Project Details Project Details

Project Name
Laying of Bogibeel rail-cum-road bridge over Brahmaputra river
Project Brief
The project involves laying of 46.5 km of railway track and 29.5 km of road. It includes a 4.3 km Bogibeel rail-cum-road bridge over River Brahmaputra near Dibrugarh in Assam. The bridge with 34 spans of 125 metres and two of 32 metres will connect Sisi Bargaon.
Sector
Transport
Sub-Sector
Railway track, tunnel, viaducts, bridges
Project Capacity
76.0 KM (Kilometer)
Location The geographical location of the project
Assam
Project Status
Completed
Government/Non Government A government project pertains to project implemented either through traditional procurement mode or through PPP mode. A non-government project pertains to a project implemented solely by private sector.
Government
Any Other Information Any other relevant information for the project
As of November 2016, the revised completion date was 15-Mar-2018 (Source :- nfrcon.org)

Name Of Authority Name of the government agency that is the implementing authority for the project
Name Of Authority
Northeast Frontier Railway
Project Contractor Name of the concessionaire executing the project along with contact details such as name of the person, address, email, phone, fax, etc.
Name Of Contractor
Gammon India Limited
Project Timelines
Date Of Award Of Project The date on which the work order/notice to proceed was issued by the project authority to the developer
30-Apr-2008
Date Of Project Completion(Actual)
Not Available
Date Of Project Completion(as per Contract)
31-Mar-2017
Project Cost
Project Cost (as per Contract) in Rs Crore
3,996.70
Project Cost (Revised) in Rs Crore The project cost, if different from the cost as per original estimates
4,996.00
Project Cost(Actual) in Rs Crore Actual cost of the project
5,920.00