Login
Login Id
Password
Caps Lock is on.
Remember Me
Login
Forgot Password
Last updated on: 06 December 2019
HOME
ABOUT US
REPORTS
PRE-DEFINED REPORTS
Note: These Reports provide information on infrastructure projects across pre-defined set of categories.
All Infrastructure Projects
Government Infrastructure Projects
Government Infrastructure Projects (PPP)
Government Infrastructure Projects (Traditional Procurement)
Private Sector Infrastructure Projects
Infrastructure Projects State Wise
Infrastructure Projects Sector Wise
Infrastructure Projects Status Wise
Infrastructure Projects Year Wise
SUMMARY REPORTS
Note: These Reports offer concise information across different states, sectors, implementation status and year of award.
State wise
Sector wise
Status wise
Year wise
Authority Wise
DESIGN YOUR SEARCH
CONTACTS
FAQS
GLOSSARY
USER MANUAL
USEFUL LINKS
PPPININDIA.GOV.IN
HOME
ABOUT US
REPORTS
PRE-DEFINED REPORTS
Note: These Reports provide information on infrastructure projects across pre-defined set of categories.
All Infrastructure Projects
Government Infrastructure Projects
Government Infrastructure Projects (PPP)
Government Infrastructure Projects (Traditional Procurement)
Private Sector Infrastructure Projects
Infrastructure Projects State Wise
Infrastructure Projects Sector Wise
Infrastructure Projects Status Wise
Infrastructure Projects Year Wise
SUMMARY REPORTS
Note: These Reports offer concise information across different states, sectors, implementation status and year of award.
State wise
Sector wise
Status wise
Year wise
Authority Wise
DESIGN YOUR SEARCH
CONTACTS
FAQS
GLOSSARY
USER MANUAL
USEFUL LINKS
PPPININDIA.GOV.IN
Project Details
Project Details
Back
Print
Export to Pdf
Project Information
Project Name
Underground Sewerage Scheme (Bhiwandi-Nizampur) - Phase I
Project Brief
The project involved laying of 15.20 km underground sewerage pipelines. It involves construction of 13 MLD new sewerage treatment plant & construction of 1 MLD effluent treatment plant, repair works of 17 MLD STP plant, raw water pumping main, laying of sewerage pipeline of 600 mm diameter DIK-7 from ajay nagar pumping station to new STP, laying of treated sewerage gravity line of 700 mm diameter
Sector
Water Sanitation
Sub-Sector
Sewage collection, treatment and disposal system
Project Capacity
13.0 MLD (Millons Liter per day)
Location
The geographical location of the project
Maharashtra
Project Status
Completed
Government/Non Government
A government project pertains to project implemented either through traditional procurement mode or through PPP mode. A non-government project pertains to a project implemented solely by private sector.
Government
Any Other Information
Any other relevant information for the project
Not Available
Name Of Authority
Name of the government agency that is the implementing authority for the project
Name Of Authority
Bhiwandi Nizampur City Municipal Corporation
Project Contractor
Name of the concessionaire executing the project along with contact details such as name of the person, address, email, phone, fax, etc.
Name Of Contractor
Eagle Construction Company
Project Timelines
Date Of Award Of Project
The date on which the work order/notice to proceed was issued by the project authority to the developer
31-May-2010
Date Of Project Completion(Actual)
31-Mar-2016
Date Of Project Completion(as per Contract)
31-Jan-2015
Project Cost
Project Cost (as per Contract) in Rs Crore
64.72
Project Cost (Revised) in Rs Crore
The project cost, if different from the cost as per original estimates
71.80
Project Cost(Actual) in Rs Crore
Actual cost of the project
71.80
Back
Last Updated on 04-Dec-2019
#
- The project may have additional details that are pertinent. Kindly check the 'Any Other Information' field for further details.
*