Project Details Project Details

Project Name
Sewage Treatment Plant (Dhanwapur)#
Project Brief
The project involved construction Of 100 MLD 2nd. STP & MPS at Behrampur, Gurgaon
Sector
Water Sanitation
Sub-Sector
Sewage collection, treatment and disposal system
Project Capacity
100.0 MLD (Millons Liter per day)
Location The geographical location of the project
Haryana
Project Status
Completed
Government/Non Government A government project pertains to project implemented either through traditional procurement mode or through PPP mode. A non-government project pertains to a project implemented solely by private sector.
Government
Any Other Information Any other relevant information for the project
STP work completed upto tertiary treatment & under commissioning. The work was allotted subject to decision of Hon?ble High Court & court decision was conveyed after 6 months and subsequently work also delayed by 6 months.

Name Of Authority Name of the government agency that is the implementing authority for the project
Name Of Authority
Haryana Urban Development Authority
Project Contractor Name of the concessionaire executing the project along with contact details such as name of the person, address, email, phone, fax, etc.
Name Of Contractor
Not Available
Project Timelines
Date Of Award Of Project The date on which the work order/notice to proceed was issued by the project authority to the developer
22-Mar-2012
Date Of Project Completion(Actual)
31-Mar-2015
Date Of Project Completion(as per Contract)
Not Available
Project Cost
Project Cost (as per Contract) in Rs Crore
94.40
Project Cost (Revised) in Rs Crore The project cost, if different from the cost as per original estimates
Not Available
Project Cost(Actual) in Rs Crore Actual cost of the project
Not Available
# - The project may have additional details that are pertinent. Kindly check the 'Any Other Information' field for further details.
* - Updated status for the project is not available.