Project Details Project Details

Project Name
Indira Gandhi Nahar Project - Stage II#*
Project Brief
The project involves implementation of Indira Gandhi Nahar Project - Stage II
Sector
Water Sanitation
Sub-Sector
Irrigation (dams, channels, embankments, etc.)
Project Capacity
Not Available
Location The geographical location of the project
Rajasthan
Project Status
Under Construction
Government/Non Government A government project pertains to project implemented either through traditional procurement mode or through PPP mode. A non-government project pertains to a project implemented solely by private sector.
Government
Any Other Information Any other relevant information for the project
Though as per approved revised estimate 2010, of IGNP stage II, Culturable command area of project is 12.45 lac hectare, however, at present State Govt. has directed to complete works in 10.71 lac hectare on priority. Out of this 10.60 lac hectare has been opened by completing canal works. Thus canal works are balance in only 11 thousand hectare only. Updated status for the project is not available.

Name Of Authority Name of the government agency that is the implementing authority for the project
Name Of Authority
Indira Gandhi Nahar Board
Project Contractor Name of the concessionaire executing the project along with contact details such as name of the person, address, email, phone, fax, etc.
Name Of Contractor
Not Available
Project Timelines
Date Of Award Of Project The date on which the work order/notice to proceed was issued by the project authority to the developer
Not Available
Date Of Project Completion(Actual)
Not Applicable
Date Of Project Completion(as per Contract)
31-Mar-2014
Project Cost
Project Cost (as per Contract) in Rs Crore
6,921.32
Project Cost (Revised) in Rs Crore The project cost, if different from the cost as per original estimates
Not Available
Project Cost(Actual) in Rs Crore Actual cost of the project
Not Applicable
# - The project may have additional details that are pertinent. Kindly check the 'Any Other Information' field for further details.