Project Details Project Details

Project Name
Rural Electrification (North Bihar) Project - R-APDRP Part-B
Project Brief
The project involves construction of 33/11KV Power Sub Stations alongwith associated 33KV &11KV lines for strengthening of distribution system in 28 Towns of North Bihar. Strengthening and augumentation of distribution network 33KV & below for reduction of AT & C loss.
Sector
Energy
Sub-Sector
Electricity transmission
Project Capacity
258.87 CKM (Circuit Kilo Meter)
Location The geographical location of the project
Bihar
Project Status
Completed
Government/Non Government A government project pertains to project implemented either through traditional procurement mode or through PPP mode. A non-government project pertains to a project implemented solely by private sector.
Government
Any Other Information Any other relevant information for the project
Not Available

Name Of Authority Name of the government agency that is the implementing authority for the project
Name Of Authority
North Bihar Power Distribution Company Limited
Project Contractor Name of the concessionaire executing the project along with contact details such as name of the person, address, email, phone, fax, etc.
Name Of Contractor
Godrej & Boyce Manufacturing Company Limited
Project Timelines
Date Of Award Of Project The date on which the work order/notice to proceed was issued by the project authority to the developer
22-Nov-2013
Date Of Project Completion(Actual)
03-Dec-2019
Date Of Project Completion(as per Contract)
17-Jun-2015
Project Cost
Project Cost (as per Contract) in Rs Crore
343.54
Project Cost (Revised) in Rs Crore The project cost, if different from the cost as per original estimates
Not Available
Project Cost(Actual) in Rs Crore Actual cost of the project
Not Available