Project Details Project Details

Project Name
Varangaon Talwel Lift Irrigation Scheme#
Project Brief
The project involves implementation of Varangaon Talwel lift irrigation scheme. It will spread over ICA-16948 Ha & IP-24744 Ha. Construction of Ozarkheda Dam is included in the Scheme.
Sector
Water Sanitation
Sub-Sector
Irrigation (dams, channels, embankments, etc.)
Project Capacity
85.67 CBM (Million Cubic Meter)
Location The geographical location of the project
Maharashtra
Project Status
Under Construction
Government/Non Government A government project pertains to project implemented either through traditional procurement mode or through PPP mode. A non-government project pertains to a project implemented solely by private sector.
Government
Any Other Information Any other relevant information for the project
Work on the project delayed due to following reasons:- i) Non availability of sufficient funds. ii) Delay in permission for 74.54 ha. forest land. iii) Acquisition of Type -2 land for which permission of Divisional Commissioner is required and permission for 28 such cases is obtained on 20.07.2012. As on October 2015, expected date of the project completion is 31-Mar-2020. (Source:- Assistant Superintending Engineer, Tapi Irrigation Development Corporation, Jalgaon Circle)

Name Of Authority Name of the government agency that is the implementing authority for the project
Name Of Authority
Tapi Irrigation Development Corporation
Project Contractor Name of the concessionaire executing the project along with contact details such as name of the person, address, email, phone, fax, etc.
Name Of Contractor
IVRCL Limited, Pune
Project Timelines
Date Of Award Of Project The date on which the work order/notice to proceed was issued by the project authority to the developer
07-Jun-1999
Date Of Project Completion(Actual)
Not Applicable
Date Of Project Completion(as per Contract)
08-Jul-2006
Project Cost
Project Cost (as per Contract) in Rs Crore
302.26
Project Cost (Revised) in Rs Crore The project cost, if different from the cost as per original estimates
916.81
Project Cost(Actual) in Rs Crore Actual cost of the project
Not Applicable
# - The project may have additional details that are pertinent. Kindly check the 'Any Other Information' field for further details.
* - Updated status for the project is not available.