Captive Power (Angul) Project - Unit VII
Project Brief
Installation of a single 120 MW coal based unit (7th unit) to increase the power generation capacity to 840 MW.
Sector
Energy
Sub-Sector
Electricity generation (grid)
Project Capacity
120.0 MW (Mega Watt)
Location The geographical location of the project
Odisha
Project Status
Completed
Government/Non Government A government project pertains to project implemented either through traditional procurement mode or through PPP mode. A non-government project pertains to a project implemented solely by private sector.
Government
Any Other Information Any other relevant information for the project
Not Available

Name Of Authority Name of the government agency that is the implementing authority for the project
Name Of Authority
National Aluminium Company Limited
Project Contractor Name of the concessionaire executing the project along with contact details such as name of the person, address, email, phone, fax, etc.
Name Of Contractor
National Aluminium Co. Ltd.
Project Timelines
Date Of Award Of Project The date on which the work order/notice to proceed was issued by the project authority to the developer
Not Available
Date Of Project Completion(Actual)
Not Available
Date Of Project Completion(as per Contract)
Not Available
Project Cost
Project Cost (as per Contract) in Rs Crore
Not Available
Project Cost (Revised) in Rs Crore The project cost, if different from the cost as per original estimates
Not Available
Project Cost(Actual) in Rs Crore Actual cost of the project
267.00