Project Details Project Details

Project Name
140 MW Wind Based Power (Sangli) Project
Project Brief
CLP Power India has set up a 140 MW wind based power unit in Sangli district.
Sector
Energy
Sub-Sector
Renewable energy (grid)
Project Capacity
140.0 MW (Mega Watt)
Location The geographical location of the project
Maharashtra
Project Status
Completed
Government/Non Government A government project pertains to project implemented either through traditional procurement mode or through PPP mode. A non-government project pertains to a project implemented solely by private sector.
Private Sector Infrastructure Projects
Any Other Information Any other relevant information for the project
Not Available

Project Developer Name of the private player implementing the project
Name of Developer
CLP India Private Limited
Project Timelines
Date Of Start Of Project The date on which the work order/notice to proceed was issued by the project authority to the developer
Not Available
Date Of Project Completion(Actual)
31-Aug-2014
Date Of Project Completion(as per Contract)
30-Jun-2014
Project Cost
Project Cost (as per Contract) in Rs Crore
900.00
Project Cost (Revised) in Rs Crore The project cost, if different from the cost as per original estimates
Not Available
Project Cost(Actual) in Rs Crore Actual cost of the project
900.00
# - The project may have additional details that are pertinent. Kindly check the 'Any Other Information' field for further details.
* - Updated status for the project is not available.