Project Details Project Details

Project Name
Water Supply (Bijapur) Project - UIDSSMT
Project Brief
The project involved providing water supply sheme to Bijapur city with Krishna river as source, under UIDSSMT. Under this scheme following were the major improvements implemented. i) Source enhancement 27.27 MLD to 65.27 MLD. ii) Storage enhancement including feeder mains. iii) Remodelling of distribution network i.e., providing continuous pressurized water supply (24x7) in Zone No.6, 15, and 17. The project is implemented under 8 packages
Sector
Water Sanitation
Sub-Sector
Water supply pipeline
Project Capacity
38.0 MLD (Millons Liter per day)
Location The geographical location of the project
Karnataka
Project Status
Completed
Government/Non Government A government project pertains to project implemented either through traditional procurement mode or through PPP mode. A non-government project pertains to a project implemented solely by private sector.
Government
Any Other Information Any other relevant information for the project
Not Available

Name Of Authority Name of the government agency that is the implementing authority for the project
Name Of Authority
Karnataka Urban Water Supply and Drainage Board
Project Contractor Name of the concessionaire executing the project along with contact details such as name of the person, address, email, phone, fax, etc.
Name Of Contractor
Veolia Water India Private Limited
Project Timelines
Date Of Award Of Project The date on which the work order/notice to proceed was issued by the project authority to the developer
12-Jul-2012
Date Of Project Completion(Actual)
08-Feb-2015
Date Of Project Completion(as per Contract)
11-Jul-2014
Project Cost
Project Cost (as per Contract) in Rs Crore
62.78
Project Cost (Revised) in Rs Crore The project cost, if different from the cost as per original estimates
88.90
Project Cost(Actual) in Rs Crore Actual cost of the project
88.90
# - The project may have additional details that are pertinent. Kindly check the 'Any Other Information' field for further details.