Project Details Project Details

Project Name
Setting up a 300 MW phase-II coal based power unit at Chillakur
Project Brief
The project involved setting up a (2x150 MW) (Phase-II) coal based power unit at Chillakur in Nellore district.
Sector
Energy
Sub-Sector
Electricity generation (grid)
Project Capacity
300.0 MW (Mega Watt)
Location The geographical location of the project
Andhra Pradesh
Project Status
Completed
Government/Non Government A government project pertains to project implemented either through traditional procurement mode or through PPP mode. A non-government project pertains to a project implemented solely by private sector.
Private Sector Infrastructure Projects
Any Other Information Any other relevant information for the project
Not Available

Project Developer Name of the private player implementing the project
Name of Developer
Simhapuri Energy Private Limited
Project Timelines
Date Of Start Of Project The date on which the work order/notice to proceed was issued by the project authority to the developer
28-Feb-2011
Date Of Project Completion(Actual)
06-Mar-2015
Date Of Project Completion(as per Contract)
30-Sep-2012
Project Cost
Project Cost (as per Contract) in Rs Crore
1,198.00
Project Cost (Revised) in Rs Crore The project cost, if different from the cost as per original estimates
Not Available
Project Cost(Actual) in Rs Crore Actual cost of the project
1,198.00