Project Details Project Details

Project Name
Implementation of 50 MW coal based captive power unit at Wadapalli
Project Brief
The project involved implementation of coal based captive power unit at Wadapalli in Nalgonda distirct.
Sector
Energy
Sub-Sector
Electricity generation (grid)
Project Capacity
50.0 MW (Mega Watt)
Location The geographical location of the project
Telangana
Project Status
Completed
Government/Non Government A government project pertains to project implemented either through traditional procurement mode or through PPP mode. A non-government project pertains to a project implemented solely by private sector.
Private Sector Infrastructure Projects
Any Other Information Any other relevant information for the project
Not Available

Project Developer Name of the private player implementing the project
Name of Developer
India Cements Limited
Project Timelines
Date Of Start Of Project The date on which the work order/notice to proceed was issued by the project authority to the developer
31-May-2011
Date Of Project Completion(Actual)
31-Dec-2013
Date Of Project Completion(as per Contract)
31-May-2012
Project Cost
Project Cost (as per Contract) in Rs Crore
250.00
Project Cost (Revised) in Rs Crore The project cost, if different from the cost as per original estimates
Not Available
Project Cost(Actual) in Rs Crore Actual cost of the project
250.00
# - The project may have additional details that are pertinent. Kindly check the 'Any Other Information' field for further details.