Project Details Project Details

Project Name
Construction of a New Multi-purpose Berth (Berth No. 18) for handling general cargo & containers at NMPT#
Project Brief
(i) The construction of new 300 m. long berth proposed in the New Western Dock including all civil works, capital dredging in front of the Berth, mechanical, electrical and instrumentation works to establish one exclusive Container Terminal at the New Mangalore Port. (ii) The Stockyard behind the Berth having space of approximately 6 Hectares will be developed for storage. The Berth width will be 25 m. suitable to accommodate rail mounted gantry cranes with 20 m. gauge. The Berth quay level will be + 4.6 m above CD. Jetty will be supported on piles of adequate strength and depth to be founded on the seabed rock. Diaphragm wall to be provided as retaining structure of 300 m + 75m long with rear anchor to separate the sea from the land. A 250 m long additional diaphragm wall with rear anchor is required to be constructed at the sea side.
Sector
Transport
Sub-Sector
Ports (excluding captive)
Project Capacity
5000000.0 MT (Metric Tonne )
Location The geographical location of the project
Karnataka
Project Status
Under Construction
Government/Non Government A government project pertains to project implemented either through traditional procurement mode or through PPP mode. A non-government project pertains to a project implemented solely by private sector.
Government
Any Other Information Any other relevant information for the project
* Approved Project cost including Capital Dredging.Estimated civil work cost 113.55 crores. Awarded Construction cost (civil work) 93.62 crore.

Name Of Authority Name of the government agency that is the implementing authority for the project
Name Of Authority
New Mangalore Port Trust
Project Contractor Name of the concessionaire executing the project along with contact details such as name of the person, address, email, phone, fax, etc.
Name Of Contractor
DBM Geotechnics and Constructions pvt. Ltd.
Project Timelines
Date Of Award Of Project The date on which the work order/notice to proceed was issued by the project authority to the developer
28-Oct-2013
Date Of Project Completion(Actual)
Not Applicable
Date Of Project Completion(as per Contract)
27-Jun-2015
Project Cost
Project Cost (as per Contract) in Rs Crore
137.44
Project Cost (Revised) in Rs Crore The project cost, if different from the cost as per original estimates
Not Available
Project Cost(Actual) in Rs Crore Actual cost of the project
Not Applicable
# - The project may have additional details that are pertinent. Kindly check the 'Any Other Information' field for further details.