Project Details Project Details

Project Name
Satpura Thermal Power Project#
Project Brief
The project involved setting up of 500 MW (2x250 MW), Unit 10 & 11 of Satpura Thermal Power Project at Sarni in Betul.
Sector
Energy
Sub-Sector
Electricity generation (grid)
Project Capacity
500.0 MW (Mega Watt)
Location The geographical location of the project
Madhya Pradesh
Project Status
Completed
Government/Non Government A government project pertains to project implemented either through traditional procurement mode or through PPP mode. A non-government project pertains to a project implemented solely by private sector.
Government
Any Other Information Any other relevant information for the project
Unit 10 was completed on 18-08-2013 and Unit 11 was 16-03-2014.

Name Of Authority Name of the government agency that is the implementing authority for the project
Name Of Authority
Madhya Pradesh Power Generating Company Limited
Project Contractor Name of the concessionaire executing the project along with contact details such as name of the person, address, email, phone, fax, etc.
Name Of Contractor
Bharat Heavy Electricals Limited
Project Timelines
Date Of Award Of Project The date on which the work order/notice to proceed was issued by the project authority to the developer
27-Feb-2009
Date Of Project Completion(Actual)
16-Mar-2014
Date Of Project Completion(as per Contract)
26-Jan-2012
Project Cost
Project Cost (as per Contract) in Rs Crore
3,032.34
Project Cost (Revised) in Rs Crore The project cost, if different from the cost as per original estimates
3,514.00
Project Cost(Actual) in Rs Crore Actual cost of the project
Not Available
# - The project may have additional details that are pertinent. Kindly check the 'Any Other Information' field for further details.
* - Updated status for the project is not available.