates
Not Available
Project Cost(Actual) in Rs Crore Actual cost of the project
Not Applicable
# - The project may have additional details that are pertinent. Kindly check the 'Any Other Information' field for further details.
* - Updated status for the project is not available.