Project Details Project Details

Project Name
Development of 72 km Mumbai Urban Transport Project (MUTP) Phase II project
Project Brief
The project involves construction of 88 track in length of 72 km, new 12-car rakes (864 coaches) DC to AC conversion on Central Railway (172 Track km), thereby completing the DC-AC conversion on Mumbai Suburban system. Resettlement & Rehabilitation of more than 2500 project affected households under MUTP Phase II.
Sector
Transport
Sub-Sector
Railway track, tunnel, viaducts, bridges
Project Capacity
72.0 KM (Kilometer)
Location The geographical location of the project
Maharashtra
Project Status
Under Construction
Government/Non Government A government project pertains to project implemented either through traditional procurement mode or through PPP mode. A non-government project pertains to a project implemented solely by private sector.
Government
Any Other Information Any other relevant information for the project
Not Available

Name Of Authority Name of the government agency that is the implementing authority for the project
Name Of Authority
Mumbai Railway Vikas Corporation Limited
Project Contractor Name of the concessionaire executing the project along with contact details such as name of the person, address, email, phone, fax, etc.
Name Of Contractor
Bombardier Transportation
Project Timelines
Date Of Award Of Project The date on which the work order/notice to proceed was issued by the project authority to the developer
31-May-2008
Date Of Project Completion(Actual)
Not Applicable
Date Of Project Completion(as per Contract)
31-Mar-2021
Project Cost
Project Cost (as per Contract) in Rs Crore
5,300.00
Project Cost (Revised) in Rs Crore The project cost, if different from the cost as per original estimates
8,087.00
Project Cost(Actual) in Rs Crore Actual cost of the project
Not Applicable
# - The project may have additional details that are pertinent. Kindly check the 'Any Other Information' field for further details.
* - Updated status for the project is not available.