Project Details Project Details

Project Name
Construction of EM-Bypass connector from Padmapukur to Kamalgazi in Kolkata district
Project Brief
The project involved construction of EM-Bypass connector from Padmapukur to Kamalgazi in Kolkata.
Sector
Transport
Sub-Sector
Roads and bridges
Project Capacity
19.0 KM (Kilometer)
Location The geographical location of the project
West Bengal
Project Status
Completed
Government/Non Government A government project pertains to project implemented either through traditional procurement mode or through PPP mode. A non-government project pertains to a project implemented solely by private sector.
Government
Any Other Information Any other relevant information for the project
Not Available

Name Of Authority Name of the government agency that is the implementing authority for the project
Name Of Authority
Kolkata Metropolitan Development Authority
Project Contractor Name of the concessionaire executing the project along with contact details such as name of the person, address, email, phone, fax, etc.
Name Of Contractor
IVRCL Limited
Project Timelines
Date Of Award Of Project The date on which the work order/notice to proceed was issued by the project authority to the developer
28-Dec-2007
Date Of Project Completion(Actual)
30-Jun-2016
Date Of Project Completion(as per Contract)
28-Dec-2009
Project Cost
Project Cost (as per Contract) in Rs Crore
53.09
Project Cost (Revised) in Rs Crore The project cost, if different from the cost as per original estimates
77.72
Project Cost(Actual) in Rs Crore Actual cost of the project
77.72