Project Details Project Details

Project Name
Wind Based Power (Bijapur) Project
Project Brief
Greenko Group is setting up a 151.2 MW wind based power project at Basavanabagewadi in Bijapur. The project will be implemented in 3 phases, Phase I will include capacity of 51.2 MW Greenco's GE 1.6X32 XLE Turbines, Phase II of 50 MW Gamesa's 2.0X25 G97 Turbines and Phase III of 50 MW
Sector
Energy
Sub-Sector
Renewable energy (grid)
Project Capacity
151.2 MW (Mega Watt)
Location The geographical location of the project
Karnataka
Project Status
Under Construction
Government/Non Government A government project pertains to project implemented either through traditional procurement mode or through PPP mode. A non-government project pertains to a project implemented solely by private sector.
Private Sector Infrastructure Projects
Any Other Information Any other relevant information for the project
Not Available

Project Developer Name of the private player implementing the project
Name of Developer
Greenko Group
Project Timelines
Date Of Start Of Project The date on which the work order/notice to proceed was issued by the project authority to the developer
Not Available
Date Of Project Completion(Actual)
Not Applicable
Date Of Project Completion(as per Contract)
31-May-2015
Project Cost
Project Cost (as per Contract) in Rs Crore
1,300.00
Project Cost (Revised) in Rs Crore The project cost, if different from the cost as per original estimates
Not Available
Project Cost(Actual) in Rs Crore Actual cost of the project
Not Applicable