Project Details Project Details

Project Name
Implementation of 200 MLD Bhama Askhed water supply scheme in Pune
Project Brief
The project involves implementation of Bhama Askhed water supply scheme in Pune district. The project includes a 42km pipeline from the dam to the PMC limits.
Sector
Water Sanitation
Sub-Sector
Water supply pipeline
Project Capacity
200.0 MLD (Millons Liter per day)
Location The geographical location of the project
Maharashtra
Project Status
Completed
Government/Non Government A government project pertains to project implemented either through traditional procurement mode or through PPP mode. A non-government project pertains to a project implemented solely by private sector.
Government
Any Other Information Any other relevant information for the project
Out of 42 km pipeline, laying work on 6 km pipeline was completed till January 2015

Name Of Authority Name of the government agency that is the implementing authority for the project
Name Of Authority
Pune Municipal Corporation
Project Contractor Name of the concessionaire executing the project along with contact details such as name of the person, address, email, phone, fax, etc.
Name Of Contractor
Hindustan Construction Company Limited
Project Timelines
Date Of Award Of Project The date on which the work order/notice to proceed was issued by the project authority to the developer
10-Feb-2014
Date Of Project Completion(Actual)
29-Nov-2019
Date Of Project Completion(as per Contract)
Not Available
Project Cost
Project Cost (as per Contract) in Rs Crore
253.11
Project Cost (Revised) in Rs Crore The project cost, if different from the cost as per original estimates
380.00
Project Cost(Actual) in Rs Crore Actual cost of the project
Not Available
# - The project may have additional details that are pertinent. Kindly check the 'Any Other Information' field for further details.
* - Updated status for the project is not available.