Project Details Project Details

Project Name
Mega Food Park (Chhattisgarh)*
Project Brief
Land: 78.27 Acres Compents: Core facilities related to processing of fruits and vegetables; Basic infrastructures facilities requird for operation of industrial units like Road, water supply, power supply, Pollution Control arrangements etc.
Sector
Social and Commercial Infrastructure
Sub-Sector
Common infrastructure for industrial parks, SEZ
Project Capacity
78.27 Acres
Location The geographical location of the project
Chhattisgarh
Project Status
Under Construction
Government/Non Government A government project pertains to project implemented either through traditional procurement mode or through PPP mode. A non-government project pertains to a project implemented solely by private sector.
Government
Any Other Information Any other relevant information for the project
The Ministry grant to the project is Rs. 50.00 crore. No grant has yet been released to the project yet.Updated status for the project is not available

Name Of Authority Name of the government agency that is the implementing authority for the project
Name Of Authority
Ministry of Food Processing Industries
Project Contractor Name of the concessionaire executing the project along with contact details such as name of the person, address, email, phone, fax, etc.
Name Of Contractor
Raipur Mega Food Park Pvt. Ltd
Project Timelines
Date Of Award Of Project The date on which the work order/notice to proceed was issued by the project authority to the developer
04-Jun-2014
Date Of Project Completion(Actual)
Not Applicable
Date Of Project Completion(as per Contract)
04-Dec-2016
Project Cost
Project Cost (as per Contract) in Rs Crore
126.12
Project Cost (Revised) in Rs Crore The project cost, if different from the cost as per original estimates
Not Available
Project Cost(Actual) in Rs Crore Actual cost of the project
Not Applicable