Project Details Project Details

Project Name
Water Supply Scheme (Panchkula)#
Project Brief
Supplying Canal Water from Water Works Sec-39, Chd. to Panchkula (Upto U.T. Boundary near Naugaja Peer). (Deposit Work by MC Chandigarh). Laying of 800mm i/d 18.31 km MS pipe line inner lined & outer coating & specials from WW Sec-39 to U.T. boundary along with surge control equipments. Construction of pump chamber at WW Sec-39, Chd. and making arrangement for inlet connection with sump & interconnection of main pipe. Pumping machinery including cost for restore of electric connection and SCADA system and flow meter at WW Sec-39 Chd.
Sector
Water Sanitation
Sub-Sector
Water supply pipeline
Project Capacity
Not Available
Location The geographical location of the project
Haryana
Project Status
Completed
Government/Non Government A government project pertains to project implemented either through traditional procurement mode or through PPP mode. A non-government project pertains to a project implemented solely by private sector.
Government
Any Other Information Any other relevant information for the project
Pumping Machinery installed, Electric connection yet to be provided.

Name Of Authority Name of the government agency that is the implementing authority for the project
Name Of Authority
Haryana Urban Development Authority
Project Contractor Name of the concessionaire executing the project along with contact details such as name of the person, address, email, phone, fax, etc.
Name Of Contractor
Not Available
Project Timelines
Date Of Award Of Project The date on which the work order/notice to proceed was issued by the project authority to the developer
11-Jul-2012
Date Of Project Completion(Actual)
31-Jan-2014
Date Of Project Completion(as per Contract)
Not Available
Project Cost
Project Cost (as per Contract) in Rs Crore
61.68
Project Cost (Revised) in Rs Crore The project cost, if different from the cost as per original estimates
Not Available
Project Cost(Actual) in Rs Crore Actual cost of the project
61.68