Project Details Project Details

Project Name
Solar Photovoltaic Power (Mahoba) Project*
Project Brief
The project involved setting up of 10 MW solar photovoltaic power unit at Mahoba
Sector
Energy
Sub-Sector
Renewable energy (grid)
Project Capacity
10.0 MW (Mega Watt)
Location The geographical location of the project
Uttar Pradesh
Project Status
Completed
Government/Non Government A government project pertains to project implemented either through traditional procurement mode or through PPP mode. A non-government project pertains to a project implemented solely by private sector.
Private Sector Infrastructure Projects
Any Other Information Any other relevant information for the project
Updated status for the project is not available.

Project Developer Name of the private player implementing the project
Name of Developer
Azure Power India Private Limited
Project Timelines
Date Of Start Of Project The date on which the work order/notice to proceed was issued by the project authority to the developer
Not Available
Date Of Project Completion(Actual)
02-Feb-2015
Date Of Project Completion(as per Contract)
02-Feb-2015
Project Cost
Project Cost (as per Contract) in Rs Crore
800.00
Project Cost (Revised) in Rs Crore The project cost, if different from the cost as per original estimates
Not Available
Project Cost(Actual) in Rs Crore Actual cost of the project
Not Available
# - The project may have additional details that are pertinent. Kindly check the 'Any Other Information' field for further details.
* - Updated status for the project is not available.